Good morning all, James Palmer here and thanks for joining this 29 Metals update for the September quarter for 2024. Today we'll be speaking to the presentation released this morning alongside our September quarter report and joining me here are Ed Cooney, our Chief Operating Officer, Peter Herbert, our Chief Financial Officer and Christian Steller, our Group Executive, Corporate Development. Look, it's great to be speaking with you all again today to talk through what was a great quarter of delivery by the team, a quarter that moves us closer to our 2024 objectives and beyond. Pausing on slide three before we get into the quarter results, just highlights again the 29 Metals investment proposition, specifically large Australian-based copper endowments, lots of upside potential. Slide four lays out our key 2024 priorities, and they remain the same as when I spoke to you three months ago. Health and safety first, always, and across the group discipline in productivity and in cost improvements, with some great wins by the team on this front during the quarter. At Golden Grove, it's all about the drumbeat of delivery to maximise free cash flow and moving towards a final investment decision at Gossan Valley. At Capricorn Copper, it's all about the imperatives for a sustainable restart, with water reduction the immediate focus. Slide five shows a summary of the September quarter. On safety, our TRIF slightly up over the quarter, and we remain focused on safety as our number one priority. Operationally, it was a strong water delivered by the team at Golden Grove, producing 4.4 kilotons of copper and 19.1 kilotons of zinc, positioning us well to deliver our full-year metal production guidance. In addition, the asset generated $42 million of operating cash flow and $26 million of free cash, so a great result. At Capricorn Copper, really pleasing progress was made towards our immediate-term focus of reducing water levels on site with the team progressing the things within our control to position the asset for optimal water reduction in the coming wet season. Specifically commencing treatment of the water in the Mill Creek Dam in preparedness for controlled treated water releases during the wet season was a major milestone for the quarter. So I'll now pass to Ed to talk through Golden Grove in some additional detail. I'll then provide an update on Capricorn Copper prior to Peter providing a corporate and finance update for the quarter. So over to you, Ed.

speaker
Ed Cooney
Chief Operating Officer

Thanks, James, and morning, everyone. So moving on to slide seven, as James mentioned, a great quarter delivered by the team at Golden Grove, producing 4.4 kilotons of copper and 19.1 kilotons of zinc, positioning us well to deliver our four-year metal production guidance. As foreshadowed in the June quarter report, higher zinc production in the second half of this year is being enabled by paste filling completed earlier in the year and progress of Xantho extended development advance, providing access to high-grade ore through the second half of the year. And from the chart on the top right-hand side of the screen, you can see the proportion of Xantho extended ore at circa 50% for the last two quarters. To this end, 9.1 kilotons of zinc production during the quarter was about a 300% uplift versus the March quarter and a 25% uplift versus the June quarter. Zinc grade milled was 6.3% versus 4.8% the prior quarter, with the higher feed grade increasing zinc recovery from 83% to 85%. Copper production is also tracking well year-to-date with production of 4.4 kilotons during the quarter, which puts our year-to-date copper production at 16.6 kilotons and positioning us well relative to the full-year guidance range of 18 to 22 kilotons. Development at Zanzo extended continues at rates to enable full-year metal production guidance. with lower quarter-on-quarter development at Xantho extended of approximately 700 metres versus the June quarter of a bit over 900 metres. And that was reflective of lower planned activity as we established the next sub-level of fresh air infrastructure within the lower levels at Xantho extended. So moving on to slide eight and another pleasing quarter for unit costs. with C1 costs and all in sustaining costs of $2.52 and $3.42 per pound US of copper sold respectively. Marginally higher quarter on quarter absolute site costs were driven by a planned eight day extended shutdown during the quarter and some additional required maintenance expenditures. The quarter-on-quarter increase in unit costs was primarily due to reversal of the stockpile movement credit from the June quarter of $33 million to a $21 million charge, and increased treatment charges linked to the higher zinc sale volumes and recent strength in the zinc price, given the link to the zinc treatment charge escalator associated with pre-IPO offtake agreements. Impacts of stockpile movements and treatment charges were partially offset by higher byproducts during the quarter. Moving on to slide nine and activity associated with the capital expenditure on the TSF4 project really ramped up during the quarter and final key approval from the Department of Water and Environmental Regulation required for completion of construction is also now in hand. The photos on slide 9 show the excellent progress being made on the project and hopefully you can get some context of the scale of the facility. The project remains on track for completion in Q1 of 2025. And owing to its scale and thickened tailings deposition methodology, TSF4 is expected to enable lower deposition costs over the life of the mine. In addition, the upfront investment in long-term tailings capacity is really expected to de-risk future tailings permitting requirements as compared to the incremental approach of building stage lifts on smaller facilities adopted at Golden Grove in prior years. Next on slide 10, production efficiency initiatives continue to be a major focus for the team at Golden Grove and indeed across the business. Working closely with our contract partners on site, productivity initiatives to increase metal production and reduce unit production costs have been a key focus through the year. A couple of recent wins on this front are shown, specifically the BlastIQ project, which actually won an award at the recent Australian Mining 2024 Prospect Awards and enables digital reporting, analytics and information sharing between underground operators and production engineers. And the implementation of some 3D standard drive scanning technology. So these are really two further examples of leveraging the fibre optic backbone that we installed underground in 2023 to really have faster work cycles, increased mobile fleet availability and improved safety. And turning to slide 11. We continue to progress Scotland Valley towards a final investment decision with works during the quarter really focused on review of outcomes from geotechnical assessments of both box cut and raised bore locations, receipt and analysis of surface infrastructure and underground mining tenders and refinement of the economic model. Gossam Valley to date has been drilled from surface, but history certainly shows that mining fronts at Golden Grove tend to grow over time, and the team are very excited about the prospect of getting underground and the opportunity of really testing the extent of known minimisation. Upon development, Gossam Valley is expected to enhance overall ore production and scheduling flexibility by providing an additional independent and relatively shallow production front at Golden Grove. I'll hand back to you, James, to talk through Capricorn copper.

speaker
James Palmer
CEO

Great. Thanks, Ed. Yeah, some real highlights there at Golden Grove. So in Capricorn, yeah, reduction of water levels on site remains the immediate focus. As outlined post the June quarter, controlled release of treated water is required to rebase site water levels in the nearer term and to effectively manage potential future high rainfall wet seasons. Treated water releases are of course subject to flow rates in Gunpowder Creek, with flows to facilitate the controlled releases typically occurring during the wet season, which is between November through April, so almost upon us. Given the volume of water on site, meaningful water reduction is likely to take more than one wet season. The significant investment made year to date to optimise controlled street of water release outcomes ahead of the 24-25 wet season and beyond, it's important to stress that that investment made enables a step change in the site's treatment and release capability compared to last wet season. Specifically, the Mill Creek Dam, or MCD, water treatment and release infrastructure and the refurbishment of the lime slaking plant now enables treatment of water in the MCD via water circulation and inline lime dosing and the controlled release of pre-treated water directly from the MCD to Gunpowder Creek. This provides a tenfold uplift versus achievable water release flow rates during the 23-24 wet season. To this end, commencement of lime dosing of water in the MCD using the new water treatment infrastructure was a significant milestone during the quarter and positions the team really well for optimal treated water release over the coming wet season. With this significant investment in water treatment and release capability, we're confident of being ready for water release when the creek flows begin. In addition, applications to amend the existing EA have been submitted and are being assessed by the regulator. And while this process continues, in parallel, we're working with the regulator to secure an acceptable interim mechanism to streamline water release outcomes for the 24-25 wet season. Commissioning of the repurposed processing plant as an interim water treatment plant commenced post quarter end adding to the big list of wins the team had for the quarter. As we release water from the MCD we'll be able to use the repurposed processing plant to treat water from EPIT to refill the MCD for further controlled treated water releases. We expect this to be a more efficient process as opposed to refilling the MCD with water from EPIT and solely treating it with the MCD infrastructure, or as per last wet season, treating the water from EPIT via lime dosing in ponds three and four. So either way, a step change from last wet season. Looking beyond the immediate reduction of water levels, a new water treatment plant as a long-term water solution and life of mine tailings capacity are the other imperatives for a future successful and sustainable restart of operations at Capricorn Copper. Although not the immediate focus, progress continued to be made on both fronts during the quarter and detailed design for a new water treatment plant progressed and multiple tailings options continue to be assessed to maintain optionality. On slide 14 the picture on the left shows the in progress treatment of water in the Mill Creek Dam in preparedness for controlled treated water releases during the wet season. You can see the bulk treatment and release infrastructure on the bank of the MCD there in the middle of the picture, which is taking water from the dam, dosing it with lime, then circulating it back into the dam. On the right mechanical evaporators working at EPET where onsite water inventory was reduced from 3.7 to 3.5 gigalitres via this mechanical and natural evaporation during the quarter. On slide 15 you can see the vehicle shown in the plan view photos of the bulk treatment and release infrastructure and the enhanced diversion dam photos showing the scale of the projects undertaken to date which can be difficult to appreciate when not on site. All of this investment puts the asset on a fundamentally better footing from an environmental compliance and water management perspective and provides a step change in the capability to manage high rainfall wet seasons and achieve meaningful wet season releases to reduce the water levels onsite. Now slide 16 shows the good drill results received at the beginning of the quarter, but more broadly talks to the significant value unlocked at Capricorn Copper once we deal with the water. So shiny core and big copper intervals aside, the great thing about these drill results is the team were able to confirm continuity and orientation of a new mineralised zone east of the portal fault in an area previously thought to be unmineralised. So in that area, previously thought to be unmineralised, we now have results like 45 metres at 2.5% copper, 36 metres at 3.9% copper, within a broader zone of 228 metres at 1.2% copper. So very mineralised as it turns out. All of these results around an existing 64.8 billion tonne resource with established development and infrastructure both on the ground and on the surface. All look at a 1,900 square kilometre land position within the highly prospective Mount Aussie environment. So there's lots of copper there. We just need to take care of the water issue so we can sustainably and successfully start operations and unlock the value of that copper in the ground. So with that, I'll hand over to Peter to provide a finance and corporate overview of the September quarter. Peter.

speaker
Peter Herbert
Chief Financial Officer

Thank you, James. On slide 18, I'll start with our revenue outcomes for the quarter. 29 Metals unaudited revenue of $177 million for the September quarter was an increase of 39% on the prior quarter result. This was driven by a 52% increase in sales at Golden Grove, offset by the reduced sales at Capricorn Copper post-suspension of operations. Golden Grove's higher revenues reflect increased sales volumes of copper, zinc and gold quarter on quarter. Copper as a percentage of total revenue was 47%, a decrease on the prior quarter result of approximately 50% reflecting the runoff of production and sales of Capricorn copper in the prior quarter and a greater proportion of zinc and gold by-product revenue in Golden Grove sales. The strong sales result for the quarter resulted in Golden Grove generating $42 million of operating cash flow and $26 million of free cash flow for the quarter. Cash outflows at Capricorn Copper were $23 million with investment in water management capabilities and environmental compliance projects ahead of the 2024 wet season. Outflows are expected to continue to reduce through 2025 as these projects are completed and operating costs are reduced to reflect lower steady state activity levels. Reduction of cash outflows during the production suspension period at Capricorn Copper remains a focus. To this end, the power supply agreement at the site was varied from 12 megawatts to 5 megawatts, effective from July 2024, reducing fixed power supply costs. Additionally, trucking of stockpiles to Mount Isa for processing and sale commenced post the end of the quarter. Corporate cash flows for the quarter included stamp duty instalment payments in connection with the 2021 IPO-related acquisition of Golden Grove. Installment payments commence from the beginning of the September quarter. The $27 million stamp duty amount plus interest is payable in 12 equal installments. Additionally, 29 MLS continue to amortise senior liabilities with a further US $2.5 million principal repayment plus interest during the quarter. Progress was made on the insurance relating to the loss and damage suffered as a result of the extreme weather event at Capricorn Copper in March 2023 during and post quarter end. 29 Metals and insurers are advancing discussions seeking settlement of the service component of the claim and pushing for that on a basis as soon as possible. 29 Metals finished the quarter with unaudited available liquidity of $104 million, consisting of $60 million of cash and under an offtake facility amounted to US $30 million. This compares to available liquidity of $130 million at the end of the June quarter. Thank you very much, everyone, and back to you, James.

speaker
James Palmer
CEO

Great. Thanks, Peter. Thanks, Ed. So as we spoke to on slide four, in closing, the team and I understand the immediate priorities for the business for the rest of 2024 and are making good progress. We must continue to focus on safe, sustainable improvement in productivity and disciplined cost management across the business. We must continue the drum-headed delivery that Golden Grove is establishing now that we're firmly into Xantho extended to deliver guidance. And at Capricorn Copper, we must continue to manage our environmental responsibilities, manage costs and progress the imperatives for a sustainable restart of operations with the immediate priority and focus on reduction of water levels. And we must do all of this without ever compromising on our commitment to health, safety and wellbeing. So I'm looking forward to delivering another strong quarter to bring the year home and meeting many of you over the coming days, weeks and months. So with that, we're happy to take your questions.

speaker
Operator
Conference Operator

Thank you. If you would like to ask a question, please press star 1 on your telephone and wait for your name to be announced. If you'd like to cancel your request, please press star 2. If you are on a speakerphone, please pick up the handset to ask your question. Your first question today comes from Daniel Morgan from Baron Joey. Please go ahead.

speaker
Daniel Morgan
Analyst, Barrenjoey

Good morning. My first question just relates to tailings dam 4 at Golden Grove. Good to see it's approved and in execution. I'd just like to get a greater understanding of if you can in any way quantify the benefit to your go-forward operating costs versus, say, a 2024 baseline. You know, dollar millions perhaps. I just want to get some understanding of what the benefit is from a better tailing solution. Thank you.

speaker
Ed Cooney
Chief Operating Officer

Oh, you go, Ed. Yeah, great. Go. Thanks, Daniel. I'll take that one, Ed. Maybe I'll start from capital intensity. So our TSF3, the lift that we're currently depositing into, that was about an $8 million capital investment for two years' capacity. This facility is sort of circa $30 million for a... you know, broadly 10 to 15 year mine life. So from a, I guess from a capital intensity perspective, that's probably a 20 to 30% reduction per cubic metre of capacity. In terms of operating costs, that's probably a little bit trickier to answer. I'll probably respond by saying qualitatively it's a much lower risk facility by its very nature, being thickened tailings. So you don't have the same level of systems of governance, which will enable the operations team to be sort of freed up and focus on other productive activities. but hopefully that gives you some flavour for the benefits.

speaker
Daniel Morgan
Analyst, Barrenjoey

Yeah, thank you. Second question is, can I just understand the stockpiles available a bit better at the end of the quarter? I mean, if I look at Q2, for example, it looked like you had about 3,000 tonnes of copper and 5,000 tonnes of zinc. At that time, you produced but had not sold in that quarter. And then I look at this quarter... And it appears to me that 2,000 tons of that 3,000 tons was unwound, but a negligible amount of the zinc. My point here is, you know, can you just outline, I guess, a potential cash flow or working capital benefit or unwind at some point in the future? Thank you.

speaker
Peter Herbert
Chief Financial Officer

Thanks very much. I'll take that one. It's Peter here. We had a, I mean, in terms of sales for the quarter, we did have, you know, good volumes, you know, go out the door. So we would see that stockpiles, you know, largely, you know, normalised, you know, quarter on quarter. There's obviously always some left, but, you know, we did do a good job of, you know, making shipments and you see that reflected. you know, in the strong cash flows for the quarter. I think, you know, our focus, you know, for here going forward, Golden Grove, is to, you know, maintain that, you know, good proportion of Xantho extended or coming into the phase so that we can, you know, keep that run rate up in terms of production and sales, you know, and make that as consistent as possible, you know, quarter on quarter, which is always, you know, always the challenge and the opportunity for a business like Golden Grove.

speaker
Daniel Morgan
Analyst, Barrenjoey

Okay, thank you. Question just on your copper concentrate terms. I'm talking about TCRCs here. Are you linked to benchmark prices? I'm just trying to understand if you might soon benefit from a reduction in TCRCs in 2025 at face value.

speaker
Peter Herbert
Chief Financial Officer

Yeah, they are linked to benchmark. And so you don't see an immediate reduction until that renegotiation of terms happens on an annual basis. So it's always difficult to predict you know, how that moves. Obviously, spot prices are, you know, indicative but not, you know, determinative of where the market's going. So, yes, as we see those contracts come up for renewal and that negotiation process conclude, we'll see that flowing through, whether that be positive or negative. We always watch with interest, of course.

speaker
Daniel Morgan
Analyst, Barrenjoey

And last question, if I may, just are you in discussions or negotiations with lenders regarding a revised debt facility or facilities. Thank you.

speaker
Peter Herbert
Chief Financial Officer

Yeah, thanks, Dan. I think when we look at our facilities at the moment, and I think we've been, you know, relatively, you know, clear on this in the past, is that these were put in place in 2021. And, you know, since then, the business has changed, you know, significantly in terms of the events at Capricorn Copper. But also, you know, as we look forward to, you know, new opportunities for the business, you know, whether that be Gossam Valley or other, you know, growth opportunities, we want to make sure the balance sheet is in the right place to support those initiatives. Our engagement with lenders continues to be strong. We speak with them regularly and we're starting to speak to them about, you know, what the profile of the business should be as we go forward so we can accommodate, you know, our objectives and priorities, you know, as a business. So, yes, we're starting those discussions, Daniel. From a timing perspective, you know, we would see the next, you know... key milestone in terms of that senior debt profile to be the step down in October next year of the working capital facility, which is the thing that sort of drives us. That's not, you know, that's obviously not, you know, in the very near term, but, you know, we clearly want to get out of that, you know, as soon as we can.

speaker
Daniel Morgan
Analyst, Barrenjoey

Okay. Thank you very much, Johannes and Peter. Thank you.

speaker
Operator
Conference Operator

Thank you. Your next question comes from Alex Papiano from Citi. Please go ahead.

speaker
Alex Papiano
Analyst, Citi

Hi James and Peter. So the announcement noted progress made over the quarter on the surface insurance claim. Can you give some more colour on the progress that was made and potential size and timing of the outstanding claim?

speaker
Peter Herbert
Chief Financial Officer

Yeah sure. Peter again here. I'm happy to talk to that. Naturally discussions are of course pretty sensitive so I can't give a sense of the quantum but I'll try and do my best to talk to the kind of work that's happening in the background. For a bit of context, we're through the period of indemnity cover post the loss event in 2023, March 23 that is. To a large extent, we're talking about backwards looking information here and there's a lot of work to go through to sift through the detail of that and considerable effort from the teams on site and in supporting functions as well as from the loss adjusters and the insurers themselves. You know, that, you know, we've made really good progress on resolving, you know, much of the queries. And we, you know, we would see and assess that we're, you know, closer to the end of that process, certainly, you know, than the beginning and start to see and touch the finish line. So, you know, we're pushing hard. I think everybody... from all sides of that process, you know, concede that, you know, this is a long process and everybody's, you know, keen to draw it to a conclusion as quickly as possible. And, you know, frankly, we're encouraged by, you know, the efforts of everybody to try and reach that conclusion. So good progress being made. You know, we're hopeful to provide, you know, updates as soon as we can on what that looks like. But we'll wait and see what, you know, quantums are as we go through that, you know, that discussion process and conclude any outstanding queries.

speaker
Alex Papiano
Analyst, Citi

Yep, okay. In terms of the underground component, does full underground access need to be established for that claim to progress, or what's holding that claim from progressing further?

speaker
Peter Herbert
Chief Financial Officer

It's a question of policy and whether there's alignment on what's covered under the policy or not. It's not a question of the activity that the company is or isn't undertaking around that at present. It's more a case of whether the policy speaks to that, which I think we've disclosed in the past. So with the focus from our team and insurers is on advancing the service component of the claim. as being a piece that's not in dispute. So look, as that process draws to a conclusion, there'll be more focus on the bits that remain unresolved at that point. So that's the likely progression from here, and that should give you a sense of where our focus and effort is turned to at the moment.

speaker
Alex Papiano
Analyst, Citi

Yep, great. OK, thank you. I'll pass it on.

speaker
Operator
Conference Operator

Thank you. Your next question comes from Ben Lyons from Jarden.

speaker
Ben Lyons
Analyst, Jarden

Please go ahead. Oh, thanks. Thank you. Good morning, James, Peter, Ed. Just a couple of quick ones from me. Firstly, at Golden Grove, just observing some pretty significant variability in the development rates at Xantho Extended over the past few quarters. And that's probably consistent with the mine plan. But when you think about the sustainable development rate that's required to continue lifting that proportion of Xantho Extended ore that's in the mix, What sort of number do you think about on a monthly or quarterly basis for those development rates?

speaker
James Palmer
CEO

Yeah, Ben, I might... I'll throw it in for the detail on that, but just when you're asking that question, it was certainly one of the things that I was, you know, looking for and getting down into Xantho, just having a look at the progress the team have made. Again, really good progress, I think, as Ed covered in the outset there. It is as per plan because it's all around the ventilation as we do establish those new levels. So certainly, you know, making good progress and on the plan. Reducing the variability across the board is something that we're shooting for at Xanthope. And maybe Ed on some of the detail of Ben's question.

speaker
Ed Cooney
Chief Operating Officer

Yeah. Morning, Ben. Yeah, so Q3, we had anticipated some lower activity levels because we were setting up the next infrastructure at the lower levels. So we also probably did a bit more rehab in some of the operational areas of Gossam Hill and Sculls. But in terms of responding to your question, look, I think the race where we're at, you know, is where we need to be. You know, broadly, that might be sort of three to four kilometres per annum. That will drop off over the life of mine, though, I would say. But sort of near term, as long as we're maintaining those levels, you know, we should sustain the proportion of xantho ore in the mill feed.

speaker
Ben Lyons
Analyst, Jarden

Okay, awesome. Thanks for the detail, Ed. And just maybe more conceptually, now that you've got some additional development there at lower levels, what sort of constraints are you currently facing there? Is it still vent or is it your pace cycles or trucking? I know the bottleneck's probably constantly moving, but what's the current sort of constraint and challenge? Thanks.

speaker
Ed Cooney
Chief Operating Officer

Yeah, you're right. It'll be a mix. I mean, as we open up more stoves, you know, there'll always be pressure on backfill, Ben, just by nature of the stove sequence. So ensuring that we have the pace full into the voids in a timely manner will drive availability of the next available source. And ultimately, trucking at depth ventilation, you know, they're two key constraints. So We'll always look to see what we can do to, you know, improve that. There are enabling technologies on the horizon that we will look to explore, but ultimately, yeah, ventilation, trucking and paste-filled turnaround stoves are the keys.

speaker
Ben Lyons
Analyst, Jarden

OK, cool. Thanks, Ed. Maybe just quickly changing focus to Cap Copper. I think earlier this year, guidance was given for about $18 million of holding costs over the second half of the year. And just observing that $23 million was spent during the September quarter alone. Now, I might have missed an update between that March quarter, $18 million versus where we're currently at. But it seems like there's still a fair bit of cash outflow at Cap Copper as you're rehabbing. So just wondering what sort of level of cash outflow you're looking at in the December quarter. Thank you.

speaker
Peter Herbert
Chief Financial Officer

yeah thanks thanks ben so we um maybe just starting first uh we spent about 18 or 19 in terms of costs for the for the quarter and the cash outflows are 23 so a little bit of working capital unwind from the prior quarters In the German quarter, we did guide that expected costs for the rest of the year would be between $10 to $15 for capital costs and $20 to $22 for operating costs for the quarter. So that was... Sorry, the path of apologies. So we're sort of on track to be within that guidance in terms of the December spend if you take out the costing curve for this quarter. And what I can say is the focus at the moment is on, you know, reducing people, gear, contractors from site as the projects to get us ready for the wet season, you know, come to completion, you know, which they are in readiness for the 1st of November when the wet season officially starts. So that, you know, that number remains our guidance and we're comfortable with tracking, you know, inside of that range.

speaker
James Palmer
CEO

Yeah, and Peter, I might just, Ben, I'll just add one more. Again, just being on site, some of that, you can see, A, the work that the investment has bought us, and B, certainly from the previous time I was on site, you can just see the reduction in the project work, you know, just simple things like you'd count and that type of thing. So those costs certainly coming off.

speaker
Ben Lyons
Analyst, Jarden

Okay, that's really helpful. Thank you, James, Peter, Ed. Thank you. Thanks, Ben.

speaker
Operator
Conference Operator

Thank you. Your next question comes from Adam Baker from Macquarie. Please go ahead.

speaker
Adam Baker
Analyst, Macquarie

Good morning, James and team. Just on Gosselin Valley, can you remind us what's outstanding on the permitting there and are you going to be releasing an updated study to the market before proceeding with FIB, noting that the last study was in late 2022? Thanks.

speaker
Ed Cooney
Chief Operating Officer

In terms of the permitting, we submitted an application for that I remember in the March quarter. So we would anticipate hearing back from the department probably early in the new year. So that's timing in terms of permanent approval, works approval. In terms of updates, yeah, look, I mean, we've been out to tender. We've got pricing in, a bit more further work in terms of some of the technical supporting information. We will be updating with all those inputs in the future, yes.

speaker
Adam Baker
Analyst, Macquarie

Okay, so timing for potential optimization of the study would be, you know, first half in calendar 2025. Is that correct?

speaker
Ed Cooney
Chief Operating Officer

Probably earlier than that. I've got James bearing down on pushing me to get all that work completed. So, you know, it's currently work in progress. We're working as quickly as we can. Probably not in a position to guide when, but I would say it'll be sooner than what you indicated.

speaker
James Palmer
CEO

Yeah, it's one of those certainly being done, you know... Pushing the team. ..everything that I'll see to bear. It looks like a good project. We're certainly looking to bring that forward, not push it back.

speaker
Adam Baker
Analyst, Macquarie

Thanks for that. And maybe on Golden Grove and what you're seeing with the workforce there, I've seen a number of redundancies in the mining sector in different commodities over the last 12 months. Are you seeing it easier to get workers on site? Are you seeing some of those positions getting filled quicker? Just a quick comment around that, please.

speaker
Ed Cooney
Chief Operating Officer

Yeah, I'll take that one. I would say yes. You know, I think we've had some challenges over the year in terms of availability of labour from time to time, be that underground operators on trucks or, you know, securing technical professionals, but I think we're certainly on technical professionals well-placed at the moment and we are seeing a reprieve in terms of availability of operators. So, you know, always challenging, but I think at the moment, you know, we're probably positioned better than we have been over the calendar year. I'll pass it on.

speaker
Operator
Conference Operator

Thank you. Once again, if you would like to ask a question, please press star 1 on your telephone and we'll have your name to be announced. Your next question comes from Daniel Roden from Jefferies. Please go ahead.

speaker
Daniel Roden
Analyst, Jefferies

Good day, Tim. Good morning. Thanks for taking my question. I just wanted to better understand, I guess, some of the optionality at Capricorn Copper. maybe just walk us through again the timeline for the permitting development and operations of some tailings considerations. So which options have what timeframes on them and when can we expect those to be executed?

speaker
James Palmer
CEO

I'll take it from a high level and then hand to Ed for any additional detail. I mean the first thing is we've been making it really clear internally as well as externally and working with government regulators. It's all around releasing water. That is the critical path. So that's definitely been the focus of the team. But then the next two, as we said, watered fragment plant, yes, there's been some progression, but again, back to some of the how do we reduce holding costs, we're reducing work on those things that aren't critical part. long-term water treatment, and then long-term tailings. With the tailings, as we said last quarter, we've got the opportunity that the suspension brings us to have a look at other options. Obviously, we put that in the last quarter, TSF3 being the most mature, but actually we've got a couple other options there that could be lower cost, but they're less mature from a permitting perspective. But focus, you know, particularly when we're talking to anyone in government, coordinator generals or DESI or otherwise, it's all around releasing water in the wet season, which, you know, normally starts at the end of next week. But, Ed, anything you want to add?

speaker
Ed Cooney
Chief Operating Officer

I think the other comment I'd make is just in terms of the site water inventory, what we've said is we think it's likely it will be more than one wet season to get the site water balance to a level where we think supports restart of the operation. So hopefully that gives you an indication of timeline. And in that timeline, that enables us to, in parallel, progress options for tailings.

speaker
Daniel Roden
Analyst, Jefferies

Yeah, OK. I guess I'm just trying to look at it from the perspective of, you know, how much cash could you be able to build ahead of that? Because restarting the asset is going to take a fair amount of capital. So maybe what's the, you know, FY25 has been, sorry, calendar year 24 has been guided to, but 2025, like what's the normalised care and maintenance cost for cap copper not being in production?

speaker
Peter Herbert
Chief Financial Officer

We're going through the budgeting process at the moment for next year and beyond. What I'd say, what you're looking at the moment in terms of the spend rate is obviously investment to get the site ready to release water. To a large extent those are one-off investments and then that will be about maintaining the site through that and managing the water levels through that infrastructure. Certainly investment at the moment is high and we're looking to step that down as we go into 2025 but not in a position to give guidance on that at this stage.

speaker
Daniel Roden
Analyst, Jefferies

Just last one, the capital and copper stockpiles that are being maltreated. Can you just give an indication on maybe what the opportunities there in terms of like quantifying in terms of cash flows?

speaker
Peter Herbert
Chief Financial Officer

Yeah, I mean, to be clear, not huge. It's 40,000 tonnes of material at about 1.5% copper. So, you know, you can do some, you know, back-of-the-envelope caps as to what that could look like on a total trading basis. But, you know, think single-digit millions, you know, type of result here. It's not life-changing in that sense.

speaker
Daniel Roden
Analyst, Jefferies

OK, Norris, I'll pass it on. Thank you. Thanks, Daniel.

speaker
Operator
Conference Operator

Thank you. Your next question comes from David Radcliffe from Global Mining Research. Please go ahead.

speaker
David Radcliffe
Analyst, Global Mining Research

Hi, good morning, James and team. So my question is on Golden Grove. And when you look at the volumes, you need a strong current quarter to meet the low end of guidance for both ore mined and ore milled compared to that tonnage guidance you've got out there. So could you maybe talk to the confidence in achieving this and how the quarter started?

speaker
Ed Cooney
Chief Operating Officer

Yeah, so a couple of comments from me on that one. I guess, you know, as I alluded to earlier in terms of some of the operator availability challenges in the WA context, over the calendar year in terms of managing TKMs, you know, that's probably been a challenge for us in terms of moving the volumes. So we have focused the available TKMs on the highest grade material at depth, being Xantho extended. We also did incur some... remote loaders, welding stoves in the second quarter. But in terms of Q4, everything's going well in terms of delivery for the grain we need to produce the metal. I would say volumes on a full year basis are going to definitely be at the low end of the island's range.

speaker
David Radcliffe
Analyst, Global Mining Research

Okay, thanks. And then maybe as a follow-up, looking to next year's volumes, given that we're at the low end this year, and obviously you're anticipating Xanthoxan to step up, but do we still, something like approaching that 1.6 million rate that's been put out in the past is achievable in 2025?

speaker
Ed Cooney
Chief Operating Officer

Yeah, I mean, that will always be our aspirational target. I think last calendar year, being 2023, we probably achieved about 1.5 or a bit over 1.5, 1.55. It just depends on the various operational challenges that we encounter during the year, availability of people and the like, but that will always be our target to try and maximise volumes and keep them helpful.

speaker
David Radcliffe
Analyst, Global Mining Research

Alright, thank you. I'll pass it on.

speaker
Operator
Conference Operator

Thank you. Your next question comes from Timothy Hoff from Canaccord. Please go ahead.

speaker
Timothy Hoff
Analyst, Canaccord

Hi, Tim. Thanks for the question. I'm just looking to dive into the question around concentrate volumes that Dan was looking at before. I guess noting that you've opened up a new mining front at Xanthel Extended where you've got a big change in the constituents of ore. Have you seen any contaminants or deleterious elements that are impacting your concentrate qualities? Is that perhaps a read-through to your TCRCs that seem to have changed quite a bit this quarter?

speaker
Peter Herbert
Chief Financial Officer

No sense that there's any deleterious materials coming through impacting that. On the TCRCs, absolutely higher this quarter than the previous quarter. What you're seeing in TCRCs is a couple of things. a higher proportion of zinc in the sales mix, which typically attracts a higher TC. In addition, more sales went through the pre-IPO offtake contract where there is a link in the TC to the zinc price escalators. And so we've had strong continuing zinc prices, which has impacted those. So it's very much a function of existing contractual terms around offtake and a high production and sales of zinc during the quarter, nothing to do with the quality of the concentrate itself.

speaker
Timothy Hoff
Analyst, Canaccord

Excellent, thank you. And those pre-IPO off-takes, have they got a drop-dead date or do they roll off at any point?

speaker
Peter Herbert
Chief Financial Officer

Yeah, they're fixed tonnages. So we will be delivering 100,000 tonnes into that, you know, this year. And, you know, over the balance of the next two years, there's 140 left to go. The escalator does improve over the next... over that outlook period as well, so we would expect that, you know, holding price constant to be less as we go forward. But, yeah, that... So, yes, we would see that... that dropping down, and as we look to ramp up production and zinc overcoming use as well, it obviously becomes a lower proportion of the overall sales too.

speaker
Timothy Hoff
Analyst, Canaccord

Thanks very much, Ash.

speaker
Operator
Conference Operator

Thank you. Once again, if you would like to ask a question, please press star 1 on your telephone and wave your name to be announced. As there are no further questions at this time, I'll now hand back to Mr Palmer for any closing remarks.

speaker
James Palmer
CEO

Great, thank you. Yeah, well, thanks for the time. Thanks for the questions. From our side, yeah, another strong quarter of delivery delivered. And we certainly hit the ground running for this last quarter to bring home the year and deliver guidance. So I think you can see the potential for the next two years, 29 medals, to be quite different to the last two. So thanks. Have a safe and productive day.

speaker
Operator
Conference Operator

That does conclude our conference for today. Thank you for participating. You may now disconnect.

Disclaimer

This conference call transcript was computer generated and almost certianly contains errors. This transcript is provided for information purposes only.EarningsCall, LLC makes no representation about the accuracy of the aforementioned transcript, and you are cautioned not to place undue reliance on the information provided by the transcript.

-

-