This conference call transcript was computer generated and almost certianly contains errors. This transcript is provided for information purposes only.EarningsCall, LLC makes no representation about the accuracy of the aforementioned transcript, and you are cautioned not to place undue reliance on the information provided by the transcript.

Fervo Energy Company
11/9/2026
Greetings and welcome to Fervo's third quarter 2026 earnings conference call. At this time, all participants are in a listen-only mode. A brief question and answer session will follow the prepared remarks. As a reminder, this conference is being recorded. It is now my pleasure to introduce your host, Paxton Bentzinger, Senior Director of Corporate Development and Investor Relations. Please go ahead, sir.
Thank you. Good morning, everyone, and welcome to Fervo Energy's Q3 2026 earnings call. Joining us today are Tim Latimer, co-founder and chief executive officer, and David Ulrey, chief financial officer. Before we begin, I'd like to remind everyone that today's discussion will contain forward-looking statements within the meaning of applicable securities laws. These statements reflect management's current expectations and assumptions and involve known and unknown risks and uncertainties that could cause actual results to differ materially. Please refer to the forward-looking statements and risk factors disclosed in today's earnings release and in our filings with the SEC. Additionally, today's discussion may include certain non-GAAP financial measures. Reconciliation tables are provided in the appendix of the earnings release as applicable. Now over to Tim to kick things off.
Thank you, Paxton, and good morning, everyone. I'll start with the most important development of the quarter. Our first geoblock at Cape Station is in commercial operation, delivering power to the grid and generating revenue under our power purchase agreement. A few years ago, enhanced geothermal was an idea recently proven with a pilot that had just begun operating. Today, it is a 33-megawatt power plant, consistently delivering clean, firm electricity. When we last spoke in August, I said we'd judge our progress on four things. First, the strength of our pipelines. Second, how well and how quickly our modular approach serves customers. Third, our license to operate in the communities where we build. And fourth, our execution in the field. This quarter, we advanced on all four, and Cape Station is the clearest evidence. Cape Station's first geoblock is the first greenfield enhanced geothermal system development in the world to reach commercial operation, and it was built in just 23 months. It demonstrates that enhanced geothermal can deliver reliable, carbon-free power at utility scale. We firmly believe that integrating modularity and best-in-class continuous improvement into infrastructure construction will drive tighter delivery timelines, and we're proud to have taken the first step in delivering this promise by completing our first geoblock ahead of schedule. During this call, I'll elaborate on the startup of operations before turning to our recent PPA with Google. which we believe is the largest enhanced geothermal PPA signed to date. I'll also speak about continued operational success at Cape Station, policy tailwinds, and progress across our pipeline. Before we go further, I want to talk about safety. Nothing we build matters if we don't build it the right way. Our trailing 12-month total recordable incident rate now stands at 0.10, even as we scale up construction and operations at Cape Station. This quarter, our facility's construction crew also reached a major milestone. One million hours worked without a recordable incident. The men and women building our geoblocks do complex, demanding work, including work at heights, hot work, and exposure to the elements, so that reliable, clean energy can be built in America. We are deeply grateful for their efforts. One million hours without a recordable incident reflects the seriousness with which we approach this work and the tools and processes that let it be done safely. We've said that we want to show that you can be at the forefront of innovation and still lead in health, safety, and the environment. This milestone is strong evidence that innovation and safety can go hand in hand. Now, back to Cape Station. On September 30th, we declared commercial operation at our first geoblock ahead of our contractual deadline. We synchronized to the grid on September 24th, and today Geoblock 1 is generating revenue under its PPA. In just 23 months, we turned an empty plot of land into a fully operational power unit. This milestone sends a clear message to customers, utilities, regulators, and other developers. Enhanced geothermal is now delivering at utility scale. We took science and intellectual property validated at Project RED and built a 33-megawatt full-scale geoblock that is delivering on our PPA, supported by Project Finance, and we delivered it on time. We're still early in our overall K-Phase I operational life cycle, But while our pilot proved the building blocks of EGS, CAPE Phase 1 data is beginning to confirm the benefits of operating EGS at scale. Geoblock 1 is performing in line with our operational expectations, including both production performance and power delivered under our PPA. Said simply, brine is arriving to the power plant at the desired volume and temperature, and electricity is being sold to the plant. Geoblock 1 has given us the playbook. It has taught us about commissioning sequence, equipment and controls, contractor coordination, and regulatory approvals. We've run that playbook once, and now we run it repeatedly, improving each time we do. Geoblocks 2 and 3 are on track with the timeline we laid out during our IPO. Both have reached mechanical completion. Geoblock 2 has achieved grid sync, a major milestone which marks the end of hot commissioning. The plant is now in its tuning and early operations phase, exporting test energy to the grid. Geoblock 3 is close behind in cold commissioning, where we are testing the mechanical and electrical systems prior to introducing Brian. We continue to expect commercial operation for these geoblocks by January 1, 2027, which puts us on track to deliver approximately 100 megawatts of firm, clean power from FERBO's first three geoblocks by 2027. As we deploy our repeatable geoblock delivery model across other geoclusters, both in Utah and in other states, we expect efficiencies to compound in terms of both speed and cost. Over time, we are confident we can build and commission geoblocks in fewer than 18 months. This brings me to what we are now calling CAPE Google 400. Geoblocks four through 11, the next eight units from our factory model that will deliver to Google in 2028 under our recently signed PPA. These geoblocks are on track for mid-2028 delivery. Let me turn now to the details of that agreement. In September, we announced what we believe is the largest enhanced geothermal power purchase agreement signed to date. It is a 15-year take-or-pay agreement, meaning Google is committed to paying for this power irrespective of the Beaver County Data Center plans on terms that are fixed for the life of the contract. The agreement covers approximately 396 megawatts, delivered in four tranches of 99 megawatts each. with commercial operation targeted to begin in mid-2028 and the full set of geoblocks targeted to be online before the end of 2028. Construction is already underway and I will share that progress shortly. Beyond the 396 megawatts contracted, we also committed to offer Google an expansion option of approximately 600 megawatts, which would bring the total to one gigawatt. Let me explain how delivery works under this agreement because the structure is as important as the size. The signed 396 megawatts is the first layer, and it is initially grid connected. For Fervo, it is a firm, binding, and financeable contract that we can build against today, with parent guarantees from both Fervo and Alphabet behind it. For Google, we believe grid connectivity means the power they are buying has value regardless of how much of the power they consume, as Google can monetize the power in the broader market. That is the point of this structure. It lowers project on project risk, We built Cape Station on our schedule. Google can develop a potential data center on their schedule, and neither party is waiting on the other. The second layer, the 600 megawatt expansion option, is behind the meter. Unlike the 396 megawatts, which are grid connected, Vervo and Google are pursuing direct-to-load delivery for this expansion to the potential regional data center. This would be under Utah's SB 132, a framework that lets large load customers connect directly to new generation. with protections for existing ratepayers. Our joint work to seek regulatory approval is underway, and we'll share updates as this progresses. We are working on all of this with the same commitment to transparency and high-quality stakeholder engagement as we conduct with the rest of our business. Our partnership with Google adheres to the Geothermal Sustainable Development Act, the voluntary standards I spoke about last quarter. In October, we were at Google's community event in Millport High School, where 250 neighbors came to learn about the potential data center and ask questions. We are pleased with our progress to date, proud to partner with Google, and honored to operate in a community of engaged, invested citizens. Of course, everything we do comes back to execution in the field, so I will turn to construction. Work on Cape Google 400 continues on track across all eight 50 megawatt geoblocks, our standard design going forward. As I mentioned, we expect first power from these geoblocks in mid-2028, ramping to approximately 400 megawatts by the end of that year. Since last quarter's call, the first set of 50 megawatt turbines has passed factory acceptance tests, and we've accepted delivery of major equipment in line with our development plan, including recuperators and over 60% of all air-cooled condensants. On the subsurface side, we now have four H&P Flex 3 rigs running the Cape Station. Drilling for geoblocks 4 through 11 is approximately 18% complete. Our drilling results continue to improve as we drill more wells with our 3.0 design. Recall that our 3.0 design includes extending laterals to 7,500 feet, stepping up the lateral diameter to 8 and 5 eighths inch casing, and charging at an average reservoir temperature of 430 degrees Fahrenheit. Each of these changes results in more power capacity through higher flow rates and higher temperatures. Reducing costs and increasing production aren't the result of any single breakthrough. They're the result of intentional iterative improvements where small changes compound into large increases in productivity. Dissolvable plugs and a redesigned tow prep reduce completion time and complexity. Rotary steerable systems and insulated drill pipe allow us to reach deeper, hotter rock without slowing down. Procurement at scale is driving cost efficiencies on our surface equipment, where our ORC framework with Mitsubishi Heavy Industries through its Trevodan subsidiary provides better pricing and firm delivery timelines on the equipment at the heart of each geoblock. No single action will win the day on cost reduction, but what Fervo is demonstrating is that through our methodical approach to development and our dedication to continuous improvement, we continue to remove costs from the system. And as a result, we are positioned to achieve 5,500 per kilowatt of installed CapEx for geoblocks four through 11. Our long-term target remains at $3,000 per kilowatt. We maintain a keen focus on returns-oriented deployment of capital, where each dollar spent must justify its economic value. Last quarter, we spoke about using small amounts of capital toward this effort, and one area we've identified is that by pairing relatively small amounts of solar with our geoblocks to power our station auxiliary load, we increase the amount of high-value geothermal power that is available for sale under our PPAs. We expect to continue identifying opportunities like these, were through our repeatable approach, we drive costs down and improve returns. Next, I'd like to cover policy updates. We continue to see bipartisan support for geothermal at the federal level, support that has been notably broad and durable across administrations. The Department of Interior recently directed the Bureau of Land Management to allow certain early exploration activities with expedited approval. When we announced our 396 megawatt power purchase agreement with Google, Interior Secretary Burgum congratulated Google and Fervo, calling it, quote, a powerful example of how geothermal can deliver more reliable, affordable, secure, around-the-clock American energy, end quote. The Department of Energy further bolstered that support by selecting Fervo for two potential grants totaling approximately $20 million to support exploration drilling activities. Subject to finalizing definitive funding agreements, these awards would accelerate capital to evaluate prospects in Idaho and Nevada for full-scale enhanced geothermal development. The Idaho award is notable in that it would fund our first appraisal wells in that state, marking our entry into new geography for FERBO and giving us the opportunity to appraise new geothermal resources there with government support. In recognition of geothermal's extraordinary potential, Congress has taken action to advance impactful bills on permitting, commercial deployment, and R&D, all with broad bipartisan support. Next, let me step back and comment on our commercial pipeline. We now have 1,054 megawatts of binding power purchase agreements, representing approximately $11.9 billion of contracted revenue. With the addition of the Google PPA, that is an increase of 396 megawatts, or about 60% from last quarter. That binding backlog is only part of the picture. Beyond those signed agreements, we have an active pipeline of discussions across utilities, industrial customers, and hyperscalers. This broad demand reinforces just how acute the need for firm power that can be delivered quickly really is at this moment. Approximately 35% of those ongoing discussions are with utilities and load serving entities. 15% are with large load industrial buyers, and 50% are with data centers and hyperscalers. Our approach to power delivery will continue to blend front of the meter and behind the meter development. Grid-connected assets remain the foundation, though behind the meter gives customers a faster path to power when transmission timelines lag their need. Every one of our geoclusters is planned for eventual grid interconnection, so this isn't an either-or choice. It's about getting customers power as quickly as possible. Before I hand it over to David, I want to note that it's been just about six months since our IPO, And so it feels like a good opportunity to look at where we started versus where we stand today. We started with a three megawatt commercial pilot. Today, with our first geo block online at Cape Station, we have a total of 36 megawatts installed. We had 658 megawatts of contract power purchase agreements. And today we have 1,054 megawatts. And our revenue backlog has grown from 7.2 billion to roughly 11.9 billion. We raised our 2030 capacity target from 1 gigawatt to 1.1 gigawatts. We've grown our estimated resource potential from about 40 gigawatts to over 58 gigawatts. We've expanded our net geothermal leasehold portfolio from roughly 610,000 to 670,000 acres. And finally, we went from two drilling rigs to four. What hasn't changed is our conviction. When we rang the NASDAQ bell six months ago, We believe that the subsurface technology behind the shale revolution could unlock geothermal at enormous scale. That remains our belief today. Only now, we have a fully operational commercial asset and over a gigawatt of binding contracts to back it up. With that, I'll hand it over to David.
You're reading a preview of the FRVO Q3 2026 earnings call.
Free account.
Want transcripts like this in your own app? Try the Earnings call API, or read the transcript API docs.
Use this data in your own app
Pull this call's transcript, audio and slides with the Earnings call transcripts API.
See pricing