This conference call transcript was computer generated and almost certianly contains errors. This transcript is provided for information purposes only.EarningsCall, LLC makes no representation about the accuracy of the aforementioned transcript, and you are cautioned not to place undue reliance on the information provided by the transcript.

Cameco Corporation
7/31/2026
Thank you for standing by. This is the conference operator. Welcome to the Cameco Corporation second quarter 2026 results conference call. As a reminder, all participants are in a listen-only mode and the conference is being recorded. Following the introductory remarks, there will be an opportunity to ask questions. To join the question queue, you may press star then 1 on your telephone keypad. Should you need assistance during the conference call, you may reach an operator by pressing star and zero. Webcast participants are asked to wait until the Q&A session before submitting their questions, as the information they are looking for may be provided during the presentation. The Q&A session will conclude at 9 a.m. Eastern Time. I would now like to turn the conference over to Cory Kos, Vice President, Investor Relations. Please go ahead.
Thank you, operator, and good morning, everyone. Welcome to Cameco's second quarter 2026 conference call. I would like to acknowledge that we're speaking from our corporate office in Saskatoon, Saskatchewan, Canada, which is on Treaty 6 territory, the traditional territory of the Cree people and the homeland of the Métis. With us on today's call are Tim Gitzel, Chief Executive Officer, Grant Isaac, President and Chief Operating Officer, Heidi Shockey, Senior Vice President and Chief Financial Officer, Senior Vice President and Chief Corporate Officer, and Dominic Kieran, Global Managing Director of Cameco UK. Tim will provide some commentary to start the call and we will then open it up for your questions. Today's call will be approximately one hour, concluding at 9 a.m. Eastern Time. Our goal is always to be open and transparent with our communications, so if you do not have time to get into your questions during this call, or if you'd like to get into detailed financial modeling questions about the quarterly results, We'd be happy to respond and follow up to any inquiries. There are a few ways you can contact us with additional questions. You can reach out to the contacts provided in our news release, you can submit a question through the send us a message link in the invest section of our website, or you can use the ask a question form at the bottom of the webcast screen and we will be happy to follow up after the call. If you join the conference call through our website event page, there are slides available which will be displayed during the call. For your reference, our quarterly investor handout is also available for download in a PDF file on our website at Cameco.com. Today's conference call is open to all members of the investment community, including the media. During the Q&A session, please limit yourself to two questions and then return to the queue. Please note that this conference call will include forward-looking information, which is based on our current assumptions and actual results could differ materially. You should not rely on forward-looking statements and we do not plan to update them after this call except as required by law. For more information on the assumptions we've made and the risk factors involved, please see our most recent annual information form in MD&A. And with that, I will turn it over to Tim.
Well, thank you, Cory, and good morning, everyone. Thank you for joining us to discuss Cameco's second quarter and first half 2026 results. Well, the year is flying by. It's the middle of summer here in Saskatchewan, Canada, which is really the inflection point where people here have stopped complaining about the past cold winter and they start worrying about the upcoming cold winter. As we move past the halfway point of the year, I want to start by reinforcing the consistent message you've heard from us for a while now. Our strategy is built for long-term value creation. and our decisions and activities will be centered around that strategy. As a result, we are currently on track with our expectations for the year. Year to date, we've seen the support for nuclear energy not only growing, but becoming more tangible. Around the world, governments, utilities, energy intensive industries and the public are recognizing that nuclear energy is essential to energy security, National Security, Economic Competitiveness, and Decarbonization Objectives. We see that recognition translating into policy support, new build discussions, life extension decisions, up rates, fuel security initiatives, and improved public perception. Here in Canada, the federal government released its nuclear energy strategy in June. The strategy highlights the role that nuclear is expected to play in achieving national energy security and economic objectives while supporting emissions reduction. In the United States, the Department of Energy's conditional commitment to support deployment of AP1000 reactors is another very important indicator of the growing alignment between policy, proven and deployment-ready Gen 3 Plus technology, and the need to execute. We've said many times that the next phase of nuclear growth will be defined by delivery. Ambition matters, but execution is what brings megawatts into the grid and, important to us at Cameco, brings fuel requirements into the market. That's why we continue to believe that the value of proven technologies, experienced operators and established supply chains will be critical to the equation as the sector moves from aspiration to implementation. For Cameco, that alignment is very constructive. We are positioned across the nuclear fuel cycle with tier one uranium assets in stable jurisdictions, fuel services capabilities, strategic investments in Westinghouse and global laser enrichment, and strong long-term customer relationships built over decades. On the uranium and fuel market side, conditions continue to improve in the first half of the year. The long-term uranium price strengthened to decade highs and we saw increased on-market and off-market contracting activity. Customers continue to focus on security of supply with notable interest from both sovereign and commercial fuel buyers. At the same time, our contracting discipline remains one of our key competitive advantages. We continue to be patient and selective in committing supply. We layer in volumes where we see contracts that support our strategy and where we believe we can incorporate an appropriate level of downside protection with exposure to improving future market conditions. That discipline matters because sustainable supply does not simply appear because demand is growing. It requires long-term contracts to back long-term investments planned by capable and experienced operators. Over the next five years, we have contracts in place for average annual deliveries of more than 28 million pounds of uranium per year. And as the market continues to improve, we expect to continue layering in volumes that capture greater future upside. We continued on a positive contracting trajectory in Q2. However, quarterly results in our business will always reflect the normal variability of customer delivery schedules Product Mix and the timing of activity across the fuel cycle. The second quarter of 2026 was no exception. Our financial results were lower than the strong second quarter and first half that we reported last year, largely because 2025 included a significant contribution from Westinghouse related to its participation in the Dukovany reactor construction project in the Czech Republic. But looking past the impact of that payment, the underlying fundamentals of our business remain strong. A few of our outlook metrics changed as a result of the strength of the US dollar, which drove a change to our exchange rate assumption. Average realized prices continue to improve in both our uranium and fuel services segments, and our annual production outlook is unchanged. The unchanged 2026 plan calling for our share of production to be between 19.5 and 21.5 million pounds of U-308 is important. That's because to date in 2026, we've been reminded that safely operating complex, heavily regulated uranium mining and milling assets in remote Northern Saskatchewan is never without challenges. Spring road conditions affected Northern supply routes during the quarter, contributing to temporary unplanned operational disruptions at Key Lake and MacArthur River. and subsequent to quarter end, we also experienced operational challenges that had cigar lake production suspended for a couple of weeks. While we were able to address and overcome those unexpected developments with no impact on annual outlook, they were good reminders of why we have built flexibility into our supply strategy and why operating experience, risk management and credible teams matter so much in this industry. Our assets are world-class, but they are by no means simple assets. They require disciplined planning, technical capability, and constant attention to safety and reliability, and that's what our teams across the company bring to the table every day. During the quarter, we closed our agreement to increase our ownership interest in the Cigar Lake mine. The high-grade Cigar Lake mine is one of the most important uranium mines in the world, and increasing our interest reinforces our commitment to own and operate these scarce proven tier one assets that we expect will be essential in supporting the growth of nuclear energy. In our Westinghouse segment, performance in the first half was strong. As I said, once you look past the benefit that we realized related to the Duke of Oni project last year. As an operating business with deep exposure across the nuclear power value chain, Westinghouse is embedded in the day-to-day needs of the global nuclear industry while also being well positioned to drive the next wave of new nuclear capacity through its AP1000, AP300, and EVINCI technologies. New nuclear capacity creates long-term demand for uranium and conversion and fuel fabrication and related services. That's why Westinghouse is so strategically important to our broader growth thesis It gives us exposure to the full nuclear fuel cycle and to the technologies that can help shape the next era of nuclear deployment. So our message for the second half is straightforward. Our annual plan remains intact. The market continues to strengthen and Cameco's long-term strategic position is becoming even more compelling. We have flexible supply, a strong balance sheet, disciplined capital allocation, and decades of experience operating assets in jurisdictions that customers can rely on. We believe the risk to supply continue to outweigh the risk to demand and we are not prepared to dilute the value of our assets by committing supply into contracts that do not appropriately reflect the durability of market fundamentals. With tier one assets, strategic investments across the fuel and reactor life cycles, Strong customer relationships and a proven operating track record, Cameco is uniquely positioned to support the continued growth of nuclear energy while creating sustainable long-term value for our shareholders, customers, and communities. So thank you for your continued interest and support. Before moving to questions, I want to recognize Dominique Meunier, who has stepped down from Cameco's Board of Directors effective July 26, 2026, to focus on his other professional commitments. Mr. Meunier has served as a director since 2023 and has been a member of the Human Resources and Compensation Committee, the Technical Committee, and the Safety, Health, and Environment Committee since he joined the board. On behalf of the board and management team, I want to thank Dominic for his contributions to Cameco and we wish him continued success in his many pursuits. So with that operator, we are now ready to take questions.
We will now begin the question and answer session. In the interest of time, we ask that you limit yourself to one with one supplemental. If you have additional questions, you are welcome to rejoin the queue. To join the question queue, you may press star then one on your telephone keypad. You will hear a tone acknowledging your request. If you are using a speakerphone, please pick up your handset before pressing any keys. To withdraw your question, please press star then 2. Webcast participants are welcome to submit questions through the box at the bottom of the webcast frame. The Cameco Investor Relations team will follow up with you by email after the call. Once again, anyone on the conference call who wishes to ask a question may press star one at this time. The first question today comes from Brian Lee with Goldman Sachs. Please go ahead.
Hey, guys. Good morning. Thanks for taking the questions. Appreciate a lot of this AP1000 pipeline disclosure in the MDNA, so I wanted to ask first on that. You know, looking at this, it seems like the DOE process with the $17.5 billion loan funding from EDF, that's kind of toward the top of the stack in terms of timing potential. One, is that a fair characterization? And then two, can you describe kind of what milestones we could see on that process between now and, you know, let's say year end? And then what kind of engagement you're seeing from the utilities since that was launched or announced a few months ago? And I had to follow up.
Yeah, thanks a lot, Brian, for your question. We have our Global Managing Director, Dominic Kieran, here with us this morning. So I'm going to pass it over to Dominic to say a few words about Westinghouse. Dominic?
Tim, thank you. Good morning, everybody on the call. Good morning, Brian. So let me maybe just start with a comment that, as Tim mentioned, I'm very limited around what I can say about the offering that Westinghouse announced this morning. But Brian, let me get into your question. So in June 2026, Westinghouse announced the 17 and a half billion US dollars conditional commitment from the Department of Energy, energy dominance financing team. And this is really to facilitate the ordering of AP 1000 long lead items. And why is this important? Because this is a opportunity to really accelerate the deployment of AP-1000s in the U.S. So it's your specific question around what are the next steps that you can see. Well, the next steps are that we will move to definitive agreements and that is really the next step that you should be looking for is news from us about progressing to definitive agreements which will involve obviously specific utilities in the U.S., as well as the Department of Energy.
Brian, I should have mentioned as well that Dominic, as probably everyone knows, is the chair of the Westinghouse board. So I just wanted to put that into context. Grant's on the board, Heidi's on the board as well.
I appreciate the sensitivity around the different constituents involved. Fair enough. Second question, maybe just on the uranium segment. Pretty encouraging to see the realized uranium per pound ASP increased a good bit here. Curious, was that all because of the stronger market pricing or did that have anything to do with restructuring of contracts? And then how should we think about pricing the construct heading into next year? I know heading into 2026, your view had been mostly flat. So it's nice to see this uptick halfway through the year. Would this maybe not also be the sort of baseline to expect for trendline heading into next year as well? Just any thoughts there? Thank you. Thanks, Grant.
Yeah, Brian, the uranium side of the market continues to move from strength to strength. Just in general across the industry, I think what the most notable point to make is We are still not at replacement rate demand across the industry. We still don't have utilities coming forward and collectively buying at a volume that replaces what they consume under existing contracts. And yet we found ourselves back into a mid-90s long-term uranium price on its way to three digits likely. And that's in the absence of replacement rate demand. And as I remind folks, we've never been at this kind of uranium price on the front end of a uranium contracting cycle. We've only ever found ourselves at these prices on the back end. So this is really super constructive for the uranium space that on very little demand, that underlying long-term price continues to go up. And the reason for that is very simple. Utilities and those that are concerned about future production are starting to realize that they need to pay production economic prices to ensure that supply is there in the future. So that's a very good news story. Now, you spoke about our average realized price. Of course, that's derived from contracts we've already captured, from business that we've already captured, for deliveries that were just simply making, not new sales. And really, that increase in the price is a function of The contracts we're delivering into the stronger pricing in the market being reflected in the market related components, as well as some exchange rate effect, the strong US dollar relative to the Canadian dollar. But this is all part of our marketing strategy of being disciplined. Those old contracts are showing that upward leverage to the market that we said they would. And new contracting going forward is being done in a very constructive, stronger pricing environment. and we're not even at replacement rate contracting yet. It's a very exciting segment.
All right. Thanks for all the call. I appreciate it. Thank you, Brian.
The next question comes from Oris Waukadao with Scotiabank. Please go ahead.
Hi. Good morning. Question around this disclosure. around the form S-1 with respect to potential IPO for Westinghouse. I realize there's not a lot you can say, but could you give us some idea of the strategic rationale for this? Is this sort of should we think about it as getting a market value for the business outside of Canoco and Brookfield, or is this about the partners not having to put cash into the business in order to fund all the growth that's ahead of it? Just curious how to think about this.
Yeah, worst, you know, consistent with the USSEC rules governing the process, we are extremely limited in what we can say about the offering at this time. So I just we just can't provide any additional information on that.
Okay.
Okay, maybe shifting gears. Grant, could you please give us an update just where current market terms are with respect to contracting in terms of Floors and Ceilings. And with the term price having perked up this year, I'm just curious if we're also seeing ceilings move out for new contracts. Thanks.
There continues to be upward movement in the floors and the ceilings. Certainly, as we look to respond to utilities either on market or off market or you're familiar and I think most people listening are familiar that there's the two components of the term contracting market what shows up in RFPs and then what shows up bilaterally or exclusively and we call that off market. From our perspective when you look at this overwhelmingly favorable supply demand dynamic where you have a very durable demand building over 3 billion pounds of uranium that needs to be bought to run reactors on a requirements basis against a supply stack that is actually increasingly uncertain. Uncertain in terms of the depletion of existing assets, uncertain in terms of the restarts of existing assets that have been shut down and of course Promises of Greenfield, which seem to be sliding sideways, if not backwards. That's all very favorable for that supply-demand dynamic. And what it suggests is that there should be upward pressure on that pricing dynamic. And we just talked about it with respect to Brian's question on the underlying long-term price. Of course, when you think about market-related contracts, they don't reference the long-term price, but they generally have collars around them, floors and ceilings. as you've talked about. And we are seeing the floors and ceilings increase commensurate with that underlying long-term price. I think it's not unusual to see market-related contracts now where floor prices are in the high 70s escalated and where ceiling prices are 160 escalated. I can't speak for everybody. There still seems to be some in the market willing to try to discount floors and ceilings in order to win business, but that That's not what we do. We are in the business of being disciplined and looking forward to capture that long-term value with those utilities who have come to realize that security of supply is important. So as I said in my earlier answer, it is a very constructive uranium segment and it hasn't even discovered replacement rate contracting yet. And that is something that I think everybody on this call and looking at the uranium space should be focused on These are prices that we've never seen on the front end of a contracting cycle before.
Thanks, Orest.
The next question comes from Alexander Pierce with BMO. Please go ahead.
Great. Thank you. So in the spirit of continuing to ask questions that you may not be able to answer, Is it fair to assume that the timing going forward would probably the next step would come after finalization of the DOE and DSC agreements?
Alex, I have to go back again to our compliance with the SEC rules governing the process. We really can't say anything about that at this point.
Okay, I'll ask a more technical question then. So you pushed up cost guidance a little bit for this year. Is it possible to just break down how much of that cost change is due to kind of on-site maybe cost inflation, et cetera, or is there any of the cost change just because of the purchases you've made this quarter?
That's a good question that we can answer. I'm going to ask Heidi. Heidi Shockey, our CFO, would answer that one.
Hi there, Alex. The change in the cost going forward was really as a result of the impact of the foreign exchange, mainly on our purchases, as you noted. So it's, you know, any inflation we're seeing and whatnot would have been covered by the range and the big difference was really that FX rate.
Okay, thank you. Thanks, Alex.
The next question comes from Mohamed Faidabi with National. Please go ahead.
Good morning, Tim, and everyone else. Thanks for taking my question there. Appreciate the additional color provided on Westinghouse and the outlook there. So maybe just on the new pipeline, our global 81,000 pipeline outlook, or call it economics that you've shared with us, we call it the better share of revenue there. I was wondering if the 91 reactors pipeline included opportunities that you would take on with the Koreans, or if that excludes that category. Thank you.
Dominic, do you want to answer that?
Yeah, of course. Good morning. The pipeline, the 91 that we've sort of spelled out in our MDNA is very specifically focused on deployment of just the AP1000 technology. So we have not included in that any opportunities related to the Koreans deploying their technology globally. So that is, in addition, to our list of 91. That's great.
And maybe just a follow up to that on the second question. When you disclose the expected share of project value at 40 to 45%, is it something you expect to be consistently applied across jurisdictions or does it vary drastically between call it Europe, North America, or maybe the Middle East? Thank you.
Yeah, absolutely. Maybe let me just answer that with a little bit more detail around where we're at with the AP1000. So we talk a lot about EPC, to build reactors, engineering, procurement, construction. Of course, where we're really focused is on delivering a little bit of engineering that is site-specific engineering and the procurement of the parts to build the AP1000. So two comments on that, if I may. Firstly we're very unique in that we have a finalized design for our reactor and that allows us to have a very very specific and fixed scope of procurement. So to answer your question why we see real value and competitive advantage in the AP1000 is that there is no more design needed and therefore The procurement is fixed, which is the majority of that scope for Westinghouse that we've listed in the table. So in summary, we're expecting to see very similar percentages irrespective of what jurisdiction the AP1000 is deployed in.
Yeah, thanks so much for that, Colin. Thank you. Thanks, Marvin.
The next question comes from Bob Brackett with Bernstein Research. Please go ahead.
Good morning and thanks for all the Westinghouse disclosure again in the MD&A. I'd like to dig into the backlog numbers and new order numbers that you disclosed. But I think of that backlog as The amount of business pre-2025 that sort of flows through in sort of 10 years and then becomes revenue and that new order line that you talked about there is a significant step up and that was business gained in 2025. And can you talk, is that the new steady state for the level at which you're capturing business?
So, Bob, thanks for the question. Just you may hear in the background a beeping noise. We're just hearing an alarm, but we'll carry on until further notice. So, Dominic, over to you.
Yeah, absolutely. Bob, thanks for your question. So, maybe let me do it in reverse order. Let me talk about new orders entered. So, new orders entered, and this is a point in time at the end of last year, is the cumulative number of orders entered into within last year. Now, Those orders, some of those and the smaller percentage will have been executed and taken to revenue in the year. The larger percentage of those orders that have not been delivered on will enter backlog. So backlog then is at a point in time of December the 31st. How much contracted business does Westinghouse have for delivery and revenue recognition in the future? I hope that explains just what do we mean by backlog and new orders entered. Your second question was then are we expecting to see this as our steady state going forward? What I would just maybe just draw your attention to is when you look at the list of AP1000 pipelines, the 91 identified opportunities for AP1000. You can see many of those are in the future and we're at a pretty early stage with some of those projects. But while I can't give you any specific details on what we expect to happen to the backlog, I think what you can expect as we start to see the AP1000 being contracted and deployed, we are expecting to see a very positive trend on the backlog as we go forward through time.
Very clear. A quick follow-up on your end-of-a-kind unit economics for the AP1000. You've got a range for a two-pack of 14 to 17 billion US. Is that a conservative number? One could imagine that end-of-a-kind economics could be lower than that 14 billion. How do you think about the range of outcomes of that number?
Thank you for your question. I think the honest answer is it's pragmatic, right? We've given a range because it is pragmatic. And why am I being a little vague? Because some of this also depends on sort of jurisdiction. So if we think about countries that are going to deploy multiple units, we're probably at the bottom end of that range. Thank you. Thank you.
The next question comes from Lawson Winder with Bank of America. Please go ahead.
Thank you very much, operator. Good morning, Tim and Grant and team. I really appreciate the update and also echo those comments that I really appreciate the additional disclosure here on Westinghouse. When we look at the huge pipeline of 91 reactors, What percentage of those 91 units would you characterize as high probability opportunities? And then maybe being more specific on some of the different stages, like you have front-end engineering and design projects of around 11. If you look historically, what percentage of those more advanced discussions would typically convert to a full reactor build?
Dominic, please. Yeah, thank you. So thank you for your question. We have ordered the list in terms of how close the opportunities are to making what we call final investment decisions. And obviously, the closer you are to making a final investment decision, there's a couple of things to bear in mind, one of which is there's been considerable effort to get ready for a final investment decision. So a huge amount of work preparing for that. But obviously the probability increases as you get to final investment decision. We haven't put specific probabilities on the list because quite frankly, it's very, very difficult to estimate that. But let me make a couple of comments. If we go to the bottom of the list, so maybe some of our early stage opportunities that we've listed a number of countries there. It's not that we see them as lower probability, it's just that we see them as slightly earlier in the process of getting to a final investment decision. And the countries that are listed there, we are seeing very, very strong recognition of the need for nuclear in baseload energy generation. And some very, very common themes around the need for decarbonisation, The need for energy security, the need for a decent proportion of baseload power on these countries' grids, which gives us really quite a high degree of confidence we will convert a significant number of these opportunities into real projects and pass through a positive final investment decision. So we're not really in a position to give specific numbers, but I hope that gives a little bit of color as to how we think about these opportunities.
That is helpful, Dominic. Thank you very much. And then AP 300 and E Vinci. Again, the color there is very helpful. Obviously, a huge opportunity, particularly for the AP 300. But just how would you characterize the CapEx remaining for Westinghouse internally and the timeline for each of those two technologies to get to a commercial deployment level?
Absolutely. So let me start with the AP300. So just to be clear, what the AP300 is, is a scaled down version of our very proven AP1000 technology. And while this is, why do we think this is really unique and we're in a unique position is because we are basically taking the proven AP1000 technology and really just adapting it for those customers and those markets that are looking for a smaller reactor. So what does that mean? That means the capital needed to bring that AP300 technology to a final design ready for deployment is actually pretty modest. I think we've put the numbers in the EMDNA so that they're there to read. I mean, thereafter, of course, once you're into deployment, it is our Customers, our utilities, our government capex as we move into deployment of that. So I hope that explains the AP 300. As I say, we benefit from very, very modest amounts of capital. I'd say quite uniquely modest amounts of capital to finalize that design because of the pedigree of the AP 1000. And I would just draw your attention to this is not just about design. This is about ensuring there is a robust supply chain. for the delivery of these reactors. And of course, the AP300 has huge commonality with the AP1000 supply chain. On EVINCI, different technology. So this is what we call a generation four technology. And we're really focusing EVINCI, it is a much smaller reactor. It isn't 1.1, 1.2 gigawatts. It's not 330 gigawatts. It's in the small number of megawatts range. We're very focused at the moment on some opportunities with the US government and those opportunities currently are self-funding and what this presents us with is an opportunity to make decisions in the future to commit capital to these projects should we decide within our capital deployment process that they warrant additional capital.
Thanks, Dominic. That's very helpful. Thanks for the questions, Lawson.
The next question comes from George Eady with UBS. Please go ahead.
Hi, Tim. Just firstly on the duration piece for the AP1000, how does last month's DOE commitment change things? Has that sort of brought forward timelines much? Is that included sort of thoroughly in the 9 to 10 and 10 to 11 year guidance estimates?
Yeah, George, thank you. Good question. I mean, you will have read one of the purposes of last month's announcement is to really stand up the supply chain for AP1000 as it pertains to those items that are traditionally on the critical path. And so I think it's a very valid question. Is this really providing acceleration to these numbers? What we're really showing here in terms of the duration of the project, I think you can see that we've put in first projects, but also where we expect to get to with nth of a kind. We're expecting the first projects to include the LLI timelines. but what we're expecting is very quickly to get to Nth of a Kind very much supported by the announcement of the long lead item opportunity that we are working with the Department of Energy on.
Yeah okay so like I guess outside of sort of supply chain what is the biggest headwind to getting this in production like is it labour and getting the sites ready I guess if I take the Thank you. So maybe let's
Break the answer into a number of different buckets, if I may. So bucket number one is, go back to what I said earlier, do we have any design to do? Well, no, we have no design to do on the reactor. There is always some design to do around the sites, but because the design of the reactor is finished, the amount of design we need to do around the sites is not expected to be Significant for this technology. The second bucket is, are we well positioned to provide the P, the procurement part of EPC? And the answer is yes, we are. We're very focused to make sure that we have the processes and the suppliers to stand behind the numbers that are on this table. And maybe just go back to my comments about the long lead item opportunity in the US. And then finally, we're into sort of construction. and you will see from the list and construction can be seen as a bottleneck, but you can see on the list that a number of these reactors are being deployed in different countries around the world. So we don't have outside of the US a lot of perceived bottlenecks around construction. So back then really just to sort of summarize your question is, We have put this in because we have considered the risks around this. It is certainly not without risks, but we've been, we believe, prudent when we put this in as our view of what the potential future may look like.
Okay, yeah, that's super helpful. Thank you.
Thank you, George.
The next question comes from Andrew Wong with RBC Capital Markets. Please go ahead.
Hey, good morning. Just wanted to ask, with the USDOE loan programs that are available for the loan lien items, could that be combined in the future with the $80 billion initiative from the DOC? Because it looks like those two programs could be really complementary to each other.
Yeah, Andrew, that's probably a question for the U.S. government more than it is for us. At the moment, we treat them as two parallel projects. The DOE had a particular focus on standing up the American nuclear supply chain. That is at the heart of the long lead item program that Dominic had just explained. The Department of Commerce, you'll recall, was a different driver. That driver was to accelerate the deployment of AP-1000s really by harnessing foreign direct investment pledged in the United States. Right now, they are different projects on different tracks. If they are combined, that would be under the direction of the US government. I guess the point is, the reason it adds to 20 reactors is because the demand for baseload 24-hour carbon-free power is massive. And so combining them and only settling with 10 reactors would not even begin to satisfy the demand that the U.S. government is seeing and trying to be in front of. So we'll watch it very closely, but at the moment, they're two separate programs run by two separate departments and both represent a very exciting opportunity for AP1000s as reflected in the updates that we put in the MD&A.
Okay, for sure. Yeah, I mean, I was just thinking complementary programs, so it's good to get to enter the kind as fast as possible with both programs that they work together. Regarding, I want to ask about conversion.
Andrew, just on that point, Dominic made this reference, and maybe we'll just put a finer point on it. Whether it's the DOE or the DOC moving forward or all of the programs that you see in the list of 91, it is essential to capture those three S's that we've talked about. We need to standardize and we've standardized to a common design. The AP1000 has a unique competitive advantage as articulated in the MDNA because it's design ready, it's fuel ready, it's licensed, it's regulatory ready, and it's been deployed. So the standardization has been checked. I think what you were referring to was the second S, which is sequence. And it is important that you sequence properly so that these programs are complementary, so that you're not standing up a skilled or a trade workforce and they're all competing with each other at the same time. So standardized sequence. And of course, the third S we always talk about is simplify, which doesn't mean change the design. It means learn the lessons that have come before. and that is the key of good industrial practices to get to that nth of a kind as quickly as possible. So to your point, I agree with you and I hope it didn't sound like I was dismissing it. They are complimentary as long as we are standardizing sequencing and simplifying. The two programs are different, but if we follow those three S's of good industrial practice, nobody needs to fear nuclear new build. In fact, we need to embrace it in a much more aggressive way than we have.
Yeah, that's great. Much appreciated. Maybe just wanted to ask about actually conversion enrichment prices as well. We've seen plans for new supply of both that's set to come on over the next, let's say, five years or so. But when we look at prices for conversion enrichment, they haven't really come down even with the new supply announcement. So I was just curious what you make of that. Why do you think that's the case? And What kind of takeaways would you say that that could imply for the uranium markets?
I think we've talked about a lot, but I'll just remind everybody on the call that you generally buy nuclear fuel backwards. You start with how many fuel bundles do you have, and if you need more, you then go to the fabricator to secure the service, and then You go to the enricher, the converter, and uranium. And we've always talked about if you want to know where uranium is going, just look at what's happening downstream. And downstream, you're right in pointing out very strong pricing in fabrication, enrichment, and conversion. And obviously strong pricing brings the promise of new supply. But I think what you're seeing in market pricing is the utilities themselves are being very clear-eyed about some of these promises. and so if it's an incumbent in Richard for example doing an expansion at a brownfield facility well that's going to have a high probability of success but when it's somebody who's never been in the business before with an unknown technology promising new supply those tend to be doubted by the utilities that have to count on that and don't want to take on that risk so I think the fact that there's been a lot of announcements but prices remain strong is just simply as fuel buyers go into security of supply mode, they are going to be very clear-eyed about who's making those promises. They're going to look at their track record and they're just going to discount some of those promises, especially the new ones on the conversion side. And those that are proven in the business will be the primary beneficiary of the higher prices. That includes Cameco.
Much appreciated, thank you.
Thanks, Andrew.
The next question comes from Brian McArthur with Raymond James. Please go ahead.
Good morning, and thank you for taking my questions. And again, maybe it falls under the category you can't answer, but I just want to check that there's nothing changed in the partnership with the U.S. government. If you do an IPO, they had an option if they invested to... participated in that IPO. Has any of that changed at the timing of this changes?
I'll just open and then I'll pass it to Grant, but I'll just say that, of course, we're restricted from discussing this, but I'll tell you that we in Brookfield control Westinghouse today and we don't expect that to change, so Grant.
Brian, the only reminder is if you go back to that announcement about the partnership with the Department of Commerce from last fall, it had... two important vesting conditions in it. And the first vesting condition was that it was the responsibility of the Department of Commerce to arrange financing of a minimum $80 billion to support the development of AP1000. So that has not changed. That would be the trigger that we would look for under that participation interest. That has not changed.
Yeah, that's sort of what I was trying to read through here, but I'll leave it at that. Second question, can I just make sure I'm understanding this chart right, which again, thank you for all the Westinghouse information, but in simple terms, you talk about concrete minus three, it looks like you get 10% of the value on a AP 1000, we're talking 8 billion, let's call it 800 million, the Westinghouse, and then you get a margin of EBITDA margin of 20%. Am I reading the combination of those two charts properly? and again, I suspect those are averages, so it may be different on a reactor basis. Is that a fair comment, Dominic?
Yeah, Brian. Yeah, thanks for the question. So the way to read the chart is the total sort of cash flow spend, which if you refer to the table, we're saying for what we call a pair, a twin pack is between 20 and 26 billion. That's the total spend, and you can see the difference there between effectively near-term build and end-of-the-kind, reflecting that end-of-the-kind, we incorporate all the learnings, which means we can go faster on the build, so higher spend sooner. So to that total spend, you then apply the Westinghouse share of that, which is circa the sort of 40% to 45%. and then to that you apply the typical corporate EBITDA margins that we've put on the table.
Right, and then if I look at the next chart where you show these lines where it looks like, you know, if I just use not a current one, it looks like, you know, at T minus four, you know, you have zero if I'm reading this right and then at T minus two, looks like I get 20%. So I'd book 20% of that You know, if it's $8 billion for a AP1000 near term, I'd book 20% of that in year T-3 if I'm reading the chart right, and then get a margin of 20%, EBITDA margin of 20%. I get it, everything's going to be different within a plus or minus. Is that sort of the right way to combine those two charts?
Broadly, it absolutely is. I think what changes a little bit is how that 45% changes throughout the duration of the project, but at an aggregate level, I think your approach is correct.
Brian, I might just add that in the first five years, we get 50% of the revenue in the initial projects, and then that speeds up, of course, as you get to nth of a kind.
Right, that makes good sense. And then is that normalized adjusted EBITDA of 20%? Is that kind of normalized over the whole cycle? Like in the first 50% you'd be getting 20%? Or would you get like higher up front and get 30 and get 10 on the back end or 10 even comment on that?
Probably can't comment on that. That's Yeah, just average over the whole project is about 20%.
Fair enough. And then on top of that, you get for do they become operating plants at that time obviously do in addition to that you get the 45 to 60 that you're talking about at the bottom of the table?
Yeah that's what that yeah that's what that means so once it goes into operation kind of on an annualized basis we're looking at fuel refueling outage services and all that and on an then it kind of it flips into our core business which is uh and and that's just recurring opportunity for the core business ongoing.
And Brian, just on that recurring core business, we're using our interchangeably. That table refers to Westinghouse's share of the core business. It does not refer to any Cameco uranium conversion and one day enrichment that would go into that core business. So that is just a Westinghouse contribution. And then of course, Why we're putting such a shoulder into new build is because we want to create our own 80 to 100 year demand for Cameco's core business of uranium conversion and eventually enrichment as well.
Right. No, that makes sense too. That was going to be my next question. Great. Thank you very much. Again, thanks very much. I think everybody will find these tables very, very helpful. I just want to make sure I'm reading it right. Thank you very much. Thanks. Thanks to you, Brent.
The next question comes from Craig Hutchinson with TD Cowan. Please go ahead.
Hi, good morning, guys. Can I just ask where things stand with regards to the Department of Commerce strategic partnership? Like what's the next milestone that we should we look for with regards to getting, I guess, a definitive agreement there? Thanks.
Well, you'll recall, Craig, that we initially agreed to a binding term sheet with the Department of Commerce. And so while there is an effort to achieve definitive agreements, we still have a basis for moving forward on that program as the Department of Commerce envisioned it. So what's critical there is to find the right projects that match up the interest of the Department of Commerce, the interest of the United States government in securing the The 24-hour baseload power that will come from the AP-1000s with those foreign investors who are interested and capable of investing in U.S.-based projects. So we are free to move ahead and explore all those opportunities. That does not require the definitive agreement because it was a binding term sheet. And that work continues. So what you would watch for is any announcements with those who have pledged foreign direct investment in the United States and the Department of Commerce on moving projects forward? And like a lot of things, a lot of work and a lot of thought is going into it. We just we don't have any projects to point to at the moment. But as I answered earlier, these continue to run in parallel and we view them as separate projects at the moment for that reason.
Just in terms of potential for cost overruns, is there a thought on how that would be managed? Would there be any exposure from Westinghouse's perspective if there was cost overruns on new builds? Thanks.
The question of cost overruns has been, I think, if not the first, the second question on the minds of utilities for a while now. But I think Where the conversation is going is that there's actually a toolbox of investment tax credits, if they're still available, production tax credits, as well as the reality that when you deploy an AP1000, you're deploying a reactor that's no longer first of a kind. Yes, there's next of a kind, but it's no longer first of a kind. And as that design certainty and fuel certainty and license and regulatory certainty is combined with the standardized sequence and simplify. The question about managing a project with a known product actually diminishes the conversation around cost overrun. It shifts it over to what is the package of tools that are available? I already mentioned things like investment tax credits. And then really what is the confidence of those that are supplying as well as construction services in their own capabilities. And ultimately what we're seeing is very fruitful conversations that utilities realize if they go with first of a kind in a brand new design, they're probably going to need cost overrun insurance. But if they go with an existing design that's already been deployed, then the tools are appropriate to manage those tail risks. So that's why the conversations are accelerating to ordering long lead items. And that's why you see a very robust list of 91 reactors from front-end engineering design close to FID all the way through to origination because it's just the reality of the competitive advantage of the AP1000. It's diminishing the need to worry about first-of-a-kind tail risks.
Thanks, Grant. Appreciate the call.
Thanks, Greg.
The next question comes from Christopher Souther with Truist. Please go ahead.
Hey, thanks so much for taking my question and all the disclosure here around Westinghouse. Could you talk a little bit around the project equity commitments that you and potential utility would be required to put up just like from a timing perspective if we could marry that with the revenue chart that you gave and just from a strategic standpoint is the plan to own projects over the long term or monetize those over time like what would be kind of Westinghouse's plan around that?
I think you're referring to the Department of Energy program for the long lead items.
Exactly.
So in each of those envision that you have something like five two-packs. Each two-pack has a special purpose vehicle that's put together and it's a combination of equity in the form of the utility as well as Westinghouse. But for Westinghouse, it's actually its margin that goes into that equity as opposed to putting cash in. So the owners and Westinghouse themselves don't intend to do that. That SPV exists until the utility is at FID and ready to commit to a build program and at which time it's sold forward to the relevant utility. It really is an acceleration. It's to take the traditional model where you have a utility who decides on nuclear, goes through a reactor selection process, decides on a technology and then starts all the front end engineering and design ultimately to lead to a final investment decision and then starts ordering long lead items. Well, if we did that, that's going to take a lot of time. In order to accelerate new build, we're trying to take the long lead item order and move it in front of FID and have a package of supply chain capabilities available. So it really is a shift in the normal way of building nuclear. And Westinghouse, you know, we're happy to be involved in that because when you look at a global demand stack that we now count at 91 reactors, we're pretty confident that ordering long lead items is a really low risk thing for us to do because there's going to be demand for those products when you have 91 that are being considered.
Okay, so there's no equity role that you guys are looking at for like long term ownership. That makes sense. Thank you.
Thanks, Chris.
This concludes the question and answer session. I would like to turn the conference back over to Tim Gitzel for any closing remarks.
Okay, thanks, Operator, and thanks to everybody who were on the call today with us. We appreciate it. Cameco remains well-placed, as you know, to support the next chapter of nuclear growth. while protecting and extending the value of our assets for shareholders, customers, and communities. So everybody have a wonderful weekend and enjoy the rest of the summer. Thanks.
This brings to an end today's conference call. You may disconnect your lines. Thank you for participating and have a pleasant day.