Thank you for standing by and welcome to Lundin Mining's third quarter 2026 earnings conference call. Currently, all participants are in a listen-only mode. After the speaker's presentation, there will be a question and answer session. To ask a question during the session, you will need to press star 11 on your telephone. To remove yourself from the queue, you may press star 11 again. I would now like to hand the call over to Jack Lundin, President and CEO. Please go ahead.

speaker
Jack Lundin
President and Chief Executive Officer

Welcome to Lundin Mining's third quarter 2026 earnings call. Our operating and financial results were released yesterday and the news release, presentation, and webcast replay will be available on our website. All amounts are in U.S. dollars unless stated otherwise. After the prepared remarks and presentation, as always, we'll open up the floor for questions. Today's results will contain forward-looking statements that are subject to risks and uncertainties, and we encourage you to review the cautionary notes in our presentation and our filings on CDAR+. Joining me today on the call is our Chief Operating Officer, Juan Andres Morel, and our CFO, Teitur Poulsen. Before turning to our results, I want to address the challenges at Casaronas, which have impacted the company's performance this year. The Atacama region experienced an exceptionally severe winter, with two major storms in July and August damaging transmission line towers and leaving the operation without power for approximately 30 days. Throughout these events, the Casaronas team maintained a strong focus on safety and worked diligently to restore operations in a controlled and responsible manner. The impact has extended into the fourth quarter with snowmelt reducing haulage rates and limiting ore deliveries to the mill. As a result, full year copper production guidance at Casaronas has been revised to 105,000 to 115,000 tons from the previous range of 120 to 130,000 tons. Juan Andres will provide further detail on these challenges in the operations section. Our revised full-year consolidated copper production guidance is now 285,000 to 310,000 tons, while cash cost guidance remains unchanged at $1.95 to $2.15 per pound. Despite these challenges, strong commodity prices and disciplined operational performance supported another quarter of revenue exceeding $1 billion and strong cash flow. Importantly, we also continue to make meaningful progress on our growth strategy. At Chapada, we sanctioned construction of an additional ball mill as part of the SAUVA growth project. Earthworks and concrete placement are underway, ball mill fabrication has commenced, and commissioning is targeted for late 2027. The finer grind will improve recoveries and allow us to capture greater value from the higher-grade SAUVA deposits. adding approximately 15,000 tons of annual copper production and 45,000 ounces of gold. At Vicuña, we achieved two important milestones in this quarter. First, we secured a long-term provincial royalty agreement with the San Juan government, consolidating our infrastructure obligations into a single royalty structure and providing a five-year payment holiday on trust contributions. Second, we received regulatory approval from Argentina's electricity regulator, ENRE, to construct the high-voltage power line connecting the project to the national grid. Together with the RIGI approval received earlier this year, these milestones represent important progress towards advancing Vicuña to a sanction as planned. While we continue to navigate the challenges at Cacerones, our underlying business remains strong. We have a robust balance sheet, a compelling pipeline of organic growth opportunities, and a clear path forward at Vicuña. Our priorities remain unchanged, operating safely, delivering consistent operational performance, and advancing growth strategy as we work towards our ambition of becoming a top 10 global copper producer. Performance at Candelaria and Chapada led the way this quarter and delivered our highest gold production of the year at 37,000 ounces, which drove down consolidated C1 cash costs quarter over quarter to $2.01 per pound, excluding storm-related impacts at Casaronas of 66 million. Despite the operational challenges encountered in the quarter, Q3 was one of the strongest financial quarters in the company's history. Record realized copper prices drove revenue above $1 billion for the fourth consecutive quarter, while adjusted EBITDA reached $650 million and free cash flow from operations was $418 million, putting us in a net cash position of $237 million at the end of the quarter. Year to date, our adjusted EBITDA and free cash flow from operations have both already surpassed full year 2025 totals. and we expect 2026 to be another record financial year for Lundin Mining. On capital returns, we repurchased approximately 2.4 million shares for an aggregate consideration of 62 million under our normal course issuer bid and declared our 39th consecutive quarterly dividend. In August, the board approved an increase up to $100 million to our share repurchase program for the remainder of 2026. I will now hand it over to Juan Andres to walk through the operational results in more detail. Thank you, Jack.

speaker
Juan Andres Morel
Chief Operating Officer

And good morning, everyone. Consolidated copper production was 63,000 tons. Candelaria and Chapada had strong quarters, while Cacerones was the only site meaningfully affected by the weather-related disruption. Gold production was 37,000 tons. Thank you for joining us today. The operation delivered an excellent third quarter, producing 35,000 tons of copper, up 13% from the second quarter. The increase was driven by a greater contribution of ore from phase 12, which delivered higher average head grades in line with the planned grade profile for the back half of the year. Production remains on track with full year guidance of 135,000 to 145,000 tons. An important milestone at Candelaria this quarter was the substantial completion of our underground mining insourcing initiative. Mining rates and unit costs have been better than planned levels, and we expect underground mining rates to stabilize at approximately 14,000 tons per day by the end of 2027. This expansion represents a meaningful path to grow production at Candelaria. Turning now to Chapada, The operation produced 12,600 tons of copper in the quarter, up 5% from the second quarter, the highest quarterly output in the last two years, along with 16,900 ounces of gold. We expect to see similar levels in the fourth quarter as well. Throughput benefited from high plant availability and improved glass fragmentation. Chapada remains on track to meet its full-year copper production guidance of 45,000 to 50,000 tons. As discussed, it was a difficult quarter for Cacerones. A series of severe winter storms caused two extended production stoppages in July and August, totaling approximately 30 days of suspended operations when accounting for the time required to safely restart including thawing the flotation banks and turning over the mills. I want to recognize the Cacerones team for their outstanding work navigating these conditions safely and efficiently. Production in the quarter was 15,000 tons of copper reflecting the impact of the storm. As we move out of the winter in the southern hemisphere, operations continue to face weather events of lesser severity. In October, the site received 1.4 meters of snow. Snow melt has created extremely muddy conditions in the pit. This has reduced haulage rates and limited the volume of ore delivered to the mill. Haulage speeds have dropped by 20% along with track availability. The last two months of difficult conditions have impacted maintenance schedules and reduced fleet availability. Given the mining rates we saw in September and October, we reforecasted production for the remainder of the year, factoring in the lower haulage speeds and maintenance time to improve the fleet availability. As a result, we have further revised Casa Dones full-year copper production guidance from 120,000 to 130,000 tons to 105,000 to 115,000 tons. This is very disappointing. but is not a reflection of the underlying asset or the team. It is a direct result of the storm events that have driven Chile's lowest copper production in 20 years. New full-year consolidated guidance is now 285,000 to 310,000 tons with cash cost guidance unchanged at $1.95 to $2.15 per pound. I will now turn the call over to Teitur to walk through the financial results.

Want transcripts like this in your own app? Try the Earnings call API, or read the transcript API docs.

Disclaimer

This conference call transcript was computer generated and almost certianly contains errors. This transcript is provided for information purposes only.EarningsCall, LLC makes no representation about the accuracy of the aforementioned transcript, and you are cautioned not to place undue reliance on the information provided by the transcript.

-

-

Use this data in your own app

Pull this call's transcript, audio and slides with the Earnings call transcripts API.

See pricing

9,000+ companies · REST API