This conference call transcript was computer generated and almost certianly contains errors. This transcript is provided for information purposes only.EarningsCall, LLC makes no representation about the accuracy of the aforementioned transcript, and you are cautioned not to place undue reliance on the information provided by the transcript.
10/21/2026
Thank you everyone for joining the call today. With me is Wayne Bramwell, Managing Director and CEO of Westgold Resources. Over to you Wayne.
Thank you and hello everyone. Welcome to Westgold's September 2026 quarterly results call. Joining me today are Aaron Rankine, our Chief Operating Officer, and Tommy Heng, our Chief Financial Officer. We'll walk through today's numbers before opening up the floor for questions. Slide 4. A strong start to FY27. Safe and profitable ounces is Westcold's mantra. Safety first. In Q1 we recorded no lost time injuries and our LTIFR reduced to 1.17. We also saw strong improvement across our key leading safety indicators. supported by sustained frontline engagement, critical control verification and leadership field presence, reflecting our ongoing focus on fatality prevention and critical risk management. Now to our business performance. We've delivered a strong start to FY27, producing 98,400 ounces at an all-in sustaining cost of $2,912 per ounce, and we remain firmly on track to deliver our FY27 guidance. With Q1 under our belt, that takes us to more than 400,000 ounces produced over the last four quarters. Importantly, ore produced from our ore mines increased 7% this quarter. That lifted our ore stockpiles by 51% to 696,000 tonnes, roughly six weeks of mill feed. Those stockpiles kept our mills running through wet weather in the Murchison and provided ample ore feed when the mills emerged from their heavier maintenance schedule this quarter. At Beta Hunt we hit a record 2 million tonne per annum annualised mining rate in September with the new interim ventilation now commissioned. Aaron will take you through this in more detail later in the presentation. Our margins remain strong. An all in sustaining cost margin of $3,117 per ounce delivered $292 million in mine operating cash flow and a $251 million underlying treasury build. We closed September with over $1 billion in cash, bullion and liquid investments, remaining debt free and fully unhedged. It was also a big quarter for our future. We grew group ore reserves by 41% to 4.1 million ounces and set out a fully funded pathway towards half a million ounces of production through our updated three-year outlook. We continue to reward shareholders, declaring a 10 cent fully franked FY26 dividend and also buying back $22 million worth of shares in Q1 FY27. We also introduced a new shareholder capital returns policy. Our strategy is doing what it was designed to do. Stronger production, driving stronger cash generation, which funds both our growth and ongoing returns to our shareholders. Slide five. Q1 results firmly in line with guidance. Q1 has put us firmly on track for FY27. We produced 98.4 thousand ounces broadly in line with the 98.9 thousand ounces we delivered in Q4 and right on pace for our full year guidance of 385 to 425 thousand ounces. Our all in sustaining costs of $29.12 per ounce was below our guided range of $29.80 to $33.80 per ounce. That's despite a quarter with more planned mill maintenance across all our processing hubs and higher waste stripping in our open pits. We're investing in line with plan. Non-sustaining capital was $111 million against full year guidance of $450 to $480 million going into development at Bluebird, Great Fingal and the Beta Hunt Mines and into processing, power, ventilation and camp infrastructure. Expiration was $24 million against guidance of $50 to $75 million for the full year. Spen picked up in the quarter as planned drilling programs received their approvals and access and will keep drilling. Slide 6 Westgold 456 Fully Funded Growth In September we released our FY27 guidance and an updated 3 year plan. The simplest way to describe it is Westgold 456. What does it mean? Four. Four operating hubs across the Murchison and Southern Goldfields with 5.7 million tonnes a year of installed processing capacity. That grows to more than 7 million tonnes a year by FY29 through the Kew expansion this year and the Meeker Tharra expansion planned in FY28. 5. A fully funded pathway to around half a million ounces a year by FY29. FY27 sees Great Fingal Reach commercial production and the Kew expansion come online. From there, production steps up to between 425 and 470,000 ounces in FY28, reaching 460 to 510,000 ounces in FY29. with our all-in sustaining costs falling at that point to between $2640 and $3000 per ounce as higher grades and throughput come through. We're funding the 456 plan from our own cash flow while continuing to return capital to shareholders in parallel. 6. Fletcher. It isn't included in the three-year outlook but with a 1.1 million ounce maiden reserve announced last year, it could add around 140,000 ounces a year on top of our production and gives us a very tangible pathway beyond 600,000 ounces a year for the group. Our Q1 result is the first step in delivering that plan. With that, I'll hand over to Aaron to take you through our operational results.
Thank you Wayne and good morning to everyone on the call. Our operations continued to build momentum in Q1. We mined 1.42 million tonnes of ore at 2.2 grams per tonne, up 7% on Q4, which was our strongest mining quarter of last year. That increase came from Great Fingal, Starlight, our Murchison Open Pit Program and Beta Hunt, with overall mine grade lifting slightly quarter on quarter. Processing throughput was steady with mills fully utilised, processing 1.46 million tonnes of ore at 2.3 grams per tonne. Quarter on quarter upside at Lakewood was offset by usual Q1 heavy plan maintenance regimes across all of our processing hubs. The result was 98.4 thousand ounces, in line with Q4, with production sourced from our own mines up 5%. That takes us to over 400,000 ounces over the last 12 months. The capability of this business is starting to show and there is plenty more to come. Slide 9. Our stockpiles are building by design, creating resilience in our operations and de-risking our planned incremental mill expansions that will support higher production at lower costs. Total ore stockpiles grew 51% to 696,000 tonnes, about six weeks of mill feed at our installed capacity. The build happened in both regions, the Murchison up 60% to 485,000 tonnes and the Southern Goldfields up 34% to 211,000 tonnes on the back of record mining at Beta Hunt. The resilience this creates was on show this quarter. When wet weather closed haul roads in the Murchison over the period, our mills kept running at full speed. Slide 10. Regionally, the Murchison produced 71.9 thousand ounces, slightly below Q4. That reflects lower OPA production and increased planned maintenance at all three Murchison mills. Notably, production from our own ore sources in the Murchison was up around 4%. Across the Murchison hubs, Meekatharra delivered 35.9 thousand ounces, with a consistent feed grade of 2.5 grams per tonne. The mill ran at an annualised 1.9 million tonne run rate, still above its 1.8 million tonne annualised base capacity. Q lifted to 19,000 ounces with grade slightly improving to 2 grams per tonne as more great fingal is introduced into the blend and Fortnum continues to deliver to plan with around 17,000 ounces. In the southern goldfields Higginsville produced 26.5 thousand ounces up on Q4 that includes the scheduled toll treatment parcel at Lakewood partly offset by the major plan shutdown at the Higginsville mill. Slide 11. At Bluebird, mining ran at an annualised 870,000 tonnes, slightly below our 1 million tonne per annum target, with the mining schedule focused on smaller, higher grade stopes, evident in the increased mine grade at 3.1 grams per tonne for the quarter. We continue to open additional mining areas, giving us multiple mining fronts, underpinning the improved mining rates and delivery of plus 1 million tonnes for the full FY27. Bluebird is well positioned as the key feed for larger meek tharum mill that will be delivered in FY28. Slide 12. Earlier today we released an update on Beta Hunt and it's a milestone we're proud of. When we acquired Beta Hunt in August 2024 we saw a high quality ore body held back by legacy infrastructure and a lack of drilling. Under prior ownership it had not sustained mining rates above around 1.4 million tonnes per annum. Over the last two years we've invested around $33 million to remove infrastructure constraints in ventilation, dewatering, water supply and power. We've also substantially improved mine design and significantly increased diamond drilling to bolster reserve and resource confidence. That work is paying off. In September Beta Hunt delivered a record month at an annualised circa 2 million tonnes per annum. Our interim primary vent was commissioned during the quarter ahead of the target we provided in Q4 and we are now targeting a sustained 2 million tonne a year mining rate from Q2 this year. Beta Hunt also delivered its second consecutive quarterly record, mining 423,000 tonnes in Q1. With those foundations in place, our focus shifts to optimising cost and looking forward to firm up what is possible. Integrated Southern Goldfields expansion studies are underway and due next half, while we continue with seven drill rigs growing the ore body. With that, I'll hand over to Tommy to take you through our financial results. Thank you.
You're reading a preview of the WGX Q1 2027 earnings call.
Free account.
Want transcripts like this in your own app? Try the Earnings call API, or read the transcript API docs.
Use this data in your own app
Pull this call's transcript, audio and slides with the Earnings call transcripts API.
See pricing