4/29/2026

speaker
Operator
Conference Operator

Standing by and welcome to the Boss Energy Investor Conference call March quarter 2026. All participants are in listen-only mode. There will be a presentation followed by a 30-minute question and answer session. If you wish to ask a question, you will need to press the star key followed by the number one on your telephone keypad. In the interest of time, participants are requested to limit the number of questions to two per turn. If you have additional questions, you are welcome to rejoin the queue and we'll be able to ask further questions if time permits. If we run out of time and do not have time for your questions, we ask that you please call our office on 08-6263-4494 or email boss at bossenergy.com and speak to our team. I would now like to hand the conference over to Mr Mark Ducey, Managing Director and Chief Executive Officer. Please go ahead.

speaker
Mark Ducey
Managing Director and Chief Executive Officer

Thank you. The BOSS Energy March quarterly conference call. Joining me on the call this morning is Justin Laird, our CFO. We're happy to take questions at the end of this call. Turning to slide two. In summary, this has been a challenging quarter operationally for the business. At the same time, we've made significant progress in advancing our pathway forward. In terms of the honeymoon operation for the quarter, production for the quarter was lower and costs were higher than forecast. The primary driver was the impact of heavy and repeated rainfall events during March, which restricted access to site and limited the delivery of key reagents required to maintain stable leaking conditions. This is also compounded by delays in commissioning additional processing capacity, including columns and associated primary pumps. As a result, we revised our FY26 production guidance to 1.4 to 1.45 million pounds. We have reconfirmed our C1 cost guidance of $36 to $40 per pound, and all in sustaining cost guidance of $60 to $64 per pound. Note that we expect to finish the year towards the upper end of our cost guidance range. Importantly, we have now commissioned NIM6 column 4 in April, with column 5 expected to be completed this quarter. Completing this stage of construction and commissioning is a key step in stabilising operations and improving forecast reliability. This will be a key milestone from a plant operational perspective. On finance, the company remains in a strong financial position with $211 million of cash and liquid assets. we achieved an average realised sale price of US$73.6 per pound, with total sales of Australian $34.4 million during the quarter. Importantly, even with lower production and continued capital investment, the business was broadly cash flow neutral for the quarter, taking into account timing on payments. BOSS Energy remains in a strong financial position. Finally, on strategic programs of work, we have made meaningful progress on unlocking value through execution of our pathway forward. We released updated mineral resource estimates for Gould, Stam and Jason and accelerating permitting pathway. And we continue to advance the new feasibility study and wide space wellfield design. There has been a clear step change in our understanding since December, and based on the work completed to date, I am increasingly confident in the value that we can unlock through this approach. Turning to slide three. Looking at honeymoon production in more detail, drums production during the quarter totaled £203,000. We entered the quarter expecting soft production due to lower forecast tenor. However, the quarter was also significantly impacted by rain events across Central Australia. March 2026 was the second wettest March on record in South Australia, and access to site was restricted for approximately 27 days during the month. This had a direct impact on operations. rainfall restricted access and delayed reagent supply and ability to maintain steady leaching conditions, and the final completion and commissioning of additional NIM6 columns and pumping surface expansion. As a result, we have revised our production guidance to 1.4 to 1.5 million pounds of drum uranium for FY26. We expect Q4 production to be in the range of 356 to 406,000 pounds. reflecting increase in flow enabled by new infrastructure. Importantly, we now commissioned NIM6 column 4, which is in operation in April. Column 5 is scheduled to be operational later this quarter. In parallel, we are upgrading the primary pumping systems, including installation of PLS, BLS, pumps 4, 5 and 6. While we've experienced some pump failures during commissioning, these are being resolved. Turning to slide 4. Honeymoon C1 cost for the quarter was $60 per pound, with all in sustaining cost of $93 per pound. This increase in cost is primarily a function of a lower production volumes during the quarter, resulting in lower fractionalisation of fixed cost, hence the increase in unit cost. There's been no structural change to our underlying cost base, and as production increases in Q4, costs will come back down. On this basis, we are reconfirming our FY26C1 cost guidance of $36 to $40 per pound, and our all-in sustaining cost guidance of $60 to $64 per pound, noting that we're likely to be at the top end of this range. In terms of capital, Sustaining capital during quarter was $5 million, primarily related to wellfield development at East Kalkaroo, which will come online into production this quarter. Project and supporting infrastructure capital totaled $8 million, largely associated with NIMS 6 columns 4 and 5, the East Kalkaroo trunk line and accelerated resource delineation programs. As with operations, these programs were also impacted by weather during the quarter. Turning to slide five. Our balance sheet remains a key strength. We closed the quarter with approximately $211 million in cash and liquid assets. The cash declined from $53 to $38 million was due to a delay in cash receipts associated with sales executed but not but cash received in the following quarter we generally try to hold approximately 50 million dollars in cash drummed uranium inventory finished the quarter at 1.53 million pounds we view this inventory as strategic for the company as we continue to see tightening of the uranium markets Sales during the quarter consisted of 3,000, 25,000 pounds at an average realized price of $73.6 US or Australian $106 per pound. We delivered 125,000 pounds into a legacy contract during the quarter. An additional 125,000 pounds will be delivered during the current quarter. This contract is for a maximum of 1.7 million pounds with annual deliveries of 20% of the previous calendar year's production up to a maximum quantity of £250,000 per year. The contract material will reflect a realised price of approximately 65% to 70% on spot price of sales for that period. Turning to slide 6. In terms of our 30% staking in the Altamesa, a joint venture with Encore, production for the quarter totaled £97,000, of which Boss Energy received £35,000 during the quarter. The production decline is associated with the timing of bringing in new wellfields online. This includes additional modules coming online at Wellfield 7, Wellfield 3 expansion development progressing with further wellfields being installed, A clear focus on ultimate series with additional drill rigs and accelerating of permitting constraints and continue resolving some of these permitting delays that the joint venture has seen. Turning to slide 7. I'll now talk about the new feasibility study, which is a key focus for the business. At a high level, our pathway forward at Honeymoon is centred on two things. That's bringing in low grade mineralisation into the wellfield design and fundamentally shifting our cost structure to ensure that we can generate solid margins on lower grade material. The pathway we are advancing to achieve this is a change in our wellfield design, moving to a wide space approach that is better suited to the honeymoon style of mineralisation. Importantly, since December, there has been a clear step change in our understanding as we progress this work. We continue to confirm the assumptions that underpin this approach. This comes back to the characteristics of the deposit. We are seeing strong continuity of mineralisation at low grades, supported by a continuation of 3D modelling and ongoing drilling. We are confirming good permeability and hydraulic connectivity, allowing flow and control across large well-filled spacing. We continue to see relatively low acid consumption, and we are significantly improving our understanding of groundwater behaviour through modelling. This work being executed is progressively validating and de-risking the pathway forward. Turning to slide eight. A step change in our approach is the use of reactive transport simulations. I won't go into the technical detail, but at a high level this is allowing us to simulate fluid flow and chemical interactions within the deposit. This was developed in the 1990s in Europe for nuclear waste disposal. It is a tool that has been used in highly complex applications globally, and now we are applying it to ISR mining at Honeymoon. The importance of this is that it's giving us a much higher level of confidence in well-filled design, well-filled planning, and ultimately well-filled performance. Turning to slide nine, the reactive transport simulations are a core part of the new feasibility study. At a high level, we're incorporating detailed inputs across geology, hydrodynamics, well-filled design and chemistry, and running these through high performance simulations. The outcome is a much deeper and more predictive understanding of fluid flow behaviour, leaching efficiencies and ultimately production performance. They have been calibrated against historic production data at Honeymoon which has given us confidence on the outputs. So while the modelling itself is complex, we are now building a better understanding of how this system will perform, which will facilitate delivery of a robust feasibility study. Turning to slide 10. In parallel to the modelling, we are establishing a series of trial wide-space wellfield patterns. This slide shows how we're developing the trial patterns for both Honeymoon Domain and East Kalkaroo. At a high level, we're testing from current well-filled spacing to a wider well-filled spacing in these trials, which will cover larger areas, reduce capital intensity, lower operating costs by reducing pool volumes. The lower costs will deliver lower cut-off grades, in turn providing more resources under leach. Turning to slide 11. Gould's Dam is a satellite deposit located approximately 80 kilometres from Honeymoon. During the quarter we delivered an updated mineral resource estimate of 38.7 million tonnes at 388 ppm U308 for 33.1 million pounds of contained uranium. Importantly the deposit is amenable to ISR. It is likely suitable for a wide space oilfield approach and we are accelerating our baseline and technical studies required for permitting. Once the accelerated resource delineation drilling is completed at Honeymoon, we plan to mobilise drill rigs to Goulds Dam, where the priority is to convert the unclassified portion of the mineral resource to inferred. We're expecting this program to commence in Q1 next financial year. Turning to slide 12. The adjacent deposit is located 14 kilometres from Honeymoon. It is smaller, with an unstated mineral resource of 13.3 million tonnes, at 410 ppm U308 for 12 million pounds of contained uranium. Importantly, mineralisation remains open and we are advancing studies through permitting. Consistent with Gould's dam, this deposit shares the similar characteristics and expected to be amenable to wide space wellfield design. Turning to slide 13. So just to close, this has been a more challenging quarter operationally, primarily driven by rain, fall and farming impacts. Our focus is on completing commissioning and delivering a strong Q4. It will be a milestone quarter with the completion of columns four and five, along with bringing in each category wellfields. At the same time, we are making strong progress on the new feasibility study. The work completed to date continues to support Halfway Forward with a step change in our understanding of the assets and how we develop it. The wide-space, well-filled approach has the potential to materially improve the cost structure, lower cut-off grades and bring more resource into production. Importantly, this is not just about optimisation of Honeymoon. It also provides a scalable pathway across the broader district, including Goulds Dam and Jason's. With a strong balance sheet and disciplined capital approach, we are well positioned to execute on our pathway forward. Thank you. And with this, I'll hand back to the operator, and we're happy to take questions.

speaker
Operator
Conference Operator

Thank you. If you wish to ask a question, please press star 1 on your telephone and wait for your name to be announced. If you wish to cancel your request, please press star 2. If you're on a speakerphone, please pick up the handset to ask your question. Your first question comes from Alastair Rankin with RBC Capital Markets.

speaker
Mark Ducey
Managing Director and Chief Executive Officer

Thanks, Justin. Appreciate the presentation. Just firstly on the testing for the new wellfield configuration, can I just ask when you'll be able to start physical testing on those configurations and what you need to do to get that underway? So in terms of those wide-space trial programs, Some of those wells have already been installed, but we expect to commence first flushing on those first of those trials in July. So it will start receiving data basically in July on those trial patterns. As you understand, these wide-spaced and typically well-filled do have a long lead and also will take time to fully deplete, so we won't have those sort of... trial plans depleted by the time we deliver the EFS, oh sorry, the feasibility study, but it'll be an important input into some of the modelling that we're doing. Okay, and is there any disruption to existing production at the plant? Do you need to sort of re-divert infrastructure that's being used for ongoing production right now to do that pre-conditioning and then ultimately the testing for the new well-built? Yeah, not at this point. We believe that we can bring those trial patterns in without having too much of a production impact. So everyone's online to say that people also have people understand is one of the constraints will be ability to flush, which is linked to our water treatment plant. We've got programs at work to continue to expand that water treatment plant to ensure that we can bring new wellfields in time online plus additional work associated with these trial patterns. Okay, thank you.

speaker
Operator
Conference Operator

Once again, if you wish to ask a question, please press star 1 on your telephone and wait for your name to be announced. That's star 1 on your telephone and wait for your name to be announced. Your next question comes from Branko Skosik with J.P. Morgan.

speaker
Mark Ducey
Managing Director and Chief Executive Officer

Hi, Branko.

speaker
Operator
Conference Operator

Branko, your line is open.

speaker
Mark Ducey
Managing Director and Chief Executive Officer

Yeah, morning, guys. I must have been on mute just then. I was just wondering how road conditions are around site. I know you called out what weather with the first quarter of the calendar year, as well as how the lexivian chemistry is performing in the plant. I know we're now end of April, so that's, I guess, starting to normalise. Yeah. So some good questions there. So road conditions have improved. We've been working with state government on main access road. That was one of the key restrictions. Generally on site, road conditions are good. We find the constraint is the state road, Mullingarie Road, which is under state control, is our biggest challenge and obviously we've got to work with the state to improve that to give us a little bit more resilience in terms of that operation. When we talk about lixivian control, it's mainly associated with the wellfields, the plants less We can get that under control quicker, but what happened with the rainfall event is effectively because of that 27 days of restricted reagents to site, we couldn't continue to provide the lithium to the wellfields. So it's taken us a little bit of time to get wellfield chemistry back in line. That's back in line, although pH, we're still going to get pH down a little bit more in some of the wellfields to see the higher tenner come through. I appreciate it. And final question from me. You called out the water treatment plant, I guess, just upgrading the capacity there. Is that coming through the FY26 capex, or is this something we can expect into FY27? Yeah, there's... The two elements there is to get that water treatment plant to nameplate. That will just be within our current cost structure. That will complete it this quarter. With the new feasibility study, we'll have to work through what infrastructure would be required and just at a high level, the water treatment plant and whether we need an additional water treatment plant will be one of the things to be addressed in the new feasibility study. And our ability to flush will ensure, as part of the shift from this current spacing to a wide spacing, that we don't see a production drop, and that will be largely linked to water treatment plant and our ability to bring on flushing and get these wide space well fields into production. Excellent. Appreciate it, guys. Thank you.

speaker
Operator
Conference Operator

Once again, if you wish to ask a question, please press star 1 on your telephone and wait for your name to be announced. Your next question comes from James Bullen with CG.

speaker
James Bullen
Analyst, CG

Good morning, guys. Just a quick question around B6. Do you have an early read on how that's performing at all?

speaker
Mark Ducey
Managing Director and Chief Executive Officer

Hey, James. B6 is not yet into production. It will come into production this quarter. Okay. And then... Go ahead.

speaker
James Bullen
Analyst, CG

And then just around Altamisa, obviously having a few delays around permitting there, wouldn't have thought Texas was a particularly onerous regulatory environment. Do you have any more colour around what's happening there?

speaker
Mark Ducey
Managing Director and Chief Executive Officer

With the permitting regime within... for Altamisa is they have to get each well-filled permit. So unlike... ourselves, we're working within a whole permitting regime within a mining lease, they have to permit each wellfield. So if there's any delay associated with defining definition of the wellfield, putting controlled monitoring wells etc, then that just flows through permitting and then permitting timetables. So that's the thing they're trying to resolve now is how they can actually change the permitting regime or accelerate that permitting regime.

speaker
James Bullen
Analyst, CG

Okay, I understand. Thank you.

speaker
Operator
Conference Operator

There are no further questions at this time. I'll now hand back to Mr. Druesey for closing remarks.

speaker
Mark Ducey
Managing Director and Chief Executive Officer

Thank you, everyone, for joining the call this morning. As noted on the quarter, we look forward to delivering a strong Q4, and we have a clear pathway forward as we continue to build confidence in this Widespace Drill Program. So thank you for joining. Thank you.

speaker
Operator
Conference Operator

that does conclude our conference for today thank you for participating you may now disconnect

Disclaimer

This conference call transcript was computer generated and almost certianly contains errors. This transcript is provided for information purposes only.EarningsCall, LLC makes no representation about the accuracy of the aforementioned transcript, and you are cautioned not to place undue reliance on the information provided by the transcript.

-

-