This conference call transcript was computer generated and almost certianly contains errors. This transcript is provided for information purposes only.EarningsCall, LLC makes no representation about the accuracy of the aforementioned transcript, and you are cautioned not to place undue reliance on the information provided by the transcript.

Resolute Mining Limited
1/22/2026
Good morning, ladies and gentlemen, and welcome to the Resolute Mining 4th Quarter 2035 Activities in 2026 Guidance. At this time, all participants are in a listen-only mode. Later, we will conduct a question-and-answer session through the phone lines, and instructions will follow at that time. For those listening via the phone lines, the presentation is now available within the Investors section of Resolute Mining's website. For those watching the webcast, if you wish to submit a written question, you may do so by using the Ask Question button on the SparkLive page. I would like to remind all participants that this call is being recorded. I will now hand over to the Chief Executive Officer, Chris Agar, to open the presentation. Please go ahead.
Good afternoon and good morning to all. Welcome to Resolute Mining's Q4 2025 Activity Report, in addition to providing some color on our 2025 annual results, as well as our guidance for 2026. Today, I'm joined on our call by Gavin Harris, our Chief Operating Officer, who's actually sitting at our SIEMA operations in Mali, as well as our CFO, Dave Jackson, in addition to our Head of Corporate Development and Investor Relations, Maddy O'Toole-House.
So let's dive into it.
When looking at our Q4 performance across the business, I'm very proud to say that we achieved all of our targets and have very much stabilized the operation, setting up a very strong foundation for 2026. But when looking at the details, our goal produced was 66,000 ounces, an increase of 6,000 ounces over our Q3 results. A lot of this work came from our activities in both Senegal and Mali. Specifically in Mali, we have stabilized our supply chain issues that we talked about at the beginning of last year and throughout 2025. where by now we've now stabilized our explosive situations and are hitting our targets through the end of the year and into 2026. Macro continues to perform extremely well and we had a very strong quarter in the last quarter of the year. As a result of the good production across the business, Our all-instaining costs came in at $1,877. Again, a decrease versus our Q3 ASIC of just about $2,200. So the difference between the two ASICs really results in the fact that we are really managing our costs across the business as extremely efficiently as possible, but most importantly, with the increase in the production levels. Very also positively, we reduced our TRIFR to 1.87 versus 1.95 in the previous quarter. CapEx came in line at $18 million. But ultimately, what we're most proud of is the fact that we generated close to $86 million of operating cash flows in Q4 relative to $70 million in Q3. So what does this mean from a net cash position for the year is that we ended the year at $209 million of net cash, which is roughly a $140 million increase in cash from the beginning of the year. With Q4, it was also very exciting for us in the fact that we had some significant developments in Cote d'Ivoire, Specifically, on December 15th, we provided an update of the Duropo DFS to the market, which shows the incredible robustness of this project, whereby the NP of the project at $4,000 is just about $2.5 billion. We'll go into more details on the specific activities for Duropo in the upcoming slides, but I'm very pleased to say that this project remains on track, on budget for construction in the first half of this year. In addition, we continued to progress across the portfolio in our exploration assets, and most notably, we introduced a Ladabo MRE at 643,000 ounces at 1.14 grams per ton. In addition, we started really drilling at the ABC deposit in Western Cote d'Ivoire, achieving very strong exploration results, which I'll go into detail in the coming slides. Across the business, we also are continuing to execute our other strategic projects, most notably in Mali. We're very much on track and on budget with our SACP project, again, which we'll talk about in the upcoming slides, and we continue to progress in Senegal on the life extension projects. 2025 was an incredibly pivotal year for Resolute, as well as a very transformational year for the business. I'm very proud to say that we were able to achieve gold production in line with our guidance of 275,000 ounces to 285,000 ounces, with final gold poured of 277,000 ounces. So very much on track of guidance, on production, also on all unsustaining costs, whereby we ended the year at an all unsustaining cost of $1,843, which is in line with our revised guidance. Additionally, CapEx came in on guidance at $118 million, and we achieved very strong operational and financial results with EBITDA coming in at $383 million. It is worth noting, though, that at the end of the year, we finished with quite a lot of gold bullion that we did not sell, so we roughly had 31,000 ounces of gold in inventory that we sold in January, which impacted the EBITDA profile for 2025. With regards to cash flow generation, and as it relates to the previous slide, we ended the year with $209 million of net cash, but our overall available liquidity was just over $320 million between our gross cash and access to working capital facilities. So when looking at the business from a qualitative perspective, we're very pleased with all the activities that occurred in 2025 to position the business for continued success in 2026. Most notably, in 2025, we substantially augmented the skill sets of the executive team. We brought new people into the business, specifically a project team in Cote d'Ivoire for the construction of the Duropo project. We also restructured a lot of the principal activities in Mali as a result of some of the challenges that occurred in 2024. We spent quite a bit of time with different government bodies across the business, and we've been augmenting the relationships that we have with the people in all the different jurisdictions that we operate. We also completed the acquisition of the Dubropo and ABC projects in Cote d'Ivoire in May of 2025. This acquisition has set the business up for continued success by becoming a multi-producer West African gold company. We also made significant achievements in continuing the projects that we have in both Mali and Senegal as it relates to the SSCP and LEP programs, which we'll go into more detail. The other key activity for the business in 2025 was continued focus on exploration, as I see this as a pivotal leg to creating shareholder value in the long term. But I'll spend a bit more time in the exploration section as it relates to some of the key activities that we see in 2026. Here's a recap of the organic growth profile for the next coming years. As you can see, in 2025, we achieved 277,000 ounces. But as you look to the future, we'll be achieving between 250,000 to 275,000 ounces for the next couple of years as we continue our stockpile processing at MACO, where we start the construction of the Daropo project. So I'm very confident by 2028, we will be on a run rate to achieve 500,000 ounces for the foreseeable future across the business. And beyond that, with the work that we're doing on exploration, I'm very confident that we'll be able to grow the production profile organically through some of the success that we're seeing in the exploration side of the business. So as you can see on the page, we're guiding gold production from 250 to 275,000 ounces across the group. That's split between SIAMA and MACO of 195,000 to 210,000 ounces of gold production out of SIAMA and 55,000 to 65,000 ounces of gold production out of MACO. MACO is quite straightforward as we're continuing to process stockpiles all through 26 and into 27. However, at SIAMA, SIAMA is going to have an interesting year as we will be commissioning the SACP program, whereby we are going to start processing the majority of the ores to be sulfides as opposed to in the past a split between sulfides and oxides. But Gavin will go into very specific details about how this transition will occur in 2026. As a result of the high gold price environment, we are seeing our oil and sustaining costs increasing, and so we are guiding our oil and sustaining costs across the group between $2,000 to $2,200. But a significant reason for the increase from 2025 is due to the fact that the royalty expense at today's gold price environment at $4,000 plus is adding quite a bit of expense to our oil and sustaining costs. Capital expenditure for 2026 is substantially higher versus 2025. And as you can see on the page, it's between $310 to $360 million. Going through the different line items will provide some context to the increase in CapEx. So let's start with SIAMA. SIAMA is being guided between $110 to $125 million. But of this number, approximately $40 million relates to the finalization of the SSCC program relative to 2025. In addition, waste stripping is also about $40 million, which is an increase versus 2025 of about $20 million. And that additional waste stripping capital is required in order to further develop the Siaman North deposit in order to access higher-grade zones for the future. At MACO, we anticipate that the capex will be between $15 to $20 million, with the vast majority of that capital being spent on capital projects at the Tambo and Bataco projects. Duropo is projected to be between $170 to $199 million subject to permitting and FID approval. And most of that CapEx is scheduled to be spent in the second half of the year. But again, we'll go into more detail on how we see Duropo being built and expensed in the upcoming slides. And finally, we continue to spend quite a bit of money on exploration as this is a key value driver for the business. And so we expect to spend at least $15 to $25 million on exploration, predominantly in Cote d'Ivoire, but we are looking to expand our activities in both Guinea and also in Senegal. So with that, let me turn it over to Gavin Harris to walk me through the specifics of each of our assets and our activities in 2026.
Okay, thanks, Chris, and good morning and good afternoon to everybody on the call. Starting in Ivory Coast, we've made major progress on JAROPO and ABC projects, which we acquired in May last year from Anglo Gold Ashanti. JAROPO is a transformational project for Resolute, and one that I was already familiar with as it was originally developed during my time with Sentiment. Throughout the second half of 2025, we built out the project team, appointing key positions in the project director, the project manager, and the project services manager. The project director, Rob Ciacchini, leads his team, which has nearly 100 years of experience building projects in West Africa, Asia and Australia, predominantly with lycopolium in the past. The long list of projects his team have worked on in West Africa include Iti, Agbao and Sisinge in Côte d'Ivoire, Hunde, Bisse and Boulie in Burkina Faso, Focola in Mali, Obertan and Zima in Ghana, and of course, Alverio and Mako Mine in Senegal. Moving on to key achievements for DROPO last year, these include the updated mineral resource estimate, which increased by 28%, the release of the updated Definitive Feasibility Study, or DFS, that outlined a larger and longer life operation than the previous DFS by sentiment in 2024, the appointment of lycopodium engineering to complete the front-end engineering design, or FEED, and the issuance of the Tender for Engineering Procurement Construction Management, or EPCM, with site visits taking place next week. Progression of permitting saw increased governmental interactions, including multiple visits from the Resolute Executive Team and a meeting with the Prime Minister. We are waiting for approval for the mining permit. At the end of last year, the permitting process slowed due to elections. With these now over and Ministers being appointed this week, we expect the last two stages of permitting to progress over the coming months. These stages are, firstly, approval in the inter-ministerial commission, followed by signature of the presidential decree. The updated DFS released on the 15th of December outlines a significantly larger project compared to the previous version of the DFS, with a 55% increase in gold reserves and an extension of the mine life. An updated gold price of $1,950 per ounce has increased total life of mine gold production to 2.2 million ounces over 13 years. Current spot gold price is significantly higher than this, but to manage the timeline and permitting, which was submitted using $2,000 pit shells, the updated DFS remains within these confines. Further gold production is anticipated at higher gold prices, which underpins the confidence that the Drobo life of mine could be extended beyond 13 years. We believe additional exploration targets between the main sewer hub and Kelisegi could add even further mine life. The upfront capital costs have increased to an estimated $516 million, which reflects updated pricing with a significant inflationary aspect compared to the previous version completed during the first half of 2024. A 25% increase in processing capacity, future-proofing the project which allows for further modular expansion. An 80% increase to the water storage capacity. A 55% increase in the capacity of the tailing storage facility to meet the additional process tonnages. Increased landscape livelihood restoration and resettlement costs and the inclusion of some previously omitted items. Financial highlights from the updated DFS at a base case gold price of $3,000 an ounce include all-in sustaining cash cost of $1,406 an ounce, a post-tax net present value of $1.46 billion at a 5% discount rate, an internal rate of return of 49%, a payback period of 1.7 years. The payback drops to under a year of $4,000 gold price, and obviously the gold price is much higher than that right now. Very strong free cash flow is averaging over $260 million per year over the first five years of production. As I mentioned a moment ago, we see a lot of upside potential at Durobo, and I believe it's going to be one of those mines that simply keeps producing well beyond initial expectations. So the key work streams for Durobo in 2026, which are already underway, are focused on maintaining project timelines whilst permitting and the final investment decision, or FID, takes place. Feed work undertaken by Lycopodium will mean that equipment and construction tender packages can be prepared and issued in the first half of 2026. This work will enable procurement of key long lead items to start as soon as FID is approved. EPCM tenders have been issued with a site visit taking place next week. We initiated a competitive group process with strong interest from world-class engineering firms with proven track records building gold mines in West Africa. The EPCM submission and adjudication will continue throughout the early part of the year, and we plan to award this towards the end of Q2. Site earthworks will start before the wet season to establish access roads in advance of the early stages of the water storage and water harvesting dates, which are key to retaining and providing water during the project construction phase. To facilitate the early work schedule, work will start on the construction of the camp and permanent village to provide messing and accommodation for the construction teams. If we assume that FID is completed by the end of Q1, the project timeline has construction starting from midway through Q2 of 2026 with commissioning starting early 2028. The first gold pour is expected to be towards the end of the first half of 2028. Again, assuming the FID is reached by the end of Q1, capital expenditure on the project in 2026 is expected to be between $170 to $190 million, with approximately 75% or $135 million of expenditure during the second half of the year. Expenditure in the first half of the year will include land acquisition and crop compensation for the villages affected by the project. So now we'll move across over to Mali and the Siama operation. Sciamma delivered 47.2 kilo ounces during Q4, with a momentum shift after two successive lower quarters, largely due to supply chain issues encountered from the end of Q1. The strong quarter resulted in Sciamma achieving the lower end of guidance with 176.3 kilo ounces gold produced at $2,008 all-in sustaining cost, again within the guidance range. Of note during Q4 was a new ore production record from the underground mine, achieving over 250,000 tons of ore in a single month. This underpinned the strong quarter, as we used alternative explosive products and suppliers to address issues encountered over previous nine months. On joining Resolute, I travelled to Mali on the evening of my first day with the company. During this visit, which lasted three weeks, it was clear the team on site needed strategic leadership to help with decision-making of the complex operation. We've made great progress in this area and we see further areas of improvement in 2026. Additionally, I spent considerable time reviewing contractor and supplier arrangements to make sure we're receiving the most competitive rates. To address some of the challenges, I carried out a restructuring of the management team in the second half of 2025. This started with the general manager of the operation. While this restructure took place, I spent three months on site at Sciamma overseeing the operation and implementing a reset to remove historical inefficiencies, also whilst taking advantage of many opportunities that were immediately visible. The team at Sciamma were bolstered with experienced and seasoned professionals bringing first-hand experience at turning around distressed assets. We conducted an operational review starting during Q3 focused on optimization of the underground assets and cost reduction programs across the whole site. It resulted in a significant drop quarter on quarter as these benefits began to hit the bottom line in Q4. You can see this reflected in the all-in sustaining cost of $1,779 an ounce. This review continues today with the new leadership team and with even more opportunities under evaluation that are expected to deliver shareholder value throughout 2026 and into the future. These ongoing measures, as a minimum, are expected to assist in offsetting inflationary pressures. Four-year capital expenditure was just below the guidance range, largely due to the Siamat Sulphide Conversion Project, or SSCP as we call it, deferring some $5 million of costs with a revised schedule for sulphide processing. This was while we were completing tabacoroni oxide reserves in Q4. The key supply chain issues revolved around transport of products internally through Mali. The largest effects were on explosive products and fuel that needed government escorts. Currently, fuel levels are stable, and to combat the explosive transportation issues we've faced, we've followed our in-country peers and will construct an explosive manufacturing plant at SIAMA in 2026. This is expected to increase operational stability and explosive availability across the operation. Whilst I've been on site at SIAMA stabilising the operations, Chris, the CEO, has been busy working to improve dialogue and build a relationship with the government, meeting with the Valiant Prime Minister in Bamako during Q4. During Q4, we completed oxide mining at the Tabacorone deposit, which lies about 40 kilometres south-east of the Siama processing plant. With nearly all economic high-grade oxide deposits local to Siama exhausted, open-pit ore production will focus on the Siama North A21 district for fresh sulphide ore over the coming years. Siama today has a processing capacity of 4 million tonnes per annum. This is split between two processing plants. The first of which is a 2.4 million tonne platinum sulphide plant which treats the underground sulphide oil. The second, a 1.6 million tonne platinum oxide plant processes open pit oxide oil. The Siamis Sulphide Conversion Project started in 2023 as key infrastructure to allow sulphide oil to be processed through the existing oxide plant. The project includes the installation of a secondary crusher after the primary crusher to reduce the harder sulphide rich material and transitional or prior to feeling the existing signal. A pebble crusher to deal with scans, which is the oversize and discharges from the existing signal. A closed circuit secondary ball mill to treat cyclone rejects and deliver the correct grind size for flotation. A column of flotation cells to recover the sulphide material prior to roasting. Two additional CIL tanks and a roaster upgrade with a new electrostatic precipitator or ESP. which will increase concentrate throughput by over 15%. All of this will allow for the plant to process sulphide feed, whilst maintaining flexibility to still be able to process oxide oil. The SSCP is currently on time and on budget. Stage 1, the oversized pebble crusher and sulphide flotation plan schedule will be commissioned in Q2 2026. The SSCP will then be able to run at 50% capacity, approximately 110 tonnes per hour during Stage 1. As we move to Stage 2, this focuses on the secondary crusher, all-mill construction and the roaster upgrade. This is scheduled to be commissioned and fully operational at Q3. Once fully commissioned, the throughput capacity is expected to increase to 215 tonnes per hour. Slammer production will increase in 2026 compared to 2025. and will deliver between 195,000 to 210,000 ounces of gold at an all-in sustaining cost of between $1,950 to $2,150 per ounce. The gold production is weighted heavily towards the second half of the year, with H1 and H2 representing 42% and 58% of gold produced respectively. This split is due to the ongoing review and optimization of open-pit mining, which will conclude during Q1, As such, mining will be limited to the Siaman North A21 waste stripping with the existing appointed contractor. During this time, existing oxide stockpiles will be processed and sulphide ore will be stockpiled ready for SSCP commissioning in Q2. The Siaman North A21 open pit is expected to mine 1 million tonnes of sulphide ore averaging 2.3 grams per tonne. H1 will be focused on waste and low-grade oxide stripping before ramping into full-scale sulphide ore production in H2. The underground operation is expected to build on the optimization work completed in the second half of 2025 and deliver over 2.6 million tons of ore to the surface. The underground production includes 300,000 tons of development ore, with total development increasing by 74% compared to 2025 and 8.2 kilometers of underground development plant. The highest grades from the underground will be processed, resulting in an average head grade of 2.4 grams per tonne. the lower grade material will be stockpiled, rebuilding the stockpiles that we've depleted during 2025. On completion of the open pit optimization review, oxide mining will take place during Q2 at the Paysands open pit, completing the oxide high-grade reserves of this old body ahead of the rainy season. This oxide will be stockpiled whilst SSCP Stage 1 commissioning takes place and will be processed later in the year. The second and third quarters focus stage 2. By the middle of Q4, sulphide concentrate stocks will be sufficient to meet the processor throughput and as such any further sulphide processing in the SSCP will defer ounces to be poured in 2027. As a result, there's an excess capacity on the SSCP to revert back to oxide and add additional ounces while stockpiled concentrate feeds the roaster. Hence the heavy weighting of ounces in H2 with 12,000 oxide gold production expected during Q4. The current sulphide plant, which receives ore from the underground mine, will process over 2.2 million tonnes in 2026, slightly down from 2025 as a three-week essential maintenance work programme takes place in the second quarter on the primary ball mills and the roaster. Once fully commissioned, the SSCP is expected to lift overall gold production by 5-10% from 2026 levels. As oxide resources deplete, oxide production is expected to decrease over the next two years, with operations transitioning to 100% sulphide processing from 2028. CapEx in Siena this year is expected to be in the region of $120 million, and this is split into three main areas. Approximately $40 million to complete the SSCV and roaster upgrades. Another $40 million of waste stripping in Siena North A21 pit and the underground development. and around $40 million comprising of equipment replacements and maintenance within the processing plant and the underground mine, and additional tailing storage facility studies and construction. A full life of mine review commissioned in H2 2025 is progressing to increase production in subsequent years. We'll report on this in H2 of this year. So we move across to Senegal now and our MACO operations. The macro operation in Senegal delivered an outstanding 2025, achieving an upward revised guidance target of 100.3 kWh at a lower all-in sustaining cost of $1,270 per ounce. The fourth quarter gold production of 18,755 ounces was enhanced by higher than forecast stockpile grades. This strong performance was achieved despite open pit mining activities ending in H1 and transitioning to stockpile material in H2. Naturally, the cessation of mining and processing of stockpiles has seen the overall feed grade decrease over the second half of the year. Processing throughput of 604 kilotons has improved year on year, but also quarter on quarter with continuous improvement. This means that recovery above 91% is maintained, despite a reduction of feed grade to 1.04 grams per tonne and higher throughput rates. This has been achieved primarily by metallurgical testing on coarser grind sizes and optimisation of the gravity gold circuit. All-in sustaining costs have increased in the second half of the year, with Q4 all-in sustaining costs of $1,666 per ounce, as overall gold production reduces with no higher-grade run-of-mine water process, increased royalty payments and non-cash stockpile movements of approximately $143 per ounce. Capital expenditure was limited to $0.3 million in the fourth quarter and a total of $2.9 million for the year. As part of our ongoing commitment to build strong relationships with the governments of the countries in which we operate, Chris also met with the President of Senegal in Q4. The Mako Life Extension Project, or MLEP, has the potential to extend the current Mako mine life up to 10 years. The MLEP encompasses two main areas, the Tomboronkoto and Bantako deposits. The exciting discovery of the Tomboronkoto deposit, approximately 20 km from the Mako mine, has a current resource of 377 kWh, with an average grade of 1.7 g per ton. The Tomboronkoto ESIA has been pre-validated by the Senegalese technical agencies and is pending ministerial approval. Importantly, this has been supported and approved by the Tomboronkoto village and surrounding communities. The Resettlement Action Plan, or RAP, and the DFS is nearing completion and the cut-off date, the point at which no further compensation can be claimed, has passed. A full survey of the affected houses and livelihoods has been completed and is now crystallised for the purposes of this project. The overall process has been completed with detailed approach to stakeholder engagement, underscoring our commitment to regulatory compliance, transparent community consultation and responsible project execution. The application for the Tamborokoto mining permit will follow the issuance of the environmental permit, with all permitting anticipated to be received by the end of 2026, assuming no major revisions are required. When we receive the mining permit, we will have the authority we need to implement the WRAP and initiate the village relocation work. We expect detailed engineering to start during Q2, with long leave items procured before the end of 2026. That means mining at San Borancoto is scheduled to start in the second quarter of 2028. Two additional deposits are currently being explored at Bantaco. The Bantaco South and Bantaco West deposits have recently published resources totaling 266,000 ounces at 1.1 grand per ton. During 2025, infiltrating technical studies and metallurgical analysis work streams were progressed, with $4.1 million of capital expenditure on this part of the project. This included progressing the ESIA submission and community engagement activities, which are far less onerous than at Tambor and Coto. 2026 work streams for Bantaco are related to technical studies. Additional infill drilling was required and progressing the permitting process. Subject to full economic analysis, Bantaco ore delivery is scheduled to commence in Q4 2027 to bridge the gap between the completion of Mako stockpile processing and the start of ore delivery from Tambor and Coto. Total capital expenditure on the MLEP is expected to be between $10 to $15 million during 2026. MACO production will decrease compared to 2025 as stock gold material is processed in 2026 and deliver a guidance of between 55,000 and 65,000 ounces of gold at an all-in sustaining cost of between $1,600 to $1,800 per ounce. The all-in sustaining cost increase is a reflection of the lower stockpile grades processed within an inflationary environment, including higher royalties due to the higher average gold prices expected in 2026 and compared to H2 in 2025. Gold production is slightly weighted to the first half of the year, with H1 and H2 representing 52% and 48% of gold production respectively, although it's important to note the potential variability when processing stockpiles. 2.2 million tonnes of ore is to be processed in an average grade of 0.9 grams per tonne, with gold recoveries above 90%. Mako currently has sufficient stockpiled low-grade ore to continue processing to the end of 2027, albeit grades will decrease as processing moves through low-grade to the mineralised waste stockpile. And with that, I'll hand you back to Chris to talk through the exploration activities.
Thank you, Gavin. And now let's move to talking about exploration. Exploration continues to be very important to the business strategic priorities moving forward. As you can see on slide 21, in 2025, we spent just shy of $25 million on exploration activities with considerable success. Of that $25 million, roughly $15 million was spent in Senegal, $5 million in Cote d'Ivoire, and $5 million in Mali. Some of the key achievements in 2025 was an initial MRE at Bentaco, as well as continued exploration activities at the Davao and Darobo. But however, when we look at 2026, we will plan to continue to spend around the same amounts of money, but a focus more on Cote d'Ivoire versus Senegal, as the bulk of the drilling in Senegal has been completed. We will continue, though, in Senegal to spend some money at Bentaco and Tombo with regards to infill exploration drilling. Like I said, the bulk of the cash expenditures for this year is going to be focused at Cote d'Ivoire because we see real value at the ABC and the DAPA projects. But I'll go to that in more detail in upcoming slides. The other key area of focus for the business, which has been forgotten about, is in Guinea. We do have a number of permits in Guinea, but we have been looking to apply for new permits. And I will be very proud to say that we did receive first reconnaissance authorizations for a number of permits in the Segura Basin, which we'll start spending time and effort in 2026. So when I look at the triangle on the right side of the page, This shows that we are developing a proper pipeline to developing the fourth asset within the Resolute business. So, again, exploration is core to our success, and we are spending quite a bit of time and effort in developing additional projects within the portfolio. Moving to page 22, I want to spend a bit more time on our ABC exploration project in the west side of Cote d'Ivoire. When you look at the map, ABC actually is comprised of four key deposits – There is a Farrakhan and Nafana permit, which you can see in the very north part of the deposit, the Kona permit, the Windu permit, and most recently, the Bonanza permit. The bulk of the initial resource is all situated on Kona. That's where you see the 2.2 million of inferred ounces at 0.9 grams per ton. In Q4 of 2025, we started an excessive drill program across all four of those deposits, where we're seeing very exciting results. So the Farrakhan and Nafana permit, which is in the north part, We got some very exciting drill results whereby we saw one hole that had 31 meters at 2.4 grams per ton from 13 meters from surface. We also started drilling in Kona to expand that deposit with very strong drill results. And this year, the focus will be to drill at least 20,000 meters across the four different areas in order to expand this footprint. We are there looking to put economics on this project, and we've commissioned a scoping study, which we hope will be released towards the end of H1 2026, but possibly to H2 of 2026. So once those numbers are completed, we will release those to the market. Similar to the ABC project in Cote d'Ivoire, we're also very excited about the Ladabo project in Cote d'Ivoire. This is a project that's about 400 kilometers to the northwest of Abidjan, which we acquired in 2024. so we spent quite a bit of time and effort in 2025 drilling out this deposit and we had a very successful mre of about 643 000 ounces at 1.14 grams per ton that was issued in q4 and that was after 16 000 meters of drilling completed in 2025. when you look at the map on the right side the resource is focused on the northeast area of the deposit in the G3S and the G3N zones. Those zones show gold that continue at depth and at strike, and so in 2026, we will start doing a bit more drilling to prove out the size of that deposit and continue to expand. We also see some interesting anomalies at the G1 area, which is kind of in the middle, and so we're going to be spending time drilling that deposit out as well. So, the goal is to try and make this to at least 1 million ounces, but also it's very similar to ABC. We will be looking to implement a scoping study report towards the end of H1, 2026, possibly and into H2, which will demonstrate the economics of this asset. So, look, in summary, I do believe that between the DABO and ABC, we have been making this for a fourth asset, fourth producing asset, I should say, within the residue portfolio. So, with that, I'll turn it over to Dave Jackson to go through the financial summary.
Thanks, Chris. Today, I will walk you through the Q4 and full year headline financial results, highlighting the key performance metrics. Overall, we ended the year strong and our Q4 metrics were in line with expectations. We continue to strengthen our balance sheet and build cash in the business. Looking at the financial highlights, our year-to-date EBITDA was an impressive $383 million, which was a substantial increase from the $319 million reported in 2024. This performance was underpinned by revenue of $863 million, generated from the sale of 259,000 ounces of gold at an average realized price of $3,338 per ounce. As previously noted, Resolute remains fully unhedged and continues to sell all of its gold at spot prices. At quarter end, net cash stood at $209 million, marking a $72 million increase from Q3. Included in the net cash figure is $135 million of unsold bullion, representing nearly 31,000 ounces of gold that were sold shortly after the quarter closed. We had $57 million drawn on overdraft facilities at quarter end. These facilities continue to be used locally to optimize working capital. Currently, the group has in-country overdraft facilities of approximately $113 million available as we continue to maintain financial flexibility for the group. The group all-in sustaining cost for Q4 was $1,877 per ounce, which represents a $328 per ounce decrease from Q3. This decrease was primarily driven by the expected increase in gold production at Syama. At Syama specifically, the all-in sustaining cost was lower than Q3 due to higher production and lower sustaining capital expenditure. As already mentioned, we have successfully navigated the supply chain disruptions in Mali, which resulted in Q4 being Siam's second strongest production quarter in 2025. Let me now walk you through the key components of our cash flow summary that led to the net cash position of $290 million at the end of Q4 on our next slide. We generated a solid $86 million operating cash flow during the quarter and $314 million for the full year. This was a substantial increase from the comparable periods in 2024 and is mainly attributed to the increase in gold price throughout the year. CapEx totaled $118 million for year-to-date. This includes $24 million spent on exploration, $70 million in project capital across SIAM and MACO, and $24 million spent on the SSCP. Overall, CapEx and exploration spend were within guidance. As previously noted, we made the initial $25 million payment for the acquisition of the Duropo and ABC projects during Q2. These projects represent exciting growth opportunities for the company and are expected to deliver meaningful long-term value for our stakeholders. BAT outflows in 2025 totaled $66 million across Mali and Senegal. We are pleased to say we obtained $34 million of BAT mandates in Senegal in 2025, which were used to offset government payables. However, VAT remains a source of cash leakage in Bali, and we continue to engage actively with the local government to recover these amounts. Our recent discussions have been positive, and we remain encouraged by the progress being made. Moving to working capital, we recorded a $29 million inflow for the year to date. This was driven by a $6 million reduction in consumable inventory across the group, a $10 million reduction in stockpile balances at both SIAM and MACO, and a $13 million change in supplier payments, which are settled in the normal course of business. Our ending cash and bullion was $266 million and marks a $165 million increase from the beginning of the year. This leaves us with ample available liquidity of over $322 million at the end of December. As noted on our last call, we have a stake in Longcore Gold worth approximately $31 million, which is currently being sold. We expect to receive these funds in Q1 this year, and we expect no tax impact on the proceeds once received. Supported by a strong cash position and ample liquidity, the company is well-placed to fully fund its 2026 capital expenditure requirements, including Doropo, through existing cash balances and the anticipated strong cash flows in 2026. We are currently in discussion with debt providers to secure additional capital for the Duropo project, which we are expecting to be finalized in 2026. The timing to secure any financing will not impact the Duropo timeline, as we expect to begin construction as soon as the permits and FID are obtained. In summary, we're in a very solid financial position and are excited about the growth potential of the business. With that, I'll hand it back to Chris.
Thank you, Dave. And look, just a couple more slides to wrap up the story. First, let's start on page 28, which just qualitatively highlights some of the key milestones we're expecting in the next few years. Let me just focus on 2026. So going first and starting in Cote d'Ivoire, the most important is we expect to get the mining permits and FID for the Europa projects in the coming months. That will then obviously formalize and kick off the construction period for the Europa, but I think as provided by Gavin, We're not slowing this down, and we believe we have the financial resources to execute the construction of the project without missing a beat and initiating full construction and initial commissioning in the beginning of 2028. In addition, we're going to provide economic studies on both the DABO and at ABC. Moving to Mali, we will be commissioning the SSCP and transitioning to almost 100% sulfide production and completing an optimization study. And then when looking at Senegal, the key activities revolve around permitting of both Bentaco and Tumble projects. So we anticipate that we'll kick off those permitting applications in 2026 and we'll keep the market updated. So we have a lot on our plates. We're very excited about what we're doing. We also see tremendous opportunities to continue to drive cost reductions across the business, and continue to develop and build our relationships with the governments where we operate. So in summary, again, very proud with what the business achieved in 2025. We achieved our production guidance. We managed our costs across the business. We generated a substantial amount of cash flow in the business, although with the support of a rising gold price environment. But most importantly, we executed our strategy of becoming a geographically diversified producer through the acquisition of the Duropo project in Cote d'Ivoire. We also made substantial improvements in exploration by focusing this as a key strategic priority for the business. I made a number of executive changes and augmented the skill set of people within the business, which is incredibly important to any mining operation. So with all the pieces that we've put in place, I'm very confident that we'll have a very successful 2026. But most importantly, we're well on track to becoming a half a million ounce producer from 2028. So with that, I will turn over to the operator for questions. Thank you very much.
Thank you. We will now begin the question and answer session. If you are dialed into the call and would like to ask a question, please signal by pressing star followed by the number one on your telephone keypad. We will pause for a moment to assemble the cues. We'll take our first question from Justin Chen with SEP. Please go ahead.
Hi, Chris, Dave, and team. Thanks for hosting the call. My first one is just maybe just clarifying the explosive situation in Maui. I read that you're planning to put in an emulsion plant and that the explosives are no longer an issue. And I was just wondering, I mean, for a bit more detail, do you have a stockpile now? And then what's the timing on the plant? And can you just give us a bit more color on that situation and I guess how it evolves through the year?
Go ahead, Dustin, and thanks for the question. Maybe just easier, I'll just turn it over to Gavin. He can probably give a bit more color than I would.
Thanks for the question. So basically our strategy at the moment is the explosives that are coming into sight have to be escorted in by the Malian government forces, obviously given the security situation in Mali. What's been happening is the government have been in talks with our team in country to effectively set up a brigade to support the mining operations. So we're getting a lot more escorts into the site now. So currently the stocks on site are good enough for us to continue production and obviously be a little bit more relaxed in terms of the issues that we have had previously. But further to that, we have been in discussion with different suppliers to effectively build their own plants on site to be able to produce the products we need going forward. So we have had a successful discussion with two suppliers on that and we're waiting for final proposals to come in ahead of building these, but we expect these to be constructed within 2026 and obviously bringing in raw materials that are precursors to explosives, will not be subject to the escorts from the government, which makes things a lot easier. So that really should solve that issue that we've had with explosives throughout 2025.
Gotcha. So perhaps to paraphrase, so the near-term issue is resolved because you have these convoys that are more frequent and the supply frequencies increased and then The Emulsion Plan is more of a longer-term solution, but timing on that in 2026 is to be determined.
Yeah, exactly. That's a good summary.
Okay, perfect. Thanks very much. And then maybe just on Mali more broadly, I mean, there's been a couple of major developments. The, you know, Barrett coming to an agreement with the government on Lulugankado. And then... I mean, there was a lot of press on the fuel blockades, et cetera, around November last year. It seems like that situation has improved quite a lot, it sounds like. And I'm curious on the situation with Bayer coming to an agreement with the government. I think four companies were having a hard time implementing their already agreed terms just because the government was preoccupied. Maybe could you give us an update on what you're seeing, country, on both those fronts?
Yeah, so Justin, I think what we see is similar to the others, that the mood has changed dramatically versus 2024, and a lot more positive and constructive. We do believe the situation with Bayer coming to resolution is good for the industry and good for Mali. I think the government understands what has happened and why, and they're trying to work with the remaining operators to try and keep it more stabilized. there was obviously a bit more noise on security at the beginning of q4 that we've seen corner reverse so it's unfortunate it's a bit more of the same um we are continuing open dialogue and constructive dialogue with the governments and trying to educate them on how we can work together for future investments that's why we're doing the phase two studies that we work with the government demonstrate that you know if we can work together we think that there's there's growth in our business um but unfortunately a bit similar to 2025 i'm still cautiously optimistic we're still very cautious that you know we need to see a bit more signs of reversals one of the key activities that we have not been receiving are vat refunds back and i think that's that's a key milestone i need to achieve for future investments um but generally the mood is much more positive and continues to head in that direction um but it's still delicate um so look i would say just to summarize security is probably
in good shape um and as fuel hasn't been an issue because we're working very closely again with the government to get the convoys and for our our mind to be fed which has been not impacted but it's still it's still delicate gotcha thanks chris no i appreciate that that's really helpful color and just one last one i'll free up the line um just clarifying with regards to the capex and exploration uh macro this year so the 10 to 15 quoted in CapEx, that's for studies and that's independent of the exploration budget for MACA this year?
That's correct. The bulk of that is study work. We will do, like I said, a bit more drilling on Ventaco, less on Tombow because we've pretty much completed that. And we'll spend more if we find more areas to explore and to expand on. But the key is to get the studies completed so that we can file for mining applications. And then depending on how we see our cash needs in 27 and 28, we may open up a bit. We're going to also look. We have two other deposits in Senegal, Singola and Romania, and we're going to do some work there. But with the resources we have, we're going to focus more on Cote d'Ivoire.
Okay, gotcha. And that will be primarily studies. It's not for, say, early site works or relocation.
There is some capital towards the back end of this year, depending on the timing. If we receive the mining applications towards the end of the year, we'll start doing some, we'll call it early site works, and mostly it's around the relocation process at Tombo. So there's probably about $3 million to $4 million anticipated in Q4 2020. for assuming we get you know exploitation permits coming in as expected but if that may change get pushed into 27. okay perfect thanks thanks really appreciate it thank you our next question comes from the line of jasper main ring from baron bird please go ahead hi guys uh thanks for the updates i just had two quick questions
Thanks for the granularity on the CapEx at Sciana this year. I just wanted to ask how we should think about that CapEx going forward after this year's $190 million spend?
Yeah, so good morning. It's a good question because I know it's harder this year because we have decided to put a bit more capital into effectively into the plan because look, the plan is 30 plus years and also we need to do a new TSF. So that's why there's additional call it 40 million of what we call capital projects. That is probably more of a one-off. I would say next year, 2027 will be probably closer to 30. And then, look, we have, like I said, more than $40 million this year in waste stripping, with a lot of that, half of it being new stripping at the 21 CM North Zone. So I'd say, look, moving forward, the run rate capex is closer to $30 to $50 million. So probably a bit on the higher end for $27, and then it'll start to stabilize in that $30 to $40 million thereafter. okay great thank you um and just as a follow-up uh why just wanted to ask why sales at chiama lagged production volumes in q4 and did they get sold in early q1 again so look in summary we had just about 30 000 ounces of gold bullion 31 000 to be specific at the end of the year it has to do with the fact that the 31st of december was on wednesday and we tend to ship our gold on fridays And so we built up stock around two weeks worth of stock. So all of that gold was then shipped effectively in the first 10 days of January. So look, we'll have, that wasn't a key impact to the lower EBITDA versus overall guidance. It's just that some of those gold sales were pushed into January, which will impact the 26 numbers.
Okay, great. Thank you very much. I'll hand it back to the line.
Our next question comes from the line of William Jones with Danica Genuity. Please go ahead.
Good evening, Christian. Congratulations on a pretty good quarter. Most of my questions have been answered, but maybe just one on trying to understand the grades going through the plan at Seattle Post 26. I know you quote sort of a 5% to 10% step up, but I gather that grades are going to be impacted just by oxide feed. So just if you could provide some colour on the grade of those oxide stocks going into the plant over the two years and if that will step up towards the reserve grades once those stockpiles are used, probably firstly. And then secondly, just a bit of the strategy around utilising those stockpiles
Yep, thanks. Well, maybe, Gavin, over to you on that one. Obviously, as we're reviewing the mind times.
Yeah, thanks for the questions there. Look, on the Siama grades, obviously the sulphides that we're seeing are reasonably good grades coming out of that Siama North A21 district, and we expect those to improve as we go forward. They're sitting around sort of 2.3 at the moment for this year. There will be ups and downs in that as we go through the mine life, but we think reasonably around 2 grams per tonne is acceptable for for what we'd be looking at at the moment. And then the underground, realistically, the grades will drop off towards the end of the mine life. But certainly over the next few years, they're sitting around that sort of 2.4 grand per tonne as we go forward.
OK, thank you for that. And then just interested on... Look, I appreciate how much you can say on this, but how you're thinking about the funding or capital stack for... and, you know, is there any target leverage perhaps that you're thinking of?
No, it's a good question, and it's an evolving question, to be honest, because of the cash flow generation that we're generating in the business. So as you saw from Dave, we have today over 300 million in liquidity. At today's gold price environment, we're generating anywhere from $30 million to $50 million of fresh cash every quarter. So that puts us in a very strong position to actually fund the bulk of the CapEx with our own resources. But we think it's prudent to put in some debt. and because we will need some cash in the future for the MLEP program. I would say, you know, we're looking at kind of a 50-50 target split between equity and debt, but it may be a bit more equity depending, when I say equity, our cash versus debt. It all comes down to the cost of capital and that debt. But what's really important to us because of the cash regeneration business and we're not a developer is that we're putting a debt facility that's very flexible that allows us to pay that back quite quickly without too many penalties and costs. um and look we've been innovated with term sheets for funding of the ropa because of the tractors of the project and where it's located in the world and again similar to what dave said we're we're working through these so we're not in a rush because we have quite a look everything's going on track as we expected and we'll probably look to put something in place towards the end of h1 maybe into early h2 because in any case we'll be using our cash to fund the front end of the project
Thank you very much, guys. I'll pass over.
Once again, if you would like to ask a question, please press R, followed by the number one on your telephone keypad. Our next question comes from the line of featured mics with Baron Jovi. Please go ahead.
Hi, Chris. Thanks for the call. Just one on ABC. It feels like it's a bit of a sleeper in the portfolio. You mentioned... there's a scoping study that you're targeting to get out in H2. How quickly do you think you could turn that around into a DFS and ultimately an FID decision?
Look, I think realistically that would be towards the back end of 27. look and i agree with you it is a bit of a of a sleeper in the group it's a fantastic asset and it's it's a very large footprint that we have um so depending on the economics of the scoping study we can try and fast track it but there is infill drilling that needs to be done and because there's various deposits on the permit we would need to think about where we would start and how we would kind of build that line because um it's it's a good problem to have but they're different the ore bodies are quite different in each of the different zones that we have so we just need to understand that a bit better but we see significant strategic value in abc and how it's continuing this with other deposits in the area so there's definitely in mind at abc that will be built at some point in time yeah okay thanks um and maybe just sorry just one more on um the robo the
170 to 190 of capex you're targeting for this year. I'm assuming all of that comes out of the 516 total capex bill for the project.
That's correct.
Yeah, okay. Cool. Great. Thanks, Ruth. Thanks, Richard.
Thank you.
At this time, we have no further questions. This concludes today's call. We would like to thank everyone for their participation. You may now disconnect your lines. Have a nice day.