2/26/2026

speaker
Emma
Moderator / Investor Relations

All right. Welcome, everyone. Good morning. Welcome to Strike Energy's first half financial year 26 webinar. We've got Peter Stokes, our managing director and chief executive officer, and Tim Cooper, our chief financial officer, joining us today. I'll hand over to Peter for an introduction and Tim will take us through the financial results before I hand back to Peter for an operations review and then we'll do some Q&A at the end with the time remaining. Peter, over to you.

speaker
Peter Stokes
Managing Director & Chief Executive Officer

Thank you, Emma. Good morning, everyone, and thank you for joining the call this morning for the first half results. I'm really happy to have you join us and we're Happy to take questions at the end. There have been a number of questions that have come through the hub and online and via text over the last couple of days. So we'll address as many of those as we can. And those that we're not able to, we'll certainly provide some additional responses to as well. I recognise, and this has come through a couple of the questions that we haven't provided a lot of communications over the last couple of months other than more of the sort of regulatory updates and certainly announcing we're hearing West's SPUD due in early April. Part of the reason and the key part of that is that a number of the discussions we're having, particularly around a couple of our major projects, are commercially sensitive. As soon as we have further information that we can share, and we will certainly do that. Over the next couple of months, we'll also start the drilling at Way West. So there will be a continuous updates coming from that drill as we work through that program. And also as we move through some of the other programs, particularly into commissioning of South Arigala Power Plant, there'll be a number of additional communications and I'll talk through some of that timeline and towards the end also talk through some of the key milestones that we are working towards over the next couple of months. And I'd like to hand back to Finn now to take us through financials before I go through the operational side of the business.

speaker
Tim Cooper
Chief Financial Officer

Thanks, Peter. Welcome everyone on the call this morning. Thanks for joining us. I'll start with operations and production at oil-yearing totaling 3.8 petajoules for the half. This is down on the same period from last year as we managed production alongside the purchase of third-party gas. This is the best one-inch commitment We achieved an average realised price of $7.37 a gigajoule, resulting in revenue of $36 million and operating cash flow of $3 million. We closed December with a cash balance of $69.5 million and debt draw on the Macquarie facility of $108.8 million, reflecting a net debt position of $39 million. The debt has been utilised for the project execution of South Yarra Gulla peaking power plant, which is 77% complete and with capital expenditure in the period of $87 million. Total capital expenditure for the period of $99.5 million, which in addition to South Yarra Gulla project included Wallyering Compression, West Yarra Gulla and Wallyering West 1. You will have noticed the material uncertainty included in the audit report, the half-year financial report. And this refers primarily to uncommitted $15 million tranche within the Macquarie financing facility, and the forecast completion of the South Yarra-Gallup peaking power plant. The uncommitted nature of this facility has not changed from previously reported. However, it is subject to Macquarie Credit Committee approval at the time that striking tends to draw down on that balance. We're engaged with Macquarie on a regular basis and do not foresee any concerns with the appropriate approvals being achieved in due course. The South Yarra Gallipower peaking project is a key objective for the company and is envisaged to generate significant cash flows. Therefore, its delivery on schedule and on budget is an important outcome for the business. Further, management continues to manage capital expenditure in a prudent manner and ensure that the best returns are generated for shareholders. Thanks, Peter. Back to you.

speaker
Peter Stokes
Managing Director & Chief Executive Officer

Thank you, Tim. Now going through the operations side of the business. So a lot of questions have come around West Arigala. We're continuing to progress with West Arigala with a number of commercial opportunities, both on the midstream, we're looking at options with our joint venture partner and certainly in the downstream and then midstream processing, we're looking at a number of options there. We're also finalising the pre-FID activities with our joint venture partner. But that said, we've already progressed a lot of that with drill availability, long lead items, and approvals well underway to commence that work once we agree with the joint venture partner exactly what we will do pre-FID. South Arigala, Tim alluded to, continues to progress extremely well. We're now nearing 80% complete overall. and a number of key components, the engine shed and facilities within the shed are nearly 100% complete now, and I'll go through that in a bit more detail. At Well Yearing, we continue to produce successfully through the last number of months. We had a short shutdown, planned maintenance shutdown prior to Christmas to install the heat exchanger, and that's done very well. And we're now working through the process looking at how much we'll ramp up that facility again ahead of doing the drilling at Way West. And then on the exploration front, we continue to plan the next stages of exploration, including the potential for a well at Ocean Hill and 3D seismic across the broader South Arigala area and Katathini, which we're looking at for early next year. and we're commencing the approvals processes that will enable us to do that. Going into West Arigala in a little bit more detail, as you'll be aware, the West Arigala asset has been included in the AMOJSU as part of the required supply for West Australian domestic gas into the future. It is a key focus for the West Australian Government to have this asset developed and we are certainly working with our joint venture partner to drive that process together and looking at how we develop the upstream and then ultimately work through the various downstream options for both parties. We are working towards finalising the independent reserve and resource estimate and still targeting to have that before the end of the quarter. And that's progressing well and we expect that to reinforce the scale. of the West Arigala broader assets across the West Arigala area in L25 and Arigala Deep in L26. And that will also continue to provide further guidance around some of the work that we'll be doing in the pre-FID activities. It's an extremely large value accretive development, and we want to make sure that we drive the best commercial outcome for Strike and our shareholders. and so we are working through that process to ensure that we maximise the value in the most efficient timeframe as well. Moving on to South Arigala, you'll see on the right-hand side of this is the photo of the shed now completely sealed with the engines installed and all of the filtration systems on the left-hand side as well. The power station is now 99 per cent complete, as I said, We've had the provider of the yenbacker units, Clark, start the commissioning, and that will get underway fully from next month, and we'll have first gas from running through the plant towards the end of April, where we start to be able to do the low bank commissioning of those facilities. We're continuing to work through other key packages of work, which you'll see on the next slide as well. And we are seeing really positive increases in the benchmark reserve capacity credit, which continues to provide an increasing underpin for that facility and starting to work closely with Western Power on the key commissioning, which commences with them over the next month or so. So we continue to engage with them actively and are working with them to complete the works now. And you'll see on the following slide The CRY switchyard, which will be handed over to Western Power with the steel pylons already in place. The large relay room being delivered to site and is now in place. And our 52 poles that run from the power station down to the Western Power area are now complete and they will and will continue the last leg of the power line, the one and a half kilometres that connects us into the Swiss at the end of our facility. We're still on target for 1st October operations. There are a number of processes that we work through, including the Western Power Commissioning and AEMO credit application process, and we'll see that in the key milestones later on in the pack. We're well on track to be doing that. And as it says here, we expect the mechanical completion and then gas induction into the facility later in early Q2. and that will enable us to start running up the system over the next several months and do the end-to-end testing ahead of the AMO accreditation process. On to well-yearing, I mentioned that we are continuing to progress well with the well-yearing project. We released recently the intention to spud the Way West well. That's now locked in to start in early April. Earthworks are well underway on site. We have the pad now being developed, the drill rigs lined up and will mobilise in the next couple of weeks. All of the materials were ordered last year and we'll be able to start that in April with an expected drilling time of around six weeks to enable us to do testing. We've already done a number of the works ahead of a tie-in pipeline that'll enable us and target a early 27 connection on success of Way West. But as we've said in previous presentations, our financials are not subject to Way West being successful. To be prudent, we've planned that that is not. But however, as a business, we're very actively driving to make sure that we're ready to connect that gas on success. As Tim said, we've continued to deliver significant volume of gas in the half of 3.8 petajoules and generated some $36 million of revenue. As we were working towards installing the heat exchanger late last year, we scaled back some of our production and took the opportunity to buy gas in the market and still provide that to our customer where we were still in the money on that gas. We continue to ensure that we've got the right balance of commercial and production and are working now towards, on the next slide, the compression units which are now installed on site are being commissioned over the next couple of months and they will come online towards the back end of Q2 as they're required for the production at site. And at the moment, we're looking like we'll ramp up over the next several months. That's just to be confirmed over the next month or so as we run the heat exchanger for a bit more time. And really looking forward to the drilling program. And as I said right at the start, we'll make sure that we continue to provide regular updates around that program as we would start work with the Ensign 970 rig that we've used previously in the business. Moving to Ocean Hill, during the half we also announced the results of the 3D seismic work. We've been working over the last period to identify a drill, initial drill location and have now landed on that position. We've been working through the regulatory approvals and land access and during the next quarter or so we intend to be able to provide some further detail on likely timing for the well that we propose to do down at Ocean Hill. But based on that 3D sizing, as we talked about at the time, the resource there looks very attractive and certainly something that we want to pursue and also continue to drive what is underpin strike over a long period of time, which is exploration success. So we're looking forward to working through that process. On Katathini, the very attractive large resource that we have or understand to have out to the east of South Arigala, we are working towards approvals for a 3D seismic across this area. And we expect to be able to get that over the next several months with an intention to run seismic post the farming season when we can get access to all of the paddocks up there. and be able to run the seismic, a comprehensive 3D seismic across that area. Over the last several months, a number of other seismic surveys have been released into the market that we're able to include into our modelling around South Arigala. But we also want to take that into the southern area, so we have a proposal to do a, which will be called the Minjuni 3D seismic, which will cover the South Arigala area and identify additional drill targets for that to ensure that we are able to monetise the 45 or so TJs that we expect in that resource. Moving to strategic priorities, one thing that we have provided some updates on is the West Australian market. The government continues to push us and others to provide domestic gas into the market and provide, ensure that we have, that we can fill some of the gaps that are starting to emerge towards the back end of this decade. And similarly provide firming capacity with our gas fired generation. So we continue to engage the government regularly and closely around the planning that they require around additional power beyond the 85 megawatts that we currently will have online, and looking at opportunities to bring that into the market, particularly as you may have picked up the reserve capacity benchmarking prices continue to increase. We expect to see that probably level off as additional battery and wind comes into the market, but the gas-fired power generation provides a key part to that renewable transition in that it provides the firming that as the coal-fired generation drops off, that will be missing from the market. And there's an opportunity for us to provide both the gas-fired generation, but also specific firming capacity in the form of synchronised condensers that enable to provide stability into the network well into next decade. The near-term reflection or key sort of milestones that we are working through over the next couple of months, or next, sorry, till the end of the year, but particularly a couple of us right in front of us, certifying the West Arigala and Arigala Deep resources. We're working to have that, as I said, no later than the end of the quarter, but we're working to try and bring that forward. And as I said, we expect that to continue to reaffirm the scale of the West Arigala resource. The South Arigala plant will have the benchmark reserve capacity credits for the 28-29 year confirmed before the end of this quarter as well, and that will see, we expect based on the draft numbers, a further increase to nearly $492,000 a megawatt, which is up from the $360,000 the previous year. and the $220,000 that we had in our FID analysis. Wearing West will be spotted in early April, so we're targeting around the 9th of April as the date that we will do that. As I said, construction of the pad, road access and mobilising of the rig is well underway. and that rig will be on site at that point and then we'll be ready to start doing what we've already done, some of the early works for some water pools and other things on site. The Way West test we expect to be done by the end of the quarter and we'll be able to continue to provide updates to the market on that as well. Practical completion of the power plant will occur around the end of the second quarter and that will be as part of the commissioning that we work through with Western Power and then as we work through the accreditation with AEMO for the reserve capacity credits which will kick in from 1 October. I should say also that as we work through that commissioning and generate power, Any power that we put into the grid, we also will be able to charge for that power and start to generate revenue for the power plant ahead of the 1 October reserve capacity credits. And the South Arragela plant is still on track for start-up and full operations on 1 October. And as we work through that with Western Power, we have confidence that we're still on track for all of the works that need to happen. Key components of the plant, as I said, are certainly well progressed now and will be signed off over the next couple of months ahead of doing the run up of the generators over in April once we have gas connected. We have run the packing loop of eight kilometres that we've run down to one of our other wells so that we've got capacity sitting there to start up the generators for peak power. So really exciting project coming to a critical part of that project now. And then we expect that the reserve capacity credits, why we'll have what will be called a temporary reserve capacity credits, That gets formalised a month or two after the power plant goes live, but we will be able to claim those reserve capacity credits from 1 October. And then one of the other things, you know, critical for us is the FID decision for West Arigala. And we're looking to still do that in the back end, before the back end of this year, subject to working through some of the downstream processing and certainly finalising timing around pre-FID activities, but we're doing everything we can to accelerate that from approvals and other parts and certainly ensuring that we and our joint venture partner have the right commercial options to take that forward. But there are a number of areas that we'll continue to explore for how we might exploit the gas out of that really, really exciting resource. So, strategic priorities for us continue to be delivering what we said we're going to do. So, we need to focus on delivering the South Arigello Power Plant, and as Tim alluded to early on, we have to deliver that project on time and on budget, and we're confident that we are on track to do that. We will need to generate that. That additional revenue will enable us to start to do some of the other activities that I spoke about around exploration, moving into some of the other areas like Catatheny and Ocean Hill, but also starting to ensure that we're exploiting other opportunities, getting ready for West Arigala development and the like as well. The activities there will only increase as we move towards FID and beyond. We're optimising the wet earring production profile and looking at options at the moment to increase the production out of that field again, which will enable us to generate more highly profitable revenue. We've been able to run two of the other wells over the last several months, so way six and way seven are producing. Way seven, we've been doing some additional trials and it's producing good gas and a lot of condensate, so we're managing the levels of condensate so that we can run that or send that condensate to South Australia for processing. We're very focused on a disciplined cost pace across the business. We're always looking for ways to optimise our costs, but also deliver value with the resources and capability that we've got in the business. And it's critical for us that we continue to do that. We're very focused on a defined way forward on West Arigala and having a clear pathway that we can share with the market and clearly understand it has a huge impact for all of us on share price for the business and a key part of the future of the strike business. And so it is an absolute focus from myself and Tim and the commercial team and our legal teams as well to ensure that we are driving that process forward. It is something we're working on every day. But I think importantly underpinning all of that is continuing to drive what Strike is known for, which is a successful exploration pipeline and delivering along on some of those key assets that I talked about, including further exploration on our current assets, but also moving into certainly looking at the opportunities for developing the Cat Athene and Ocean Hill leases that we have as well and making sure that we are getting the best out that we can out of the extensive portfolio that we have across the Perth Basin. And I should say, you know, I think, as I said, when I first joined, I'm extremely excited about the opportunities that we have in the business to develop these assets. It may feel like things are going slower than you'd like, but I think for us, ensuring that we firm up our revenue from South Arigala and well-earing is critical to enabling the future in the business and ensuring that we can efficiently deliver West Arigala and then take advantage of the exploration opportunity in front of us. On that note, thank you for everyone for attending. I'll hand back to Emma. to take us through the questions. Tim and I and Emeril will answer those. Please keep sending through your questions if you have any, and we'll address those as best we can. Thank you.

speaker
Emma
Moderator / Investor Relations

Great. Thanks, Peter. I might start off with one that we've been having a few questions on lately. And we did address it in the report, but perhaps not so much in the presentation. And that's the purchase of the pilot land. If you want to maybe elaborate on that a bit for people.

speaker
Peter Stokes
Managing Director & Chief Executive Officer

Yeah. Thanks, Emma. So the pilot land that we bought is immediately to the north of the South Arigala Acid. It was a The power line that we run to Western Power runs through that pilot land or the Heitman farm. And so we wanted to make sure that we secured that asset to enable us or the option on that to enable us to ensure that we could provide the easements to Western Power, but also certainty over ours. It also sits strategically between a couple of our assets and gives us some other options as we look for future development across the key assets.

speaker
Emma
Moderator / Investor Relations

Yeah, great. And maybe another one that we've been getting quite a few questions on and there's a lot of interest is perhaps you can talk a bit about what Hancock's proposed Bellisama gas plant might mean for strike.

speaker
Peter Stokes
Managing Director & Chief Executive Officer

Yeah. Yeah, I mean, I think for us, you know, the addition or the announcement of the additional plant is really exciting for the basin. I think for me, a couple of things that are important, having Now seeing Waitsia up and running and ramping up certainly changes the context in the Perth Basin. There was a lot of angst about could that plant be up and operating given the delays? I think that was one big milestone. I think having a large partner like Hancock announcing a significant plant in the basin too continues to provide real certainty around the infrastructure that will be in the basin. a very good option for processing of the downstream gas from West Arigala. You may be aware it sits almost adjacent, some four or five kilometres north of the West Arigala asset. It's a significant power plant. and it's progressing well. We continue to talk to Hancock about options with that facility and they actively continue to develop their assets to the north of us as well, which is only positive for the basin and having options around infrastructure I think is critical for us to ensure that we drive the best commercial outcome for strike.

speaker
Emma
Moderator / Investor Relations

Great. We're not getting too many questions in. I've got one other one, but if anybody, so if you hit the chat button and you want to ask a question, please feel free. We do have another question around just wanting to understand, are the board and management aware of the Carnarvon shares coming out of escrow in July? And what is management doing to make sure that they're in the best position when that happens?

speaker
Peter Stokes
Managing Director & Chief Executive Officer

Yep. Tim might want to jump in on this one as well. But for us, critical is delivering what we said we're going to. You know, the premise of Kanavi Investing was on the basis of us delivering against key projects, being South Arigala, having a path forward on West Arigala, delivering on an ongoing basis at Well Ewing and then having plans clear on our exploration assets into the future. From an operational context, we're absolutely focused on delivering against all of those. Clearly, there are potential corporate activities around that coming out. We're very focused on understanding where that goes. We continue to engage with Carnarvon. As you'll be aware, we have Will Barker on our board representing Carnarvon as well. And so we're working closely with Carnarvon, but we'll continue to plan and deliver. And I think the best thing we can do is deliver on the plan and more, and that ensures that the Carnarvon investment is secure and gives us options beyond that point.

speaker
Emma
Moderator / Investor Relations

Yeah, great. Tim, maybe one for you. On the Western Power, on the additional costs at South Arigala with regards to Western Power, are we seeing any action in that space?

speaker
Tim Cooper
Chief Financial Officer

Thanks, Emma. Yes, we are. We've been engaged with Western Power and government, a number of departments of government over the past few months. Those conversations are progressing and we'd be hopeful to be able to communicate an outcome in the coming couple of months.

speaker
Emma
Moderator / Investor Relations

Cool. Peter, there's a very broad question here, but are there any asset sales planned in the near future?

speaker
Peter Stokes
Managing Director & Chief Executive Officer

Simple answer is no. I think for us into the future, you know, looking at farm-ins and other things, it certainly is always on the cards, but we're certainly not looking to sell any assets.

speaker
Emma
Moderator / Investor Relations

Great. And then probably follows on, there's another one here that says, given the continuing dislocation in our share price relative to our asset, has the company considered selling West Arigala to Hancock and monetising the asset to support the share price?

speaker
Peter Stokes
Managing Director & Chief Executive Officer

Yeah, I think even before my time, I think there were some discussions. There's not a discussion with Hancock around the sale of West Darragilla. Hancock are very focused on building out the Bellissima gas plant, monetising their assets to the north of ours and ideally you know, they would want to put their West Aragilla gas through that plant as well. And we need to work through the options for us as well. But I think simple answer is no at the moment.

speaker
Emma
Moderator / Investor Relations

Great. We're not getting too many other questions in, so we might wrap it up there and look forward to speaking with shareholders soon when we've got some more news to share.

speaker
Peter Stokes
Managing Director & Chief Executive Officer

Thank you, everyone, for joining us today. Really appreciate your time and keep providing feedback. I know Emma gets a lot of calls from a lot of you, and we're happy to talk to shareholders through that process as well. Thank you very much.

Disclaimer

This conference call transcript was computer generated and almost certianly contains errors. This transcript is provided for information purposes only.EarningsCall, LLC makes no representation about the accuracy of the aforementioned transcript, and you are cautioned not to place undue reliance on the information provided by the transcript.

-

-