Operator
Good day and thank you for standing by. Welcome to the AST SpaceMobile first quarter 2024 business update call. Please be advised that today's conference is being recorded. I would now like to hand the conference over to your host today, Scott Wisniewski, Chief Strategy Officer of AST SpaceMobile. Please go ahead.
Scott Wisniewski
Thank you and good afternoon everyone. Let me refer you to slide two of the presentation which contains our safe harbor disclaimer. During today's call we may make certain forward looking statements. These statements are based on current expectations and assumptions, and as a result, are subject to risks and uncertainties. Many factors can cause actual events to differ materially from the forward-looking statements on this call. For more information about these risks and uncertainties, please refer to the Risk Factors section of AST Space Mobile's annual report on 10-K for the year that ended December 31, 2023, with the Securities and Exchange Commission and other documents filed by AST Space Mobile with the SEC from time to time. After our initial remarks, we will begin the Q&A section with questions submitted by our shareholders. Welcome, everyone. For those of you who may be new to our company and mission, there are over 5 billion mobile phones in use today around the world, but many of us still experience gaps in coverage as we live, work, and travel. There are also still billions of people without cellular broadband and who remain unconnected to the global economy. The markets we are pursuing are massive, and the problem we are solving is important and touches nearly all of us. In this backdrop, ASP Space Mobile is building the first and only global cellular broadband network in space to operate directly with everyday mobile phones, supported by our extensive IP and patent portfolio. It is now my pleasure to pass it over to Chairman and CEO, Abel Avalon.
Abel Avalon
Good day, everyone. The hard work of the past few years is culminating in a period of tremendous activity and excitement for AST Space Model. We have moved past a primary focus on improving our technology and funding our growth into the next phase of executing our vision and operationalizing our business. We are shifting from R&D to full-scale production and commercialization of our base-based cellular broadband network. Our technology is proven, patented, and validated. Our commercial ecosystem is in place and growing. We're funded to achieve our near-term goals and reach initial revenue. Our business is now accelerating. Just last week, our first five commercial satellites called the Bluebirds arrived in Cape Canaveral, Florida, after completing final assembly at our manufacturing facilities in Texas. These satellites are now undergoing final preparation for integration with Falcon 9 launch vehicle for a dedicated mission. We have seven-day contracted orbital launch window in the first half of September. Our current expectation is that we will launch in the first half of September. So this is ultimately based on a variety of factors outside our control, including the weather conditions. As the target date is finalized, we will communicate this with the public. To put our first commercial satellites into orbit, really is a culmination of significant progress to this day. I am incredibly proud of our team. We have spent over seven years and over $1 billion in investment to get to this point. Along the way, generating over 3,400 patent and patent-pending claims. Completing the assembly, testing, and other logistics to ensure that our Bluebirds were ready to transport to Florida and were ready to launch is a major milestone for our company and mission. These blue birds will each be the largest communications array ever to be deployed commercially into low-depth orbit. These arrays provide a strong signal that can reach standard smartphones directly to provide cellular broadband service and other non-communication government applications. With these initial commercial satellites, we are targeting nearly 100% geographical coverage for the continental United States using premium 850 megahertz low-band spectrum. which offers superior signal penetration in the low-band spectrum range. Low-band frequencies travel longer distances and penetrate deeper into buildings and through foliage compared to higher frequencies. These first five satellites will provide non-continuous cellular broadband service nationwide across the United States. After a few months of in-orbit service activation, this initial service for AT&T and Verizon beta test users will start with 5,600 cells across the country. This program was made possible in large part due to the continued and growing support of our strategic partners. During the second quarter, we secured another major strategic financing partner and customer, adding Verizon to a top-tier group that also includes AT&T, Vodafone, Google, American Tower, Rakuten, Bell Canada, and others. This $100 million commitment from Verizon, including $65 million of commercial prepayments and $35 million of convertible notes, just a few months after strategic financing with AT&T, Google, and Vodafone. It's another powerful validation of our technology and our business model. This investment closely follows the definitive agricultural commercial agreement announced with AT&T in May. Bringing on board two major U.S. mobile operators in the most valuable wireless market in the world, was a transformational commercial milestone for us. During the last few months, we shifted our manufacturing focus to increase Block II production, incorporating the lesson learned from manufacturing of the first five commercial satellites. We'll continue planning an initial production for the first 17 Block II satellites to be built in phases within the initial launch in Q1 of 2025. These satellites, when equipped with our ASIC, will be approximately 2,400 square feet in size and are expected to support up to tenfold improvement of processing bandwidth per satellite compared to Block 1 satellite that we are launching this September. We expect to start using our ASIC on our sixth Block 2 satellite, and we can use existing FPGA configuration for as long as it's required. Alongside this activity, we have not lost sight of our technology roadmap. We can now report that we have completed the ASIC chip tape-out with the SNC. This technology is the cornerstone of our Bluebird Block II program. The FT5000 ASIC is a novel custom low-power architecture developed to enable up to a tenfold improvement in processing bandwidth on each satellite. Unlocking opportunity for seamless space-based cellular broadband services More why. With the three bits per hertz that we have demonstrated using BlueWalker 3 and our planned commercial satellite capacity of up to 40 megahertz per beam, this translates to performance of up to 120 megabits peak data rates. The completion of the tape-out is a milestone that marks the culmination of five years of dedicated research, development, and engineering expertise with approximately 45 million all developed. In summary, we want to change the world. We're seeking to connect the billions of people who are not connected, improving public safety, enabling global commerce, and for the average user who can see fewer drop calls, frustrating dead zones, and missing connections. This has not been easy. We entered a new phase for our company. And deeply proud of the team we have assembled, and confident in the plan ahead of us. I will now pass to Scott to provide more details on our commercial and regulatory process.
Scott Wisniewski
Thank you, Abel. As we accelerate the commercialization of our network, I wanted to spend a few moments to go through the commercial and regulatory progress during the quarter, including some early wins for the first five commercial satellites. Earlier this month, we received an initial license for space-based operations in the U.S. from the SEC. This initial license authorizes AST Space Mobile to operate using V, F, and UHF frequencies to support our gateway, feeder link, and telemetry tracking control operations for the first five commercial Bluebird satellites. This license will serve as our primary license for operations in the U.S. over the life of the Constellation, so it was a big deal for the company and our commercialization, both in the U.S. and as a blueprint globally. Going forward, we continue to work with the FCC as well as our partners AT&T and Verizon to apply for upgrades and modifications to this license to facilitate full-scale commercial operations on wireless frequencies and to expand the license to support our operations over time. This FCC authorization followed the March 2024 update of our constellation filings with the International Telecommunication Union and related filings with the FCC that placed our planned commercial satellites under the jurisdiction of the United States. This initiative represented a closer strategic alignment of our network build-out and future network operations with the United States and is a key piece of our overall regulatory strategy. In addition to the progress that Bell reported with AT&T and Verizon, we continue to believe our patented technology, including our large phased array antenna technology in space, creates significant opportunities for new mission-critical capabilities in the government sector. We are moving forward with these dual-use capabilities on our constellation and expect to generate revenue from both commercial and government applications. To this effect, earlier this year we announced that ASP SpaceMobile had been awarded a new contract through a prime contractor working with the United States government. This initial phase contract, which covers the use of BlueWalker 3 as well as the first five commercial satellites, is well underway, and during the second quarter we completed successful in-orbit and ground tests resulting in completed contractual milestones and top-line revenue. This government sector strategy continues to show additional early signs of strength, with two new U.S. government contract awards in recent months to one of our prime contractors. Like the February contract, these awards represent relatively small revenue by themselves, but seek to evaluate potential for full-scale, multi-year contracted services in the future. As is customary, contracts for these two new opportunities are still being finalized, and we will provide detail if and when it becomes available. Our primary commercialization strategy is to position for significant revenue opportunities as we scale the constellation, but this initial progress is encouraging, and we believe the progress represents an upgraded outlook for additional and larger signed contract awards over time. With that, I will now pass it to Andy Johnson, our new chief financial officer, to take you through the financial update.
Andy Johnson
Thanks, Scott, and good afternoon, everyone. I joined AST this past May because I believe wholeheartedly in the company's mission to close the digital divide by connecting the unconnected and was convinced that this was a once-in-a-lifetime opportunity after visiting the manufacturing facilities in Midland, Texas. There I saw firsthand the sophistication of the company's technology, and most importantly, the incredible commitment of our team, led by Abel, in producing the world's first space-based cellular broadband service satellites. This is a seminal moment in the history of AST SpaceMobile, and I want to personally thank all of my teammates for their dedication to our mission and delivering our first five commercial Bluebird satellites for launch in just a few short weeks. I also want to thank Sean Wallace, our former CFO, who continues to consult for us for his leadership, service to the company, and partnership in making my transition seamless. It's a fantastic time to be a part of the AST space mobile ecosystem, which includes our shareholders, our talented employees across the globe, and our mobile network operator partners. We are at the forefront of our commercial constellation deployment, And I deeply appreciate those of you who are on this life-changing journey with us. Let's review the key operating metrics for the second quarter that are displayed on slide 10. On the first chart, we see for the second quarter of 2024, we had non-GAAP adjusted cash operating expenses of $34.6 million versus $31.1 million in the first quarter. Non-GAAP adjusted operating expenses excludes certain non-cash operating costs, including depreciation and amortization and stock-based compensation. These expenses are up slightly from the first quarter due to final block one expenses as we neared the finish line of producing five of the largest satellites ever to be deployed in low Earth orbit, including required travel expenses to the production site in Texas, expedited hiring of engineering talent in connection with our Block II mechanical work as we ramp up production of our next satellites, and the impact of an approximately 1 million one-time G&A expense reversal in Q1 that affects the quarter-over-quarter comparison. Turning towards the second chart on this page, our capital expenditures for the second quarter were $21.2 million versus $26.6 million for the first quarter. The figure was made up of capitalized direct materials and labor for Block 1 and Block 2 satellites and additional facility and production equipment for our 185,000 square foot assembly, integration, and test facilities in Midland. As expected, capital expenditures trended down in connection with the completion of the Block 1 satellites ahead of ramping Block 2 production. By the end of the second quarter, we incurred and paid all amounts for the five Block 1 satellites. Total spend for those satellites did not materially exceed our prior estimate of $115 million. The design, integration, testing, and launch of satellites and related ground infrastructure is capital intensive. We do expect our experience completing Block 1 will allow us to leverage our learnings to improve and optimize manufacturing costs for our Block 2 satellites. And on the final chart on this slide, we ended the second quarter with $287.6 million in cash, up from $212.4 million at the end of the first quarter. This increase includes $55 million of previously announced investment from our valued M&O partner Verizon, inclusive of a $20 million prepayment for future cellular broadband service. Our strengthened cash position at the end of Q2 also reflects our disciplined and effective use of our now-completed at-the-market, or ATM, equity facility from which we raised approximately $80 million during the quarter at increasing market prices for our common stock. As of the end of July, we completed the two-year use of the existing ATM facility and the existing common stock purchase facility with $164 million of total raise to support operating expenses and preserve our capital for building the Constellation. During this two-year period, we were prudent in our timing and use of these facilities, consuming less than 75% of the combined facility's capacity and raising capital at more than a 50% premium to our stock's volume-weighted average price. We continue to consider using the balance of our senior credit facility, which has a gross amount available to us of $51.5 million. Today, however, our efforts around raising strategic capital, including non-dilutive prepayments from our M&O partners as we ready for service, are taking precedence over the senior credit facility, which in turn continues to reduce negative carry we would have incurred if we had accessed the facility earlier. Our ability to access this facility remains subject to certain conditions and approvals. I'd like to reiterate that we currently have no plans for the remainder of this year to pursue an underwritten public equity offering. We previously provided guidance on our expected operating expense levels. We have been supporting the development and production efforts of our two critical satellite designs, Block 1 and Block 2, our ASIC chip design, and the five Block 1 satellites. The completion of this Block 1 work and a significant portion of the Block 2 development and ASIC tape-out completion is expected to result in a reduction in our adjusted operating expenses and capital expenditures in future periods. Consistent with the first and second quarters of 2024, we continue to project that our adjusted cash operating expenses for the remainder of the year will come in within a range of $30 to $35 million per quarter based on business conditions and speed of constellation deployment, and as the Block 2 design approaches completion and our focus turns to scaled production. We believe efforts to optimize our OpEx will result in a run rate at the low end of that range. These figures will vary depending upon manufacturing activity in each period. This guidance does not include the expected costs of approximately $15 million related to the tape out, and initial production of our ASIC chips. These ASIC-related costs will be recognized as an R&D expense in subsequent quarters in 2024 as milestones are completed. Timing of the changes in our adjusted operating expenditures and capital expenditures, as I have just described, could be delayed or may not be realized due to a variety of factors. Finally, we continue to work on developing a financing package from export credit agencies to source cost-effective long-term debt funding of large projects. We will keep you abreast of our progress. It's been a fantastic first 90 days. I look forward in the future to getting to know many of you and working hard to drive value for our shareholders as we position AST for full-scale commercial operations. And with that, This completes the presentation component of our earnings call, and I pass it back to Scott.
Scott Wisniewski
Thank you, Andy. Before we go to the queue of analyst questions, we'd like to address a few of the questions submitted by our investors. Operator, could you please start us off with the first question?
Operator
Tanner asks, will you wait until the first BB Block 2 is launched and unfolded before working on additional BBs?
Abel Avalon
Thanks, Tanner, for the question. No, the answer is no. We're already working on the next build of the subsequent satellites. We are actually in the process of building parts for the next 17 satellites. The main mechanical system is, yeah, changes and upgrades, but it's basically the same as Blue Walker 3 and Block 1. And we will not wait. for that deployment to continue building. So we're in the process of building. We actually started a few months back our next satellites built. You know, with the next satellites, we have a satellite that will be equipped with the FPGA and a satellite that will be equipped with the ASIC. And the first launch of four will be based on FPGAs. And the subsequent satellites will be a block two, first four block two. And the subsequent after that will be all based on AC, which is a tenfold improvement compared to the FPGA. And, you know, we're fully focused in building our next batch of satellites and to get them on the air as soon as possible.
Operator
Matt asks, You mentioned that full U.S. coverage is the first priority. What regions will you look to fulfill next and in what time frame?
Abel Avalon
Hey, Matt, thank you for the question. Yes, obviously the U.S. market is the largest, more developed wireless market. In this market we have AT&T and Verizon, and yes, we will be prioritizing deployment for the U.S. market. Then we will prioritize investors and M&Os that are paying prepaid revenue. That includes Vodafone markets, that includes Rakuten in Japan, and then new M&Os that are going to be prepaid for initialization of the service as a priority. We are launching on a 50 degree of inclination, so basically we can cover all the latitudes from 59 degrees north to 59 degrees south. So we have the benefit of being able to select the regions that we prioritize according to prepayments priorities set by new investors.
Operator
Cody asks, what concerns does the company have being that we are currently in a solar maximum? How susceptible are your satellites to solar storms?
Abel Avalon
Thank you, Cody, for the question. Well, first of all, before I answer the question, let me remind everybody about how we design these satellites. These satellites, you know, they're big. They are built out of identical modules that we call microns that make the satellite system very resilient, and it's built out of a distributed system that no one single part can make the satellite to fail. And that makes it very... resilient to the space weather, including solar storms and other conditions. We had all the data that we had collected over two years operating Blue Walker 3. And we really, of course, we have needed our time to react to solar activities, but never having a failure caused by it. So we are very confident on our satellite resilient is where it needs to be as it relates to weather conditions.
Operator
Tanner asked, after the first BB Block II, how many at a time will be launched?
Abel Avalon
Okay. Well, we have decided – thank you, Tanner, for the question. But we have decided the system to be launch agnostic. So we basically envelope our profile – to be able to support basically every large or medium launch service provider, launch systems. And depending on the size of the launch, I mean, on Block 1, we're launching five satellites in a Falcon 9. And depending on the launch configuration and the launch vehicle, it will be anywhere between four per launch for the new larger Block 2s or eight per launch depending on the launch papers.
Scott Wisniewski
And with that, I'd like to thank our shareholders for submitting these questions. Operator, let's open the call to analyst questions now.
Operator
Thank you. We will now be conducting a question and answer session. If you would like to ask a question, please press star 1 on your telephone keypad. A confirmation tone will indicate a line is in the question queue. You may press star 2 if you want to remove yourself from the queue. For participants using speaker equipment, It may be necessary to pick up your handset before pressing the start key. One moment, please, as we pull for questions. And our first question comes from the line of Griffin Boss with B Riley Securities. Please proceed with your question.
Andy Griffin
Hi, good afternoon. Thanks for taking my questions. So first for me, the 17 satellites under construction is certainly more than what we expected. How would you characterize your current production capacity. I know in the past you've discussed expectations to reach something, I think, equivalent to six satellite per month cadence. Have you reached that? Are you tracking better? Any more color would be helpful.
Abel Avalon
Yeah, I mean, when we say 17 satellites, that refers to the subsystem that we are producing. They don't need to be all produced at the same time. So we actually time them. So we start with the long lead items. We start them first. The parts that take more time to get out of the factory, they are being produced for 17 units. And for that, we buy parts in advance. We start manufacturing them way in advance. and as we need it so we keep ordering the different parts for the system. Yeah, we're ramping up. We are accelerating our production cadence, going through the five first commercials that we're launching now in September. It has helped us to expand our production capacity and also going forward We have work on vertically integrating around 95% of the subsystems. So we either control the IP, manufacture by ourselves, and control the manufacturing process for around 95% of the satellites that are on build going forward.
Andy Griffin
Great. Thanks, Abel, for that color. I appreciate it. And in terms of the initial Block 2 satellite launch, are you still tracking for the late 4Q, early 2025 kind of launch window there? Are there any delays or issues you're seeing with the launch provider?
Abel Avalon
No, we're still tracking for Q1 2025.
Andy Griffin
Okay, great. Great. Glad to hear it. And then, Scott, there was sort of an informal interview with you recently on a financial blog where you cited some ARPU assumptions for the U.S. I can't recall hearing the company formally mention potential ARPU in the past, so I would love it if there are any assumptions or expectations for ARPU you can share today, especially now that you've got two definitive agreements under your belt.
Scott Wisniewski
Hey, Griffin. How are you doing? No, we've been making a lot of progress with commercial agreements, and alongside that, been advancing our go-to-market strategies, as you would expect. We don't have any pricing or go-to-market strategies to report at this time, and I think that article was misquoted. But we're very excited about the revenue share model that we've been pushing for a long time, and we're very excited about the adoption rates and the ability to command a good wallet on these. on this service. So no pricing guidance at this time, but I would say the go-to-market planning has definitely accelerated.
Andy Griffin
Okay, got it. Understood. Thanks, Scott. And last for me, very quickly, and I'll pass it off. I just want to confirm that this new contract liabilities line item we're seeing in the statement of cash flows, is that reflecting the Verizon revenue commitment or is that something else?
Scott
This is Andy Griffin. I do think it's the revenue commitments against the prepayments and so forth, so none of that's revenue at this point yet until the services are initiated.
Andy Griffin
Got it. Okay, thanks, Andy, and welcome to the company, and thanks for taking my questions, everyone.
Operator
Thank you. Our next questions come from the line of Benjamin Soft with Deutsche Bank. Please proceed with your question.
Ben
Yeah. Hey, guys. Thanks for taking the question. Exciting quarter with a lot of interesting developments. I was wondering, now that the satellites are onsite in Florida, can you walk us through the timeline and key milestones between launching in early September until you get to commercial service?
Abel Avalon
Yeah, we actually... Hi, Ben. How are you? So we actually indicate now we're on final preparation for launch. The plan is to launch early September, first half of September. We anticipate a few months to basically activate service on those first five satellites. We have two types of users already booked on them. One is a Gorman user, and then we have our MNOs. We are prioritizing U.S., Vodafone, and our investors and people that have an MNO that are prepaying or are going to prepay for services. And so Intemo timeline is we launch, a few months to activate services. And then we are already preparing and have prepared all the ground infrastructure to start connecting to the spacecraft. So we will have some early usage immediately after for the government in parallel with the MNOs.
Ben
Okay, great. And then just going back to the 17 Block 2 satellites, Do you have any updated thoughts on the cost per satellite and the timing to launch those?
Abel Avalon
Yeah, we are maintaining our guidance on cost. Actually, we continue to look for ways to continue to improve our cost basis as we are getting to close to 95% vertical integration. But the guidance per satellite remains the same. And as I said, we're starting a launch campaign, starting in Q1, and then following up with additional launches as the satellites are ready and the launches are available. Okay, great. Thanks, guys.
Operator
Thank you. Our next question comes from the line of Chris Cho with UBS. Please proceed with your question.
Chris Cho
Great. Thank you. We've seen a number of regulatory milestones here in recent months. Can you help us think through your remaining approval process here in the U.S. and the likely timeline for that? And I think there was general optimism previously that other countries could follow suit with similar rulemaking to the U.S. Have you seen any evidence of that to date?
Scott Wisniewski
Hey, Chris. Scott here. Yeah. So, clearly we're happy with the progress this year on the regulatory front, as we mentioned in our remarks. And the FCC does truly play a leadership role globally with other countries. So in our initial markets, we're working with our close partners on moving all the regulatory processes forward. You know, we've been relatively pleased with how that's progressed with no showstoppers, really. You know, we really view it as a process that we go through diligently and And that the FCC has demonstrated a lot of leadership this year with developing new rules for supplemental coverage from space and things like that. So for us, I think initial markets are trending positively. In the U.S., next milestones to look for, there'll be a lot of filings going forward. I think part of commercial service is just there's a lot of regular filings that come. So there'll be filings about gateways on the ground. There'll be filings about test campaigns on When we first start getting block one going and then the big one is SES rights in the U.S. with the FCC. So that is that's something that will be they'll start seeing filings on that with us and with our two partners in the U.S.