This conference call transcript was computer generated and almost certianly contains errors. This transcript is provided for information purposes only.EarningsCall, LLC makes no representation about the accuracy of the aforementioned transcript, and you are cautioned not to place undue reliance on the information provided by the transcript.
4/30/2026
Thank you for standing by. This is the conference operator. Welcome to the Sentara Gold first quarter 2026 conference call. As a reminder, all participants are in listen-only mode and the conference is being recorded. After the presentation, there'll be an opportunity to ask questions. To join the question queue, you may press star then one on your telephone keypad. You'll hear a tone acknowledging your request. Should you need assistance during the conference call, you may signal an operator by pressing star then zero. I would now like to turn the conference over to Lisa Wilkinson, Vice President, Investor Relations and Corporate Communications with Sentara. Please go ahead.
Thank you, operator, and good morning, everyone. Welcome to Sentara Gold's first quarter 2026 results conference call. Joining me on the call today are Paul Tamori, President and Chief Executive Officer, Ryan Snyder, Chief Financial Officer, and Mike Silvest, our Interim Chief Operating Officer. Other members of the executive team are available for the Q&A session. Our news published last night outlines our first quarter 2026 results and is complemented by our MD&A and financial statements, which are available on CDAR, EDGAR, and our website. All figures are in US dollars unless otherwise noted. Presentation slides accompanying this webcast are available on Sunterra's website. Following the prepared remarks, we will open the call for questions. Before we begin, we would like to remind everyone that today's discussion may include forward-looking statements which are subject to risks that could cause our actual results to differ from those expressed or implied. For more information, please refer to the cautionary statements in our presentation and the risk factors outlined in our annual information form. We will also be referring to certain non-GAAP measures during today's discussion. For a detailed description of these measures, please see our news release and MD&A issued yesterday. I will now turn the call over to Paul Tamori.
Thank you, Lisa, and good morning, everyone. We achieved a very strong start to the year with production performing in line with our plan across operations. Consolidated first quarter production of 68,000 ounces of gold and 14.2 million pounds of copper. Mount Milligan delivered results consistent with their recently published PFS and full-year guidance, while the Institute delivered a strong quarter, driven by higher grades, supporting robust free cash flow generation across both sites. Our financial position strengthened this quarter, with our cash balance increasing to $543 million. This was achieved while we continued to invest in our internal growth pipeline, built working capital at Langelof, and returned $33 million to shareholders through share buybacks and dividends in the quarter. We remain focused on leveraging the strength of our balance sheet and our cash flow generation to advance a disciplined, self-funded growth strategy. In January, we announced the results of a PEA for Chem-S, highlighting the long-term potential of the project, which remains a cornerstone of our future growth pipeline. We also continue to progress key initiatives across our portfolio, including delivering on the Mount Milligan PFS and ongoing development work at Thompson Creek, which is expected to achieve first production in mid-2027. Work on the life of mine optimization study at Duke-Soup continues to progress. We are evaluating the incremental production potential of residual leaching of the heap and the inclusion of low-grade oxide mineralization outside of the current reserve pit into the mine plan. This study remains on track for completion by the end of 2026. Goldfield development activities are advancing well, with field campaigns in support of engineering now complete. Detailed engineering, procurement of long lead time items, and mobilization activities for 2026 early works are progressing as planned. First production at Goldfield remains on track for late 2028. Together, these growth projects position Sentara to deliver sustainable value for shareholders over the long term. In January, we released an updated mineral resource and preliminary economic assessment for KEMES. The study outlined a de-risk restart plan which leverages substantially existing infrastructure and focuses on an integrated open pit and underground mining operation. The PEA highlights an initial 15-year mine life with meaningful gold and copper production of 171,000 ounces and 61 million pounds respectively at an all-in sustaining cost on a by-product basis. of $971 per ounce. Chem-S is supported by robust economics with an after-tax NPV of $2.8 billion and a 29% IRR at prices of 4,500 per ounce of gold and $6 per pound of copper. The capital profile takes a phased approach with approximately $770 million in initial non-sustained capital to support open-pit development followed by $277 million in expansionary non-sustaining capital over the two years following open pit startup to support the commencement of underground operations. Most importantly, the PEA only evaluates 47% of the overall resource tons, highlighting the potential for additional resources to be incorporated into future technical studies and the project's overall scale and long-term production profiles. Overall, Chem-S represents a high-quality, compelling, and large-scale growth opportunity for Sentara. We've advanced technical work on a pre-feasibility study, which is expected in 2027. Now I'd like to provide an update on our sustainability initiatives. We continue to make progress on our environmental and permitting activities across the portfolio. During the first quarter, Goldfield reached an important milestone with the receipt of its water rights transfers supporting the advancement of the project towards operations. We remain focused on advancing the remaining permits at Goldfield and we continue to engage constructively with regulators and with the community. We remain confident in the overall permitting process for the project. Our commitment to strong social performance also remains a key focus. At Goldfield, our team hosted two Joshua Tree donation events during the quarter, engaging local communities and supporting the responsible relocation of 340 trees, including 260 for personal use and 80 replanted around the perimeter of our property. At Uxut, our social programs continue to support education, youth development, and broader community initiatives, including a sport and academic program launched this quarter that is expected to reach approximately 14,000 local students over the year. We continue to advance our commitment to responsible mining practices and transparent reporting. Our team is actively working on the 2025 Sustainability Report, which will highlight our progress across key environmental, social, and governance initiatives. We look forward to publishing the report in May and sharing the steps we are taking to create long-term value for our stakeholders. Before we move into our operating highlights, I would like to welcome Mike Silvestre as our new Interim Chief Operating Officer, who joined us at the end of March. We've initiated a search for a permanent CEO, and in the interim, Mike brings a wealth of operational experience and technical expertise to the role. His leadership will be instrumental in supporting our operations and advancing our key priorities as we remain focused on safe and reliable performance across the business. I look forward to working closely with Mike and benefiting from his expertise and his leadership. And with that, I'll pass the call over to Ryan to walk through our operating and financial highlights.
Thanks, Paul. Starting with the operations, slide seven shows the operating highlights at Mount Milligan for the first quarter. Mount Milligan produced over 29,500 ounces of gold in the quarter, representing approximately 20% of full-year guidance, in line with the production profile we previously outlined. Copper production was 14.2 million pounds. Gold and copper sales exceeded production, reflecting the impact of weather-related logistics disruptions at the end of December that deferred some sales into 2020 cents. We continue to expect bull production and sales to be higher in the second and third quarters, reflecting planned line sequencing. All in sustaining costs on a byproduct basis for $1,060 per ounce in the first quarter, benefiting from higher byproduct credits driven by elevated copper and silver prices. Recent increases in diesel prices did not have a material impact on Mount Milligan's cost structure in the first quarter. Moving on to OXU, first quarter production was over 38,400 ounces of gold, higher than planned due to higher grades. Full year 2026 production at OXU remains in the range of 110,000 to 125,000 ounces, with production in the remaining quarters of 2026 expected to be more evenly weighted and lower than the first quarter production. ASIC on a byproduct basis is $1,653 per ounce in the first quarter, lower compared to last quarter, driven by higher gold ounces produced and sold and lower sustaining capex. This was partially offset by a higher royalty expense due to elevated gold prices. At Thompson Creek, restart activities are advancing, with approximately 38% of the infrastructure refurbishment complete. Non-sustaining capex in the first quarter was $41 million. Since the September 2024 restart decision, capital expenditures have totaled $205 million. The project remains in line with the total capital estimate of $425 to $450 million and is on track for first production in mid-2027. Operations at Wenloft have provisionally resumed in April following the temporary suspension on January 29th. During the restart, we identified items requiring additional testing and validation, which is typical of bringing a processing facility back to stable operations, and commissioning continues to progress. A total of $2 million for repairs was incurred in the first quarter of 2026, including both expensed and capitalized costs, with the remaining costs expected to be incurred over the balance of the year and in line with the total estimated repair costs of 5 to 10 million. A $73 million investment of working capital was made at Landloft in the first quarter, primarily related to building inventory during the temporary suspension of operations. This investment is not expected to unwind in the near term, as Sentera plans to hold higher inventory levels through 2026, while operations and shipments normalize, and as land loss ramps up production as part of our commercial optimization strategy. Now shifting to the financials. Slide 10 details our first quarter financial results. Adjusted net earnings in the first quarter were $88 million, or $0.44 per share. Key adjustments to net earnings include $25 million of unrealized loss on the financial asset related to the additional agreement with Royal Gold, among other things. In the first quarter, sales were almost 73,000 ounces of gold and 14.9 million pounds of copper. The average realized price was $4,172 per ounce of gold and $4.48 per pound of copper, which incorporates the existing streaming arrangements at Mount Milligan. Approximately 3.7 million pounds of aluminum was sold in the first quarter at the Langlois facility at an average realized price of $26.11 per pound. Consolidated oil and sustaining costs on a byproduct basis in the first quarter were $1,705 per ounce. As mentioned previously, recent increases in diesel prices did not have a material impact on Sentera's costs in the quarter. The diesel price volatility may impact costs in 2026. However, at current price levels, any such impact is not expected to be material. Slide 11 shows our financial highlights for the quarter. In the first quarter, we generated strong cash from operations of $120 million and free cash flow of $49 million, driven by strong operational performance at Mt. Milligan and Oxsut, as well as elevated metal prices. In the first quarter, Mt. Milligan generated $125 million in cash from operations and $106 million in free cash flows. OXUT generated $134 million in cash flow operations and $132 million in free cash flow. U.S. Mali used $75 million of cash in operations and had a free cash flow deficit of $117 million this quarter, mainly related to spending on the Thompson Creek restart and the working capital increase at Limog. In the second quarter of 2026, we expect to make routine payments to the Turkish government for taxes and royalties of approximately $90 to $100 million, assuming current exchange rates. This will impact the free cash flow at AUX in the next quarter. Returning capital to shareholders remains a key pillar in our disciplined approach to capital allocation. In the first quarter, we repurchased 1.3 million shares for a total consideration of 22.5 million, and we continue to believe that repurchasing our shares is an accretive, high-return use of cash. Dependent on market conditions, we expect to remain active on the share buybacks. We also declared quarterly dividend $0.07 per share. At the end of the quarter, our cash balance is $543 million, bringing total liquidity to $943 million. This strong financial position gives us the flexibility to fully fund our organic growth projects at Mount Milligan, Goldfield, Comess, and Thompson Creek, while continuing to return capital to shareholders. I'll pass it back to Paul for some concluding remarks.
Thank you, Ryan. We are pleased with our strong start to 2026, reflecting consistent operational performance and continued delivery across the portfolio. Our operations are generating robust free cash flow, strengthening our balance sheet, and providing the flexibility to continue investing in our self-funded growth pipeline while still returning capital to shareholders. With a solid operating base and clear progress across our key growth initiatives, including Mt. Milligan, Comest, Thompson Creek, Goldfield, and Exeter, We believe Sentera remains very well positioned to deliver sustainable value for shareholders in 2026 and over the long term. With that operator, we'll be happy to take any questions.
Certainly. We'll now begin the question and answer session. To join the question queue, you may press star then one on your telephone keypad. You'll hear a tone acknowledging your request. If you're using a speakerphone, please pick up your handset before pressing any keys. To withdraw your question, please press star then two. Our first question is from Don DeMarco with National Bank. Please go ahead.
Thank you, operator, and good morning, Paul and team. Congratulations on another successful quarter. And to that point, I think I'll start off with the first question on Oxit. Another strong quarter here, and Oxit Maybe if you could provide a little more color on the reasons for the outperformance and whether they were expected or potentially surprised. You know, I heard that the production for the rest of the year is going to be more evenly weighted. Is there also potential for positive surprises in the next three quarters?
Yeah, thanks, Don, in the morning. In fact, I'll answer the question by taking a longer-term perspective on offsuit and why we're running a lifetime optimization project. This mine has reconciled positively almost since first production. And so accumulated inventories in the heaps tend to be greater than that which would have been indicated by the in-going resource model. And so when we have these elevated grades, ultimately it moves through inventories and it's whether it's in the heaps or in solution, but ultimately the root of the outperformance is better than expected or better than modeled grades reporting to the heaps. And so your second question is, will this continue? There will be times where Oxsuit continues to exhibit better than planned grades, but for the remainder of this year, we are holding to the guidance that we put out in the numbers here. So in other words, they won't be quite as good as Q1. But I'll just make a plug here for our Life and Mind Optimization Project. We are looking at a production life extension here through a combination of mining lower grade oxides that we know are outside of the current reserve pit, supplemented by the drawdown of these accumulated inventories, which we know are reasonably significant. And that's what we're pretty excited about putting out a study with our year end this year on a production life extension. But it ultimately comes down to positive reconciliation on the material coming out of the pit.
Okay, thanks for that. And then just shifting over to diesel prices. I heard during the call that the impact is not expected to be material. It was not material in Q1, but even going forward for the rest of the year, it's not expected to be material. But can you quantify this impact maybe in terms of dollars per ounce or percent OPEX for, say, current diesel prices relative to what you budgeted? And beyond OPEX, do you see any other cost pressures across your supply chain, maybe on CAPEX and some of the projects you have underway related to the higher diesel prices? Thanks.
Hi, Don. Thanks for the question. It's Ryan here. Just generally speaking, if we look across Mount Milligan and Oxsuit, a little under 10% of the cost profile is diesel, with more at Milligan, less at Oxsuit. We are somewhat hedged at Mount Milligan. So we're about 30% hedged on diesel for this year, which helps negate some of these price movements. And oxy, again, is a smaller number. And then for the Thompson Creek project, it's about 10% of their capex profile, and we're about 75% hedged for Thompson Creek through the initial capex period. So we do have a bit of cover with our hedges. You know, if diesel is around $100 a barrel, we believe we're going to stay within our cost ranges that we have out there for guidance and within our capex range at Thompson Creek. We have obviously sensitized that, and if diesel does go up $50 a barrel, it's about a $75 an ounce impact on ASIC. But at current diesel prices, we expect our cost ranges and capex ranges to hold.
Okay, thanks. And then just finally on commands, you know, of course, as Paul mentioned, the – something like 40-plus percent of the resource was not in the PEA mine plan. And looking ahead to the PFS in 2027, what are your plans to advance the resource, and would a portion of that resource that wasn't in the PEA be included in the PFS, or would that be something that would be targeted later, maybe after the mine's in production?
It's more of the latter there. So the PFS is focused on increasing the level of confidence across all areas of engineering, plus associated permitting activities. So by and large, the PFS will deliver that 15-year mine plan that is associated with that roughly half the total resource. What we would then intend to do is as we move to execution of an FS and into construction, should we approve the project, we would continue to drill and look to add further material to the mine plan afterwards. As I said, the PEA generates a 15-year mine life. So we, strictly speaking, we don't need more resources in the plan. We want to focus on delivering a robust job on the study around that which we indicate in the PEA. And the other thing we're doing during this PFS is we're just increasing the confidence in the drilling. So we're converting more inferred to indicate it just to bring up the degree of rigor in the resource that we propose to mine here in the PEA.
Okay. Thank you. That's all for me. Good luck with the rest of the year. Thanks, Don.
Once again, if you have a question, please press star then one. Any further questions, please press star then one. Our next question is from Lawson Winder with Bank of America Securities. Please go ahead.
Thank you very much, operator, and good morning, Paul and team. Nice to see you guys continuing on the strong buyback path. I wanted to just ask about your thinking on the buyback. I mean, in light of the current gold price environment, your CapEx needs, I mean, I think a lot of projects already and still decent pre-cash flow yield. I mean, do you see room to accelerate what you've been doing on the buyback versus Q1?
Our capital allocation is a discussion we have every quarter. And what has happened here with these elevated commodity prices is that not only are we able to fund our development pipeline out of cash plus operating cash flow, as evidenced by this quarter, we continue to build cash while funding the development pipeline. So it's always a question on what do we do with that, I suppose, excess cash. We are committed to a very robust buyback. You saw it in the quarter. And it's an ongoing debate. And the other message that we'd like to get out there is we believe we're very compelling value right now. And buying our shares is a strong signal that we are convinced in that valuation opportunity. So it's an ongoing debate. But I'll tell you, we remain committed to a very robust buyback here.
Okay, understood. And then, just thinking about the Oxford Life of Mine Study, could you maybe give us just a bit of a preview in terms of what we're expecting? I mean, I think right now the expectation is an extra year, maybe a little bit more than a year of mine life. I mean, is there any upside or downside risk to that expectation that we have at this point?
Well, I'll repeat what I said in Dawn's questionnaire is there's two sources of opportunity. One is just a capitalization on higher gold price, which will mobilize hitherto sub-economic oxide material outside their reserve pit. We wouldn't do it just for that, but the real opportunities on the residual leach, as I mentioned, historic positive reconciliation in some years quite significant, which has left significant inventories in the heap under leached, or in some cases, certain areas not leached when you look at the geometry of the the heaps, we'd like this to be more than a year. This is not going to be an insubstantial extension, but I don't want to get into predicting the exact number of years. But there's a good amount of inventory between the residual material and those lower grade oxides. I mean, in fact, even right now, even before the addition of those, our current models show a heap drawdown even into 2030. So even before the even before releasing the results of this project, we're already seeing leach curves, even before that project, pushing us into 2030.
Okay. No, that's clear. I guess what I'm hearing from you is, yeah, I mean, one year probably wouldn't be that satisfactory internally, and so the hope is that it would be longer. I think that's fair, but push back if that's incorrect.
That's right. Yeah, no, that's correct, Lawson. I mean, I don't want to tell you an exact number because I frankly don't know what that number is. We have to do the work right now, but we wouldn't be satisfied with just a year.
Yeah, okay. No, that's very clear. Thank you for cleaning that up. Thank you. Yeah, thanks, Lawson.
Our next question is from Brian MacArthur with Raymond James. Please go ahead.
Good morning. Thank you for taking my question. It relates to the free cash flow and the MOLLE operations. Can you just go through, there's discussion here about why capital is different between additions and total capital. It talks about AROs and ROUs. Is that all cash that's happening? I'm just trying to reconcile the free cash flow that's actually coming out of here. And the second part of that question, is there any capital in there for cost to fix land loss as well? Thank you.
Thanks, Brian. I think I understand your question. If you're looking at the conversation around CapEx and additions to PP&E and the guidance in those areas, there is a difference. It's usually for non-cash accounting things. So if you're trying to look at cash flow, looking at the CapEx number and not the additions to PP&E for Thompson Creek is the right way to go. The Thompson Creek number is just for Thompson Creek. We have not put Langloff guidance out yet. So in terms of repairs, That's not in the guidance table per se, but we have included in the commentary an estimate of 5 to 10 million for the year for the totality of the repairs at Langlois, and we believe that's still accurate. We spent 2 million in the quarter. There's some ongoing fixes that'll need to happen, but that's about the range you're looking at for Langlois.
Okay, great. Thanks. I think that clears it up. I was just trying to match everything up here, and it didn't quite match. So, again, simply, You know, if I look at it, there's the free cash flow deficit at Thompson Creek and then the free cash flow for the working capital at Langlois. That's the 116.5 you're just getting. And that's the true, what I would call cash impact of all that. And the rest of it's all non-cash accounting. And there's no Langlois in any of that. Is that correct?
That's correct. Other than the Langlois working capital, you know, so that's the right number, Brian. Thank you very much. No problem.
Once again, if you have a question, please press star then one. The next question is from Jeremy Hoy with Canaccord Gemility. Please go ahead.
Hi, thanks for taking my questions. Two for me on Mount Milligan. First one, I noticed gold recoveries are trending higher recently and you guys have had some ongoing optimization initiatives. Just wondering if you guys have seen any sort of breakthroughs at the plant, which are resulting in these higher recoveries, despite being at grades being somewhat lower. And the other question is on costs at Milligan. I think production costs are up to $94 million in the quarter, up from the prior run rate, and above what I was projecting for the remainder of the year. So just wondering if you could provide any commentary there and if we're expecting to see those normalize for the remainder of the year and sort of more in line with guidance. Thanks.
Okay, I'll take the question on recovery, and Ryan will take the last question. With recoveries, I wouldn't necessarily fixate on the first quarter and apply it to the rest of the year. Recoveries at Mount Milligan are highly dependent on, yes, the optimization work that we're doing and trying to get better recoveries, but much more so they are driven by many geometallurgical characteristics, but principally the pyrite to calcopyrite ratio in the ore. And so depending on what that ratio is in the mill feed, that will drive higher or lower recoveries. So I wouldn't necessarily, though we're thrilled with the recoveries in Q1, I wouldn't necessarily say that that will continue for the year. It'll really be a function of where we are in the ore body. Now, what will drive the better quarters in our guidance of Milligan in Q2 and Q3 is grade. We knew that Q1 was going to be a low grade quarter, particularly in gold. And in the same way, we were confident that Q2 and Q3 will be higher grade. I'll add one other point. One of the reasons that we are much more confident in our guidance and forecast than millions, say, compared to previous years, is we've implemented a grade control program or an RC drilling program where we drill a number of benches ahead. And so we're able to modify the resource model with those RC numbers. So that gives us much better predictability on grade and then, of course, associated recoveries, depending on metallurgical characteristics of the ore. So that's the answer on recovery. Ryan, you want to take that cost question?
Yeah, sure. On costs, maybe two answers. On the gross cost for the quarter, I think one thing to point out is we did sell more than we produced. So some of that is just pulling through costs that were sitting in inventory at the end of the year. I think on a quarter by quarter basis, Mount Milligan costs going forward are expected to be more or less in line with the previous year. So that can give you some guidance there. And then on a unit cost basis, a little bit higher in Q1, but as we get into the higher production quarters in Q2 and Q3, we expect the unit costs on a per ounce basis to pull down a little bit as well. So I don't think there's anything surprising to us or unique in the cost structure for Milligan during that quarter.
Okay, appreciate the call. Thank you.
Thanks, Jeremy.