This conference call transcript was computer generated and almost certianly contains errors. This transcript is provided for information purposes only.EarningsCall, LLC makes no representation about the accuracy of the aforementioned transcript, and you are cautioned not to place undue reliance on the information provided by the transcript.
5/13/2025
Thank you for standing by. My name is JL, and I will be your conference operator today. At this time, I would like to welcome everyone to the Oklo first quarter 2025 financial results and business update call. All lines have been placed on mute to prevent any background noise. After the speaker's remarks, there will be a question and answer session. If you would like to ask a question during this time, simply press star followed by the number one on your telephone keypad. If you would like to withdraw your question, simply press star one again. I would now like to turn the conference over to Sam Doan, Director of Investor Relations, you may begin.
Thank you, operator. Good afternoon and welcome everyone to Okla's first quarter 2025 earnings and company update call. I'm Sam Doan, Okla's Director of Investor Relations. Joining me today are Jake DeWitt, Okla's co-founder and Chief Executive Officer, and Craig Bellmer, Okla's Chief Financial Officer. Before we begin, I'd like to remind everyone that today's discussion, including our prepared remarks and the Q&A session that follows, will include forward-looking statements. These statements reflect our current views regarding trends, assumptions, risks, uncertainties, and other factors that could cause actual results to differ materially from those discussed today. We encourage you to review the forward-looking statements disclosure included in our supplemental slides, which are available on the investor relations section of our website. Additional details on relevant risk factors can also be found in our most recent filings with the SEC. Please note that OCWA assumes no obligation to update any forward-looking statements as a result of new information, future events, or otherwise, except as required by law. With that, I'll now turn the call over to Jake DeWitt, OCWA's co-founder and chief executive officer. Jake.
Thanks, Sam, and thanks to all for joining us today. We're looking forward to sharing our first quarter update and highlighting the progress we've made since our last update just seven weeks ago on March 24th of this year. We continue to see strong momentum across both the industry and the political landscape in support of nuclear energy, and that momentum is accelerating in 2025. The current administration has made it abundantly clear that nuclear is a strategic priority. In a recent letter to the Director of the White House Office of Science and Technology Policy, The president named nuclear energy, AI, and quantum technologies as central pillars in what he called the golden age of American innovation. That message reinforces what we're seeing across policy and regulatory activity. A series of recent executive orders underscores the administration's commitment to nuclear energy, ranging from regulatory reform and streamlined permitting to the creation of a federal task force dedicated to next-generation nuclear deployment. This includes actions to revoke outdated regulatory barriers declare a national energy emergency to fast-track projects, and establish an energy dominance council focused on accelerating technologies like small modular reactors. Other orders reinforce federal oversight to reduce state-level interference and direct agencies to conduct cost-benefit reviews of existing rules. And now, we're seeing signs that the administration may take its support even further. According to recent reporting, several new executive orders are being considered that would aim to quadruple the size of the U.S. nuclear fleet by 2050. declare certain data centers as defense-critical infrastructure, and direct the Department of Defense to take a more active role in nuclear procurement. These drafts also call for a wholesale revision of NRC regulations, streamline reactor approvals, and rebuild domestic nuclear fuel supply chains. While still in development, the scope of these proposals signals just how serious the administration is about reestablishing U.S. leadership in nuclear and how aligned that ambition is with OPO's mission and model. Secretary Wright, a former Oakland board member, has been one of the most vocal champions of the administration's commitment to expanding and accelerating nuclear deployment. He's made it clear that the U.S. must lead the global push to commercialize advanced nuclear technologies and that the federal government is prepared to support that leadership with urgency and action. We're encouraged to see that level of alignment at the highest levels, especially from someone who knows Oakland's mission and model firsthand. At Oklo, our foundation is built on the belief that advanced nuclear technology can and should play a transformative role in the global energy landscape. When we started this company, we saw an industry that had gone dormant, and we set out to reimagine what the nuclear energy industry could be. That vision continues to guide us, delivering clean, reliable, and affordable energy at scale. As a reminder, our competitive advantage is built on the intersection of three key strategies, our business model, our sizing philosophy, and our technology. First, our build-own-operate business model sets us apart. We sell power, not power plants, under long-term contracts. This structure provides predictable recurring revenue and enables a more efficient regulatory path. Second, our small-scale modern design allows us to deploy quickly and scale flexibly. By leveraging existing supply chains and their factory fabrication, we can meet demand efficiently, reduce on-site complexity, and scale in lockstep with our customers' evolving needs. Third, our proven and demonstrated technology is backed by over 400 reactor years of operational experience with liquid metal-cooled fast reactors. This gives us a robust technical foundation with distinct performance and safety advantages. Importantly, it enables us to move directly into commercialization without the need for a costly, time-consuming demonstration plan. Together, these pillars reinforce Oklo's position as a leading next-generation nuclear provider and will enable us to execute with speed, efficiency, and confidence. The key differentiator for OKLO is our ability to go straight to commercial deployment. We're not building a demonstration plant. Our Aurora powerhouse is built on mature technology derived from the reactors such as the Fast Flux Test Facility, or FFTF, and the Experimental Breeder Reactor 2, or EBR2, which operated successfully for over 30 years at Idaho National Laboratory. This isn't theoretical. We're leveraging real, validated operating data that's already recognized by the NRC. Importantly, members of our team work directly on both FFTF and EBR2. bringing deep firsthand experience to the design and deployment of the Aurora. We believe this operational legacy allows us to move with greater speed and confidence through the licensing process and positions us to bring our first commercial unit online in late 27 to early 28. While many advanced nuclear companies are still building one-off demonstrations to validate new fuels or designs, OCO is already focused on delivering a commercial powerhouse. These early stage efforts are useful to the ecosystem, but they aren't market ready. We're taking a fundamentally different path, one that's grounded in experience and optimized for near-term deployment. As we continue to execute on our strategy, we remain committed to keeping the market informed with clear and consistent updates on our progress. Our company updates will continue to be structured around six key areas. Project execution, licensing progress, fuel, recycling, and feedstock, customer pipeline development, strategic partnerships for corporate and business development, and financial updates. Since our last company update just seven weeks ago in March, we have continued progress across key areas of our business, from project execution and licensing to fuel strategy, customer positioning, and strategic partnerships. We advanced field work at key sites, made progress in our NRC engagement, and were selected as a qualified vendor through the Department of Defense's procurement process, strengthening our position to pursue future opportunities with military installations. We are in the process of formalizing new partnerships to support technology development and deployment of powerhouse and radioisotope assets at INL. On the financial front, we remain disciplined and transparent, with updates on cash burn, operating expenses, and governance included in today's materials. At Oakville, we're executing against our plan and advancing steadily toward commercial deployment. We have completed a major milestone in preparing our INL site for the Aurora powerhouse. Our team wrapped up a comprehensive drilling campaign involving seismic and geophysical studies at our proposed site at Idaho National Laboratory. The data we gathered will directly support our combined license application to the NRC and represents the final technical siting step ahead of submitting phase one of our application. We also finalized a memorandum of agreement with the Department of Energy and an interface agreement with INL. These agreements ensure that our site development efforts are aligned with environmental standards and DOE coordination. With this complete, we're well-positioned to move into the next phase of licensing and infrastructure development, with plans aiming for the plant to begin operations in late 27 to early 28. We recently initiated phase one of the pre-application readiness assessment for our Aurora INL powerhouse, reaching an important milestone in our licensing efforts with the NRC. This process, essentially a dress rehearsal, enables the NRC and OKLAH teams to align on scope and expectations ahead of our formal combined license application submission. The goal is to surface and address feedback early, reduce challenges later, and build confidence and momentum as we move toward our formal COLA submittal. We expect we will soon receive an audit report from the NRC summarizing their feedback and recommendations, which we'll incorporate into phase one of the application. The NRC feedback will be categorized as follows. Category A, final safety analysis report or FSTAR gaps where information required by regulation may be missing. Category B, items requiring additional information or further clarification or justification is needed. Category C, other observations, suggestions, or potential issues that could affect the efficiency of review if left unaddressed. We have worked diligently with the NRC to ensure a robust and complete application that should reduce Category A observations. However, every observation offers important insight into areas we can further develop to allow for an efficient and timely review of our Phase I COLA. We do anticipate some category A, B, and C items, which is entirely expected and consistent with what other reactor developers have seen. These are clarifications and refinements, not fundamental application content flaws. This is exactly what the readiness assessment is designed to identify, and it helps both OKLO and the NRC get ahead of potential considerations and areas for alignment. Notably, Oklo is using this audit as an opportunity to test several key repeatable licensing pathways and expects valuable NRC guidance on how these novel approaches will best support rapid and cost-effective deployment. We're also encouraged by broader efforts at the NRC in modernizing its approach to advanced nuclear. For example, the NRC finalized a construction exemption for TerraPower's Natrium plant, allowing construction of its energy island to begin while licensing continues. That decision shows the NRC's increasing embrace of flexible, modern, and risk-informed approaches, setting a precedent that will also benefit OKLO's deployment strategy. It supports strong alignment with the NRC and will increase predictability and reduce downstream challenges as we move forward. We also continue to make progress on other regulatory funds by nearing the submission of the licensing project plan for our OKLO fuel foundry, a key step in the broader fuel strategy, and our licensed operator topical report, which has now been submitted to the NRC. The Licensed Operator Topical Report outlines a new licensing approach designed specifically for OKLO's Aurora powerhouses. Today, most U.S. nuclear plant operators are licensed for single-plant and must be on-site to perform safety-related action, a model developed for the traditional light-water reactor fleet. OKLO is proposing a different approach. Instead of licensing operators for individual sites, operators would be licensed for the Aurora powerhouse technology itself. This should enable them to monitor multiple powerhouses from a central location and travel between sites as needed. Because Okla builds, owns, and operates its powerhouses, this licensing strategy is well aligned with its business model and emphasizes efficiency and repeatability. Once approved, the licensed operator topical report can be referenced in future applications, significantly reducing the need to re-review previously approved material. This regulatory efficiency is central to Okla's plan for scalable deployment across its fleet. By strategically submitting topical reports like this one, Oklo is laying the regulatory foundation for faster licensing pathways that support its broader commercialization goals. Each of these regulatory touchpoints reflects Oklo's proactive approach to licensing and our ability to execute efficiently. Fuel strategy is a key differentiator in advanced nuclear, and Oklo is setting a new standard for flexibility and readiness. We're the only advanced nuclear company that has secured and is actively working with HALU for our first commercial plants. On the commercial side, we've signed an MOU with Centris, currently the only domestic producer of HALU to support our powerhouse deployments with a reliable supply source. And looking ahead, our technology is designed to take full advantage of recycled fuel, and we're actively developing that capability through our in-house fuel recycling program. This three-pronged approach, government-awarded material, commercial HALU access, and future recycled fuel positions Oklo with one of the most comprehensive and durable fuel strategies in the advanced nuclear sector. It not only strengthens our long-term supply chain, but will also give us a significant cost and commercialization advantage. We were recently selected as one of eight qualified vendors for the Department of Defense's Advanced Nuclear Power for Installations Program, or ANPI. This is a significant milestone, not just because it opens near-term opportunities for deployment on military installations, but because it reinforces OKLO's position as a credible go-to solution for energy resilience in high-security environments. The program is led by the Defense Innovation Unit, or DIU, which is focused on fast-tracking commercial technologies for national security applications. That means streamlined contracting, faster timelines, and a clear path to scalable deployment. Unlike traditional procurement pathways, ANPI uses a contracting mechanism called Other Transaction Authority, or OTA. This allows for a faster milestone-based approach from early design through prototyping and ultimately can even end with a power purchase agreement. OTA contracts can also draw funding from DIU, any branch of the military, or other federal agencies, giving Oklo a versatile and well-supported path to deployment. For Oklo, this selection validates our technology aligns with our commercial roadmap and gives us added momentum with both federal and commercial partners. It's an endorsement that strengthens our position across the board. We acquired Atomic Alchemy earlier this year to expand OKWA's reach into the high-growth radioisotope market, and this company is already delivering. Founded in 2018, Atomic Alchemy is building a domestic, vertically integrated supply chain for high-value isotopes used in everything from cancer treatments and medical diagnostics to national security and advanced manufacturing. Their proprietary technology, including their versatile isotope production reactor, or VIPER reactor, is designed specifically for isotope production with a focus on efficiency, scalability, and simplicity. They've already hit key engineering and regulatory milestones and are working closely with Idaho National Laboratory to advance deployment. With strong early customer interest and a proven team in place, Alamak Alchemy gives Oklahoma Capital Light opportunity to drive near-term revenue and long-term market leadership in an essential and underserved space. Today's radioisotope supply chain is outdated, fragmented, and increasingly unreliable, stretching across multiple facilities, geographies, and transport modes, making it risky, expensive, and slow. Atomic Alchemy flips this model with a vertically integrated system. The VIPER facility will consolidate reactor operations, processing, and manufacturing at a single site, dramatically increasing efficiency and reliability. This model is not only better suited to meet modern demand, but also allows for global distribution with faster lead times and lower costs. As demand for isotopes accelerates, this supply chain advantage will be a major competitive differentiator. The Atomic Alchemy Viper platform is designed to support broad radioisotope production as well as irradiation capabilities across medical, industrial, defense, and emerging tech sectors. From lifesaving cancer therapies and diagnostic imaging to industrial sensors, aerospace applications, and advanced semiconductor manufacturing, these isotopes and irradiation capabilities are essential to critical systems in our economy. What makes this solution so compelling is not just the diversity of isotopes and radiation capabilities we can produce, but the scale and reliability our integrated model offers. This is a broad and growing market with unmet demand, and Atomic Alchemy is built to serve it efficiently and at commercial scale. We believe that Atomic Alchemy is executing a smart, multi-project approach to market entry. The first step is a lab-based demonstration project designed to validate the process and generate revenue quickly, potentially as early as 2026. This will involve a low-cost processing infrastructure and customer-ready material using third-party irradiation. The second project is the launch of a fully commercial viper facility, a four-reactor site dedicated to direct isotope production. Licensing is expected to begin in 2025 with operations targeted for 2028. That project is expected to be potentially funded off balance sheet and supported by long-term supply agreements that are already under negotiation. With this roadmap, Atomic Alchemy brings near-term upside, long-term scalability, and significant value to Uplift's broader platform. Shifting to leadership and governance, we're thrilled to welcome Pat Schweiger as our Chief Technology Officer. Pat brings deep technical expertise across advanced reactor design, plant systems, and regulatory strategy, and a track record of scaling both fusion and fission programs from concept through deployment, including his comprehensive experience working at FFTF while it was operating. which is one of the fast reactors that Oklo builds its design from. He's joining at a pivotal moment to help drive our commercial rollout, bringing the kind of strategic and operational leadership that will accelerate Oklo's next phase of growth. We're excited to have him on the team. We recently announced that Sam Altman has stepped down from Oklo's board of directors. Caroline and I first met Sam at a dinner in Cambridge, Massachusetts in April 2013. Since that first chance meeting, Sam has played an instrumental role in guiding Oklo, Caroline, myself, and our vision over the years. Sam has been a mentor, a leader, a supporter, a champion, and a friend since that meeting. Sam invested in the company and joined our board in 2015, and he helped us grow through challenges and into the incredible opportunities that lay before us. We are deeply grateful for his early conviction, vision, leadership, and support. As we move closer to commercialization, this transition reflects a natural evolution from the company's early stage development into where it is today. We are excited about the growth this represents, and I will now turn it over to Craig.
Thank you, Jake. As we move closer to commercialization, this transition reflects a natural evolution from the company's early stage development into execution. Sam's departure also supports a shift of his role from that of an insider to a potential future commercial partner, removing a possible conflict of interest as we advance potential commercial discussions with open AI. Importantly, this change does not affect day-to-day operations. In conjunction with this transition, Oklahoma's chief executive officer, Jake DeWitt, has assumed the role of chairman of the board, providing continuity and clear leadership as we enter this next phase of growth. At our last update just seven weeks ago, we discussed the additions of Dan Poneman and Michael Thompson to the board. After now Secretary of Energy rights confirmation and departure from the board, we are pleased with how we have grown the board. The experience and expertise in NRC licensing, fuel supply chains, strategic finance, and technology commercialization that Dan and Michael bring to the board are great additions to our team. I will now provide a summary of our financials. Oklahoma's first quarter operating loss was $17.9 million, inclusive of non-cash stock-based compensation expense of $2.3 million. Oklahoma's loss before income taxes was $14.2 million, which reflects our operating loss adjusted for net interest income of $3.6 million. When adding back non-cash stock-based compensation charges and considering non-cash income tax benefit recorded for the quarter, you get cash used in operating activities of $12.2 million. We believe this puts us on track to deliver on our guided range of $65 to $80 million for total cash used in operations for full year 2025. At the end of the quarter, cash and marketable securities were $260.7 million. Lastly, we have filed our proxy statement and will be holding our annual general meeting on Wednesday, June 4th, 2025. To close, I'll briefly highlight why we believe OCLO stands out in the advanced nuclear and energy landscape. We are deploying proven fast reactor technology in a compact, scalable form, reducing cost, complexity, and time to market. Our business model is built around long-term power cells, delivering recurring revenue and strong margins. We look to drive superior economics through repeatable deployment of a common design asset that can be further enhanced with recycled fuel to drive capital efficiency and a competitive levelized cost of energy. Our customer pipeline totals over 14 gigawatts and spans sectors like data centers and defense, proof of strong and growing demand. We've developed a streamlined regulatory strategy backed by years of licensing expertise and a repeatable COLA process aligned to our business model. And finally, we're not just building powerhouses. We're building a platform that integrates generation, fuel recycling, and radioisotope production. unlocking multiple high-value markets. Thank you for joining us today. Operator, we're now ready for questions. Thank you.
Thank you. The floor is now open for questions. If you have dialed in and would like to ask a question, please press star 1 on your telephone keypad to raise your hand and join the queue. If you would like to withdraw your question, simply press star 1 again. If you're called upon to ask a question and are listening via loudspeaker on your device, please pick up your handset and ensure that your phone is not on mute when asking your question. And we do request for today's session that you please limit yourself to one question and one follow-up. Your first question comes from the line of Ryan Pinkst of B. Reilly. Your line is open.
Hey, guys. Thanks for taking my questions. Jake, you mentioned the recent reports about additional executive action expected to support nuclear power. It sounds like these could include the DOD taking on a greater role in ordering reactors and installing them on military bases. Can you talk about the regulatory authority for nuclear power that the DOD has today and your thoughts on the department's ability to potentially accelerate reactor deployments, whether through programs like the ANPI or otherwise?
Yeah, thanks for the question, Ryan. I mean, I think DOD does have authority to, you know, regulate nuclear plants on sort of for their use cases and for different opportunities around that. So we see some interesting angles there. There's been kind of a mixed approach taken in the department. And I think what, you know, we've heard about some interest is looking at ways to make sure that you know, they are not going to be held up or held back at all by any kind of, you know, from their need sets, from any kind of regulatory permitting issues that could happen outside of sort of their control. Obviously, they have the ability to control it all. So I think there's some appetite and some potential interest in doing that. That said, their active infrastructure and their capability set, you know, hasn't been exercised a ton, you know, for these kinds of use cases in a while, to put it somewhat, you know, I guess, So I think there's some significant opportunities for them to step up and perhaps provide sort of an alternate pathway for some of those use cases, which is, I think, pretty exciting. Additionally, I think it creates a pretty good dynamic to look at efficiencies where if you are citing these at military installations or other government installations, if you see the broad activities across the government today, just trying to find ways to streamline and make the regulatory processes much more efficient and modern and quick and timely, I think you see opportunity for how these activities, these potential activities around sort of expanding DOD roles here could be done. But DOD does have that capability set. They do have that authority. And so I think it's a matter of looking at how they can sort of best use it to sort of push and accelerate these things.
I appreciate that, Jake. And then the fuel slide was a helpful reminder of the actions you're taking on that front. Can you give us an update on other parts of the supply chain and your confidence in commencing a fairly near-term construction effort?
Yeah, I mean, this is a feature set for, you know, we've designed two supply chain capabilities and information heavily since the beginning. You know, there's a lot of ways you can design a reactor, a lot of different materials, fuel types, coolants, all sorts of things you can do. Patrick Corbett- Some of which obviously our technologies need a lot more r&d and development before they're ready to go. Patrick Corbett- Some others just need a lot more supply chain development before you can procure the various parts needed and then. Patrick Corbett- In our case we've designed heavily to leverage what's out there as much as we possibly can feels obviously the big watch point because that's kind of the biggest. I would say sort of challenge and opportunity, if you will, that we see. But everything else, we try to leverage existing supply chains from in and also outside of nuclear as much as we can. And that's a real feature to sodium technologies, right? You can use common stainless materials. You can source those from many other industries from the process side of things. You know, when you look at like the steam generation side, that's probably why we partnered up with Siemens. um to help drive that last year and kind of accelerate that for them to be able to deliver uh and they do that very well obviously so generally speaking um you know this is a thing that we're going to be sort of pushing forward as we try to you know accelerate what we can do to actually break ground and start building uh as quickly as we can um and i think that's something that we see on the supply chain side you know most of the limitations are really centered around fuel and the other long lead items are are just looking at 18 month kind of windows and and ability to then also bring in sort of the order book and backlog that we have behind it helps us sort of be able to actually scale more of that uh as well so when we talk to suppliers it's not just about one it's about more and that kind of motivates the right kind of partnerships if that makes sense so that's how we're uh how we're looking at this and thinking of it but but you know this avoids some of the challenges you see in the light water space where you need large pressure vessels or forgings that way obviously there's some capacity for that but there's a lot less of that so work down there needs to be done to sort of show that you know to get in front of that bottleneck and that constraint, given there's only a few places in the Western world that we'll be able to source that from. We as a, not OKLO, we as America, frankly. And so for us at OKLO being able to not require those needs helps us actually diversify away from that, which is super, super helpful. Similarly on the turbine set, actually something that's a little bit underappreciated. You think about nuclear steam turbine systems, most of those are gigawatt scale systems for light water. Well, most all of those are high hundreds of megawatts to gigawatt scale systems for light water reactors. And light water reactors operate at a relatively low steam temperature set compared to other power generation technologies. And as a result, like scaling that turbine down to sort of small reactors and smaller for water-cooled conditions, not technically challenging, but requires some reasonable non-recurring engineering and sort of tooling costs to set up the infrastructure to actually make those. Whereas our systems operate at those temperature ranges and pressure ranges that look a lot more similar to where a lot of fossil fire plants operate. And that's kind of another feature about non-light water systems is you tap directly into some of those supply chains, which is super helpful. And just to kind of like emphasize the recent news of what the NRC did with their power is just an extraordinarily important validation of that model that applies also to us, right? Similar technology set shows that you can decouple the steam system, the power side from the reactor side. that opens up so much more flexibility in terms of how you can source, procure, and construct and install.
Great. Appreciate all that detail. I'll turn it back.
Your next question comes from the line of Sharif El-Meghrabi of BTIG. Your line is open.
A fuel MOU with Centris. Can you tell us when you might start taking delivery of that fuel? And is there a date by which you need to firm up that agreement?
Yeah, I think just to clarify, right, the first fuel we're getting for our first plant, that was awarded to us through a competitive process by Idaho National Laboratory and the Department of Energy. So that material is all from there. That's for our first plant. Everything with like commercial procurement happens for our second and beyond plants. And that's where we're looking at, you know, obviously working with Centris and others Um, what we see is, uh, you know, we're in the process of kind of figuring out the right structures to supply for what we need and kind of the growth and scale. So I think the idea is, you know, as we look at partnering with different folks on the, on the enrichment side, it's, it's really working to sort of what's the sort of right ramp rates for them and for us, given the customer off takes and how customers might be engaging or not engaging on this is something that we're kind of watching as this develops and we're helping develop and shape as we speak live time. You know, we'll want to start receiving that fuel as soon as reasonably possible, but some of those pieces are going to be the things that we want to put in place to make sure we set the stage for kind of a long-term growth curve up and out. When you look at what our fuel needs are, they're pretty exciting and pretty heavy. But that's great for the enrichers on the supply side, but just structuring the right kind of early deals and then also coupling that with some of these customer bases where we have, sorry, customer partnerships where their ability is to sort of come in and help actually potentially, right, uh support some of the fuel offtake that's how we're we're kind of looking at shaping some things right now a lot of that's still developing but generally speaking that's how we're structured on that sense but it's super super helpful and important right we have fuel it's actually at Idaho it's being you know we're setting up the fuel fabrication capabilities to actually be able to take that fuel and fabricate put that in our first plant um but that material has all been you know it's all out there it's all been produced um from from government reserves and inventories And that's kind of another key watch point for us is some of the actions that are potentially coming from the government. Ideally, there's a lot that moves forward on the fuel side, and we're really well positioned to be able to benefit from a lot of that beyond just what we already have.
Got it. That's helpful. And sticking with those, I guess, second and later plants, when we talk about the timeline for subsequent COLAs, um i think in the past you've said six to 18 months would that apply to reactors in different sizes let's say a customer wants to do 75 megawatt design um or is the timeline the same as the first custom cola that we're doing about to do um yeah so they'll be for the same general plan um uh what we see is you know
The timing is going to depend a little bit, but I think it'll be a staggered parallel fashion with the INL plant. The Idaho plant is a full commercial plant. We're building it on a national lab site because there's a lot of benefits of doing it, but it's a full commercial plant. And then there'll be all these things that happen after that with respect to follow-on plants and follow-on sites that we're excited about how those are progressing and developing. That said... I think the timing of those is sort of we see a couple major sites that we've obviously talked about, and we see the different customers that we've announced, and there's a very dynamic market in that sense. So what we expect is that there'll be some COLA activity that we anticipate submitting additional applications in parallel to all the first ones under review that will see some acceleration benefits, but then the real benefits will really happen on the acceleration of the COLAs. Patrick Corbett- After that we're doing a lot of like we kind of cutting edge leading edge work with the nrc on doing some of the subsequent licensing and high volume kind of high rates. Patrick Corbett- of deployment they've been developing you know activity i'm sorry capabilities and plan that lines of sort of action. Patrick Corbett- around how they're going to review those things going forward so that we're going to be one of the initial movers and one of the early kind of beneficiaries of that of those approaches. which is pretty exciting for what that looks like. But kind of that's how we see these things kind of playing out from there. But I think it's entirely likely that, you know, by sort of a year from now, we have additional COLAs under review on top of the INL one.
Got it. Thanks, Jacob. I'll turn it over. Your next question comes from the line of Vikram Bagri of Citi. Your line is open.
Hi, it's Ted on for Vic. Thanks for taking the questions. Um, I wanted to ask about the funding needs for the business, uh, just given the larger reactor size, uh, that was mentioned last quarter, um, the growth needed for atomic alchemy, uh, potential costs from terrorists, and then also potentially higher Haley prices than the initial plan. Just wondering whether, given all those factors, additional capital will be needed, and if so, when we could expect roughly that might be raised.
I'll just start really quickly. I think, again, an important point is on the fuel, right? We have the fuel allocated and awarded to us, so that helps a lot with the first plant. And then, you know, as we've looked at things, I'll turn it over to Craig here, but I think that's a big help with respect to how you sort of manage some of the Haley pricing. But with that, I'll turn it over to Craig for kind of the dynamics on that.
Yeah, and just to reemphasize the point of the balance, you've got adequate capital on it for the deployment of INL. Now, you know, it was almost two years ago since we announced these back in a year since we closed. And since that time, Haley prices have gone up, as you mentioned, Ted. We've also dramatically grown the order book. And we've now got customers wanting a much higher size powerhouse offering that is more capital efficient, but it is going to cost more capital per unit. And then we are, you know, we're two years on from the juice pack, which means we're two years on towards things to bring recycling forward. So, you know, we'll want to be positioned such that um capital um does not become a constraint as we look to progress those um growth plans and you know we'll make sure that if there is a need to raise capital we'll do that um when the time and circumstances are right so that we can do it um in a strategic manner not a reactive manner got it thank you um and i had just one follow-up um on the viper facility that was mentioned
Could you just elaborate on what the NRC process looks like for that? So it looks like there'll be a construction permit submitted this year. How does that process differ from the process for the Aurora powerhouse and then also just in terms of intensity required with the NRC? And are there any additional costs for that over and above what's provided in the guidance?
Yeah, I think, I mean, the licensing process and progress is really centered around a part 50 license application, which is a bit different. This is a non, this sounds funny, this is a non-electric power producing reactor. So it benefits from a different regulatory approach that looks a lot more similar to what university and research reactors look like. So good news there is there's some benefits that happen from that, from an efficiency side, but it is inherently built to a two-step process where you get a construction license and then an operating license. However, given kind of the nature of the review of those systems and that we expect that the construction permit review will happen at first, you'll build significant amounts of the plant and you'll apply for the operating license thereafter. This is similar to the process taken by Kairos, which received their construction permit, and then a couple other active groups that are doing work in the space on that. So that's what the application review process looks like. Again, that's quite different than a part 52, which is for power reactors, so electric power producing reactors, and doesn't have the repeatability functionality built into it because typically these kind of test reactors or these non-power producing reactors are built around kind of that not needing that repeatability so what's kind of neat about it from the oklahoma side is we're going to have a lot of experience and expertise around both those processes and there's some efficiencies that we're looking at seeing as as possible benefits to inform sort of future activities around either continued sort of regulatory modernization uh efforts um as well as potential legislative efforts around applying some of the best practices between the two to each other um and we'll obviously be kind of at the center of that experience, which is kind of neat, actually. But that's how we see those things going. Generally speaking, it's considered to be a simpler, more straightforward process to get a non-power license than a power reactor license, just given the relevant hazards around a low-power reactor operating in that kind of environment. So typically speaking, the regulatory process kind of reflects that.
Got it. Thank you.
Your next question comes from the line of Eric Stein of Craig Hallam. Your line is open. Hi, Jay Keckard.
Hello. Hey, how's it going? Hey, Eric. Good. I'm glad I wasn't sure what was going on there. Hey, so just curious, you know, I know you've done the readiness assessment. You've had quite a bit of interaction with the NRC, but also know the NRC is is known for that being a pretty onerous process on the licensing side. So as you get closer to submitting the COLA, I mean, is your confidence higher or what has maybe changed in your view, if at all, as to your prospects to move, as you said, to a commercial facility and not having to go through kind of the typical demonstration plant that might have to operate for three, four, five years?
Um, yeah, I mean, I think generally speaking, so just to be clear, this is a full commercial plant, right? Like, uh, this is a full commercial plant that will operate commercially produced full power, do all of that. Obviously it's the first plant. So there's some learnings you, you both design for an engineer around to be able to accommodate and be able to iterate through, but this is not kind of like a, Oh, build it and see how it works. I don't know. We're building out for technology that's done that already. Right. There's been two noticeable, notable examples on top of 20 plus reactors from before that around the world built around sodium fast reactor technology showing what works and what doesn't work. And the successes at EBR2 and FFTF are very significant sort of enablers for us to actually be able to take those technologies forward, apply those, right, take those lessons learned, apply them, and basically replicate what was done in many ways because they were so successful. So that's really important, right? I think sometimes the facts and the realities of sort of the history around non-lightwater reactor technology development is often very underappreciated, even in the nuclear industry. And a lot of that's just because a lot of that pioneering work happened between the 60s, 70s, 80s, and 90s, pre-digitization. Actually, I think there's a big part of the story to this, which is a lot of those lessons learned, a lot of the records, all that stuff were written in paper, put in books, put in binders, put in reports that were literally printed and filed on shelves, like literally printed. I used to say left on the shelves of history, literally, because they were. And that, as a result, had meant that accessing all of the wonderful nuggets of information that had been out there about these things, well, wasn't exactly easy to do, unless maybe you're an academia or in the research and development communities, which Caroline and I were. So we had the benefits of having a lot of the opportunity to see a lot of the amazing things about this technology set. and how mature it really was, something that, again, is vastly underappreciated by and large. And so that's a fantastic spot to be. Now, one of the things we leaned into very early in the company's history was even starting with our first regulatory interactions, including getting the Department of Energy to help with this and the National Labs to help with this, working with the NRC back in 2016, was actually getting that old information, digitizing it, modernizing it, being able to use it in the regulatory space and that we set off a bunch of activity and work in 2016 that really is continuing through today that pays significant dividends, right? So that kind of dovetails into your question of, yeah, I mean, generally speaking, as we've seen our engagement with the NRC, we've had 600 plus meetings with them. I mean, we have a huge amount of interactions in history leading up to submitting an application. You know and and being in a position that we feel you know pretty happy about so obviously the bread we're doing a readiness assessment to make sure that we understand where there might be gaps, so that we can work to address those. we've seen that had a lot of success with what their power did they also did a readiness assessment before they submitted their construction permit and or the construction permit application and. they've seen that their review has been moving. pretty well on pace I think it's slightly ahead of schedule even so that's fantastic we expect there to be some similar benefits for us obviously each case a little bit different but generally speaking that's why we've been at this for so long of all the non-light water companies active today with the NRC we've had the longest engagement right dating back to 2016 and that's a very important thing for us for having sort of that history and that maturity and that kind of credibility and capability accordingly with the regulator. I think the thing that's important is also how we take an approach isn't just about whether or not you get the license, but doing so efficiently and effectively. And I think that's that next level of depth and nuance that I think people are starting to fully understand the importance of, which is not just getting a license. That, I would say, is something that's quite doable. It's also doing it efficiently and effectively so it's scalable. And that's where we spend a lot of time trying to optimize for that. Um, back in 2019 or 2018, when we first piloted an application with the NRC, they said they could review something like that. They thought that that made a lot of sense that we proposed all these novel things, something they then built a novel review plan had based heavily on doing based on doing things. I mean, heavily in person in 2019, obviously when we submit an application for all this in-person review dynamics in 2020, that, that didn't work out so great given that, um, you know, the pandemic blew a lot of that stuff out. We couldn't have those in-person meetings and dynamics. We had, you know, obviously. change course, and that became somewhat challenging. But since 22, when we started reengaging with them in person and pre-application on this, we've been able to kind of structure around addressing some of these open items and some of these items that we've tried to push the NRC to be forward leaning on. And frankly, we've found that there's been a lot of things that they've been pretty receptive to. Still a lot of work. It's not like, hey, this is going to be a walk in the park. It's still a lot of work. There's still a lot of existing inefficiencies, frankly, in the regulatory process. but we couldn't ask for a better setup right now amidst the drive and demand on the AI side, as well as a bipartisan level of support coupled with a very, you know, an administration that's very focused on driving regulatory efficiency throughout the entire ecosystem. So all in all, it creates a pretty favorable dynamic, I think, for where we sit and how we're seeing this come together. So I guess I would say like the pre-application engagement is a way to, that we've done continually more or less since 20, well, 2016 and, Patrick Corbett- sort of re up in 22, if you will, into what we're doing now like has been has been quite I think. Patrick Corbett- Constructive to preparing both parties to be ready for an application, I think, from the feedback we've had from the energy has largely been around okay we're. Patrick Corbett- we're really getting ready for you guys have an application now we've done all this work, but I think we're getting ready for it, so we see that we expect to see how that plays out with the phase one readiness and then we'll. we'll kind of move that to the next steps of the review, hopefully, with some of those efficiencies gained. That doesn't take care of all the bumps and problems. There's still going to be things that come up, of course, but at the end of the day, it gives us a great shot on a lot of those angles.
That's great, Collin. Thank you. And then just for my follow-up, I mean, should we still think about timing of the actual COLA submission to be, I think in the past you'd said, kind of coincide with the Advance Act in the October timeframe?
yeah that's how we're looking at it um i will say that with all the pending activity around like executive orders and all these other things there's i would call it good uncertainty because it could motivate some reasons that things might move somewhat faster but um at the end of the day like uh that's how we're seeing kind of the timing evolve here so you know we expect to transition out of the readiness assessment with the feedback we get from that to be able to support us submitting for actual phase one application in um a few months after kind of the feedback from that And then that would position us to then do the readiness on the phase two part. And then also with the feedback from that position, us to be able to submit that sort of in the Q4 time frame is what we're expecting. OK, excellent. And that would mean full applications in at that point, yeah.
Your next question comes from the line of Jeffrey Campbell of Seaport Research Partners. Your line is open.
Good evening. Jake, on slide nine, Hey, on slides nine and 11, the fuel recycling and the feedstock preparing the submission to the licensing project plan for the fuel foundry. I like that. I like that name. Can you add some color on how this licensing effort might be different than that for Aurora? What the primary hurdles might be and what the timing might be like?
Yeah, it's a good question. We've been engaged with the NRC on the pre-application activities to submit for large-scale fuel fabrication work that, you know, is outside, right, just to kind of recap. We have fuel from INL and the Department of Energy for fuel for our first plant. We'll fabricate that fuel at the Idaho National Laboratory. We're building a pilot fabrication facility there. By that, I mean we're installing the equipment in existing buildings. But then as we grow and we look at sort of this backlog that we've been accumulating, we're working to set up a full-scale fuel fabrication facility, not full-scale, but I call it large commercial scale, to help us kind of start to meet that demand set. That follows a different regulatory path than the typical like Part 50, Part 52, because it's just materials handling, it's not reactors. And so it depends a little bit on the specifics of the site and the infrastructure that we're taking advantage of. But that's something where, you know, as we've been engaging with them, you can expect a full sort of application review to be done potentially in the 24 to 30 month time period, possibly as long as 36. It depends on how much infrastructure you need to install. Given the nature of kind of the regulatory environment today, there's some benefits that those timelines might be reduced. I do think there's a general view that this should definitely be done faster than reactors. So everything that moves those timelines is probably going to help with this. So that's kind of how we're seeing that progress. But we're going through evaluating different site opportunities accordingly for that. And as those things continue to progress, we'll have good updates for the market and for investors as those come together. But generally speaking, that's how we expect that to go to sort of unlock our ability to scale into the very exciting numbers and customer bases we have.
Right. And that's very helpful. The point about being faster than a reactor license certainly makes sense. My follow-up is, is this essentially somewhat similar to the way you've talked about your COLA licenses and having multiple applications even as you're waiting for INL? Is this already an effort to create a blueprint for potential field founders in a variety of locations? In other words, already thinking about scalability and the fuel foundry in the same way that you're thinking about what we want?
Yeah, it's a great question. It's definitely something we think about here. We aren't baking in necessarily the same scalability, but the lessons learned apply forward will be helpful. The reason I say that is because, like, we kind of expect this facility to be pretty large to meet a lot of our need sets for a while, and then Beyond that, we kind of are looking at how this can be built and done in different places potentially as needed. But generally speaking, this is all happening, which is like, that's a really silly thing to say. This is all kind of progressing in a way to expect to build one, but understand that there might be scalability for beyond that. So it's kind of a weird non-answer, but we're saying, yes, there's ability to have scalability from it, but The infrastructure of the regulations themselves, the actual structure, doesn't really allow for that same translatability, for repeatability, the way the reactors do, because it's not anticipated you'd build many of these. But there's going to definitely be lessons learned, and there's things we're trying to do to allow for that where it makes sense to do. But generally speaking, you know, that's kind of a thing that we'll keep watching as we kind of think through and get into the actual licensing process here. But if, you know, as we think about the opportunity space for the business, it does make sense to think about having multiple locations most likely. Um, but, but kind of not do all those at once, obviously, but that's stuff that kind of lags by probably by five to 10 year increments, as we think about the long scale growth and potential here.
And Jake, I think the other thing is, you know, size of the facility and the scale economies, you may get on one end, but logistics of having the difference between having one plant and one, one family and one location versus multiple locations and what it can do around logistics.
Your next question comes from the line of Samir Joshi of HC Reinright. Your line is open.
Hey, good afternoon, Jake, Greg. Thanks for taking my questions. First, congrats on all the progress. My question is about the borehole drilling campaign that you just announced this morning. I think the press release says that it will inform your detailed engineering design. I'm assuming this engineering design pertains to the building and building stability as against the balance of plants like the steam generators and the power conversion system that may need any modifications. Will you confirm that?
Yeah, the way I understood that was really if we expect to see like what the data does or sort of the insights from the site characterization due to impact sort of the detailed design. Yeah, I mean, generally speaking, you know, it's really just to make sure that the site characteristics and where we're exactly going to be building, like we just engineer all the right like structural mechanical pieces in the right ways to support that, that are kind of bounded by how we take that sort of bounded kind of standardized approach as is. That's really how we kind of angle to incorporate that feedback. But it's important to have that information to support then, you know, also in the regulatory process, which is kind of why we do it, if that makes sense.
Yeah, yeah, no, understood. And then the second question I have is, and maybe this has been discussed in the past, but just I want to make sure I understand. Now that you are in the phase one or initiated in the phase one of the pre-application readiness assessment, has this phase also included the specific size of the reactor in terms of whether it is 50 megawatts or 75 megawatts? Or will this be needed to be included in phase two or the next stage? Just wanted to understand that, mainly in context of one of the previous questioners who asked if the subsequent COLAs can be of different sizes. So just wanted to understand the phase one, phase two, and when you have to specify what the COLA is for, whether it is for 75 or 50 megawatt.
Yeah. So pretty much everything we're really doing is at the 75 megawatt size range. That kind of is the generalized design. And then if we flex down from that, it's just because there's a customer need or a specific need to do so, which would then, generally speaking, bound against, largely speaking, the same analyses and everything else that we do to support the 75. So really just think of it as kind of a consolidated single platform that we build off of from the licensing side. Each site, then, if it does change a little bit it's going to, obviously each site has to get its own license, but the benefits of sort of the repeatability and scalability be scalability because of that approach, you know, should hold pretty heavily. Obviously if we make significant departures by introducing major design changes, that changes some of that, but that's, That's not exactly like, you know, in terms of the near term deployment, that's not what we're intending or planning to do. And that's part of why we made that decision to kind of just centralize and focus around the size range. What that means then is if a customer wants it to be a 60 megawatt variant, then it's the same plant that we're building. We're just basically, you know, as we use the term, kind of underrating it and running it at a lower power level and then maybe low, you know, then have the ability to potentially increase that power level with more fuel going forward. So that's really how we're trying to approach that. Justin Delacruz- With the Idaho plant specifically like that's the same approach we're taking, however, we have we have a fuel constraint right we've been awarded fuel. Justin Delacruz- And to sort of best use that fuel, we would be running that plant at less than 75 megawatts. Justin Delacruz- But we're also pursuing options to perhaps and get more fuel to run that up at a higher power level that just depends a little bit on sort of our. kind of some of these activities are going to play out with respect to the fuel supplies, especially given the fact that, you know, there's another five tons of that material that we requested that's available potentially. So like, you know, some of that material we could use to help us run all the way for a full cycle at the full power level. But that's kind of how we're approaching this right now. But yeah, everything really centralizes around kind of that 75 megawatt level.
I understood. May I squeeze in one more for the Okla Fuel Foundry? Will this facility be also able to handle recycled fuel for the fabrication facility?
It's an interesting question. So what we're talking about with the fuel foundry piece here is specific to fresh fuel fabrication. However, next to – not next to physically, but in terms of in addition to that, we've been ongoing on the regulatory front for I think dating back to at this point, 2021 and pre-application preparing for the fuel recycling facility. That fuel recycling facility would also include, that would include the actual recycling as well as the fuel fabrication facility for recycled fuel. the fuel foundry we talked about here that's really specific to fresh fuel the same techniques and you know approaches in terms of facility design and process design generally speaking will be used to handle recycled fuel it's still metal it's still casting based but it has to be done obviously in a different environment given the nature of the recycled material it's casting in other words the transuranic bearing kind of feedstock that we're fabricating the fuel out of So that's a really important thing here, right? The recycling means you don't need halo. You're not using halo. You're instead using the transuranics and the uranium from recycling itself. And as a result, the material is more radioactive. It's also thermally hotter. So you need to fabricate that in a different way or in a different kind of set of constraints, but it sets a really good stage for recycling. how we can like, you know, apply some of the technologies for it. So to answer your question, the activities going on on the regulatory side for recycling are different than the fuel foundry side. But of course, there's some relations.
Got it. Thanks for that, Tyler.
Have a good one.
Your last question comes from the line of Craig Shearer of Tuohy Brothers. Your line is open.
Good afternoon. Thanks for fitting me in. So let me jump on that same line of questioning. So what exactly is the CapEx delta between a commercial-scale fuel foundry versus recycling facility? And while the licensing for fuel may be quicker than for the plants, the Aurora powerhouses, how long are we talking about constructing a foundry or recycling facility or constructing?
yeah um uh it's a couple things so basically you've got um if you think about this right you have basically two major centers for fuel for oakland plants going forward you have one center which is around fresh halo we procure that material and then we fabricate it in our fuel foundries to make fuel to go into our reactors then you'll also have the recycling side that comes in and you know we'll start to be able to recycle fuel from existing you know um plants that are producing power today as well as okla plants as well as other advanced reactors actually we can take all that material and recycle it produce a new feedstock we can make fuel out of at the actual you know uh recycling facility and then have that material go fuel some okla plants as well um so generally speaking like You know, we see those, the fuel, the foundry will most likely come into existence in terms of being operational before the recycling facility, just given the nature of kind of licensing and the technology development and everything else needed for that. And then from there, we kind of see that staged approach of you get the fuel foundry going, fabricating fuel for our plants, you get recycling that comes in later, produces fuel, all the benefits kind of play forward in those areas. But generally speaking, I mean, and I'm not saying they're staggered on purpose. It's just kind of the nature of sort of how we think about the infrastructure build out and the planning on that. So a lot of exciting stuff coming, but generally speaking, it sets the foundation for like, you know, things that then allow us to kind of grow and scale. Now, important things that come from this too. Fuel fabrication is great, allows us to make fuel. Also opens the door for us to look at potential partnerships with others to make fuel with or for others. Additionally, on recycling, similar kind of things. So good, nice opportunities to touch in and tie into different pieces there, which is pretty important. If you have a licensed facility to actually fabricate fuel, of which currently in the United States, you know, there's really, like, there's just not, it's pretty significantly undersupplied for advanced reactors. There's just not that much out there. A big opportunity, obviously, for us to be able to have that facility and perhaps support some other activity that others are doing in addition to what we're doing. So some cool things all kind of come together on that and one illusion just appoints you between both obviously stuff we did. Earlier in the year, but you know, a couple months ago, we obviously have a partnership with light bridge just kind of an example of how these things kind of can tie together now with the infrastructure and facility work we're doing. But generally speaking, you know kind of the focus, we have is okay, we know we're going to like those things support us for after you know what we have going on right now with Idaho with. the pilot fuel fabrication facility we have there as well as with the first plant we're building there. So that's kind of how we think about sort of the staging in order of operations. Craig, I'm not sure if you want to add anything specific to the commentary around kind of the incremental capex, but that's kind of how we're thinking of the phasing and the structure of this.
Well, I'd say, Jake, you know, there will be incremental capex there, but really we'll have more to say as we've kind of completed some of this appraised work on both the foundry and the recycling. And so we're No, I think it'd be too early at this point for us to talk about what that could look like.
That's fair. Could we just presume that the recycling takes more capital and longer to construct versus just the foundry? The recycling facility? Yes.
Yeah. I mean, generally speaking, because you're putting in fuel fabrication as well, yeah, it's going to be It's going to take longer to build and take more capital, generally speaking, than the fuel foundry will, is how we think about it. Now, the thing with the recycling, though, is you also open up all these massive opportunities for additional potential revenues, right, from additional radio essence of co-product sales, additional uranium sales, additional actual true bearing fuel feed sales. So a lot of things that kind of come from that, too. So it kind of diversifies that piece, which is something that we're particularly excited about, not to mention the massive savings it gives us compared to fresh fuel, which is pretty huge. But yeah, we expect that to be something that takes longer and will cost more than the fresh fuel foundry.
Great. And my last one, you touched on this a bit in Sharif's questionings. But it kind of feels like the foreshadowed new executive orders and Department of Defense involvement to grease the rails on U.S. nuclear could by far be the most meaningful on the fuel side, not government property and other things. Would you agree with that? And if so, what tangible perspective federal steps would you want to see on that front?
Yeah, I'll give you a long-winded answer to this, but I think there's a huge amount of, I'll call it, greenfield opportunity right now in terms of the policy landscape and in terms of the appetite to use, I'll call it, the national resources and assets we have as a country with respect to deployment between significant federal lands, like at the Department of Energy, requesting information about how they might be able to support building data centers at existing DOE sites. That could also tie over potentially to benefits of them being able to actually be the regulator on some of those sites, potentially. I mean, some of this depends on a lot of moving parts, but that could provide a significant accelerator benefit, accelerative benefit. At the very least, it provides an interesting competitive alternative dynamic to the NRC, which I think is good, right? Competitive dynamics like that are kind of good for everybody. So it's pretty cool. And just for us, one benefit we have, right? Like we kind of, we often have, we haven't actually talked about this as much as Maybe there's some interesting opportunities to do so, but the Department of Energy was going through the process of designing and building out and therefore included their having to approve, they're having to go through a regulatory process of their internal regulatory authority and authorization of a sodium-cooled fast reactor for neutron irradiation testing purposes. A lot of the work that they did in that process and for that project, for the safety evaluations and all those pieces, have significant carryover and benefit to us. And as a result, we've seen some of that actually place forward some benefits on the NRC side, because I think generally speaking, it's safe to say that regulators in general, like, well, I think all of us, it's not just them. It's all nice when you can build off of work that others have done as well, and you don't have to do it all kind of from scratch yourself. So if that's the case, then, you know, as we've seen there, there's some benefits. So if some of that activity and some of these potential ideas uh that we've heard kind of circle around and we know there's been appetite in capitol hill from conversations and also in different ngos and think tanks and activities around how to best leverage the regulatory authorities that the department of defense the department of energy and the nrc have kind of in a cooperative but also maybe somewhat competitive dynamic that's pretty favorable if you think about what we're doing too at idaho we have a great head start on some of these activities given we have a site use permit where deep in the process of deploying and developing there, if all of a sudden there's an opportunity to perhaps bring in folks like hyperscale partners to there and maybe build more plants there and then have some benefits because we're doing that, whether it be the Department of Energy as a regulating body or some piece like that, there's some significant benefits that can kind of come from all those pieces together. Another side of this, the work we're doing out that we announced some time ago, but part of our partnership with Centris was looking at building two plants, right, to build two plants in Ohio to help support sort of what they're doing. And that has some carryover from, you know, from Department of Energy Environment Management kind of legacy land that they've been turning over for development. So a lot of cool opportunities between the different things we've been doing on the DOE and DOD sites. Obviously, our selection and the DAU process as part of the ANPI program is also helpful for unlocking some opportunities to provide power direct there, given that, you know, AI and energy are considered, you know, pretty important things for the national security perspective. There's also opportunities to do stuff at defense land that could be constructive here as well. So I'm kind of giving you this wraparound answer to say, right now, there's a lot of the art of the possible on the table that could be really, really attractive and pretty exciting in an accelerative manner. But, you know, we'll see. Like all this stuff is actively evolving and it's going to be iterative and dynamic, I think, over the next, Patrick Corbett- couple years, frankly, but especially over the next couple months so we're we're we're excited to see what might be there and what might happen with this and we're we're trying to kind of. Patrick Corbett- thread the needle and push where things make the most sense to sort of accelerate getting plants built and scaling accordingly and bringing the right resources to the table, but that would be pretty constructive and helpful. Patrick Corbett- And then I think another dynamic that ties to that we talked I just talked a lot about fighting and regular side but. The government also owns a lot of material that could be used as fuel. And ideally, there's some opportunities to sort of accelerate that and build off of what they've already done with us, what they just did in the next round of those things for other companies building kind of small scale test plants. We're excited, but hopefully these things kind of continue to scale and ramp up for more opportunities there as well.
Thank you. I'd now like to pass the call back over to Sam Doan for a question from Oklo's retail investors. Please go ahead.
Thank you. Yeah, we had one question come through. The question is, can you elaborate on the current stage of your discussions or agreements with data center operators or hyperscale customers and how these conversations are shaping the deployment timeline and reactor siting strategy?
Yes, I can take that one. So, you know, as we said, you know, at our last call that, you know, we continue to have active discussions with all of our customers, especially those in the data center space we are. exchanging term sheets that we're talking about, you know, commercial terms. And I think it's really about how do we optimize what we do commercially around, you know, kind of, as I hold it, three factors. There's power purchase pricing itself, but there's also trying to structure deals with customers that could include some form of investment in OCLO, either kind of a prepayment like what Equinix did, or potentially some sort of like asset level investment. and also just try to work with customers that can help us share and manage risk better. In addition to one of our new hires that Jake talked about earlier, Patrick, we've also had Mike Donahue join Oklo as the person leading our business development activities, focused specifically on our data center solution customers. And I think, and Mike's been with the company a couple of months, and I think he's kind of reinforced that, you know, think about this, strategically and do it in a thoughtful manner approach that we've been taking. Now, Jake did talk earlier about the ability for us to file and have more permits on file as the first permit for our Idaho site is being reviewed. One thing we do need to have in order to file a permit is to kind of know which where we would be locating that site beyond Idaho. So that does kind of become an important step in terms of our contracting strategy linking into our permitting strategy. But we're making a lot of progress, and I think it's fair to say that our business development team is one of the busier teams in Oklahoma.
Thank you. That concludes our Q&A session. I'll now turn the conference back over to CEO Jake DeWitt for closing remarks.
Great. Thank you all, and thank you for the time, as always. I think it's only been about seven weeks since the last call. A lot of different things kind of transpiring in the broader sort of macro environment since then. And what we see, though, is kind of a consistent steady drumbeat on the AI kind of theme around energy need and sort of on the hyperscalers coming to the table and seeing a massive set of opportunities for growth uh for compute but massively constrained by power um you know at a congressional testimony just a few days ago uh I guess last week um our former chairman Sam Altman made it pretty clear that energy is probably one of the best things most and most important things the government can invest in uh and I think and just generally speaking be invested into uh and so pretty exciting opportunity space to see all those come together and couple that with a broad policy backdrop and an administration that has a heavy focus on driving infrastructure development, growth, investment, and driving the regulatory process to be conducive to that, all sets the stage for, I think, a lot of things to actually exceed expectations in some ways with the potential of ideas out there, but a lot of challenges, obviously, against that. However, we're in a different world today than I think nuclear has ever seen before, and coupling our sort of distinction with the business model we afford, our approach and technology, and kind of the integrated model we have uh we're starting to see some of the clarity of kind of the alignment of what those things unfold and enable as well as just you know generally speaking the ability to move technology development and deployment more quickly and and significantly change the paradigm that has in some ways challenged nuclear which had a lot of misaligned incentives had a lot of different parties and transactional dynamics that made nuclear really hard to scale and build These things are all a different world today. You have some of the biggest companies in the world needing power in almost insatiable amounts, having deep pocketbooks and the ability to support paying prices needed to get early plans built with a clear angle on cost declination. Beyond that, down the road, and then be able to also couple that with best practices from other industries and supply chains to really be able to deliver what nuclear long has in terms of its potential and promise. Uh, we, we, we remain, I think the mission here is, is one that transcends even just kind of the quarterly basis or the yearly basis, but something that we're working to unlock is, is the actual like, you know, capabilities afforded by splitting atoms, which when you think about heavy metal reserves, uh, that we have in the planet, coupled with fast reactors and recycling, you can talk about billion plus year, you know, energy reserves available to us with technologies. that have quite a bit of maturity behind them. So we're excited to be working on that and leading the charge on a lot of those fronts and looking forward to, you know, the next update here in a few months.
This concludes today's conference call. You may now disconnect.