8/13/2024

speaker
Operator
Conference Operator

Good morning and welcome to the Caliber Mining Corp 2024 second quarter conference call. All participants will be in a listen-only mode. Should you need assistance, please signal a conference specialist by pressing the star key followed by zero. After today's presentation, there will be an opportunity to ask questions. To ask a question, you may press star, then one on the touch-tone phone. To withdraw your question, please press star, then two. Please note this event is being recorded. I would now like to turn the conference over to Ryan King. Please go ahead.

speaker
Ryan King
Senior Vice President, Investor Relations

Thank you, operator. Good morning, everyone, and thank you for taking the time to join the call this morning. Before we commence, I'd like to direct everyone to the forward-looking statements on slide two of the presentation. Our remarks and answers to your questions today may contain forward-looking information about the company's future performance. Although management believes that our forward-looking statements are based on fair and reasonable assumptions, actual results may turn out to be different from these forward-looking statements. For a complete discussion of the risks, uncertainties, and factors which may lead to actual operating and financial results being different from the estimates contained in our forward-looking statements, please refer to the Q2 and year-to-date 2024 MD&A and consolidated financial statements available on our website as well as on CDAR+. And finally, all figures are in U.S. dollars unless otherwise stated. Present today with me on the call are Darren Hall, President and Chief Executive Officer, Daniela Dimitrov, Senior Vice President and Chief Financial Officer, and Tom Gallo, Senior Vice President, Growth. we will be providing comments on our second quarter and year-to-date 2024 results, after which we'll be happy to take questions. The slide deck we will be referencing is available on our website at calibremining.com under the events section. You can also click on the webcast to join the live presentation. With that, I'll turn the call over to Darren.

speaker
Darren Hall
President and Chief Executive Officer

Thanks, Ryan. Moving to slide three. Good morning, and thank you for taking the time to join us today. Firstly, I'd like to thank all Calibre employees and business partners for their continued focus and diligence to responsibly deliver another quarter. The organisation's commitment to act like owners is demonstrated in the following three recent milestones. In June, the Calibre team in Nevada surpassed three years without a lost time injury. In Q2, our Nicaraguan operations reported year three conformance with the World Gold Council's Responsible Gold Mining Principles. This significant milestone reflects the team's commitment to foster positive impacts on the environment, engaging with and supporting local communities, and upholding rigorous governance standards. And in early August, the team at Ballantyne passed two million hours worked without a lost time injury. Switching gears, I would like to take this opportunity to welcome Daniela Dimitrov to the team, Excalibur's SVP and Chief Financial Officer. Daniella joined Calibre in June, and their positive contributions are already evident. I look forward to Daniella's insights and contributions as we continue our journey to a quality mid-tier gold producer. Moving to the quarter, consistent with expectations, the company delivered 58,754 ounces of gold in the quarter. Q2 saw higher tons mined, largely stripping at the open pits in Nicaragua, resulting in short-term cost tension that's setting us up for a stronger production leading to lower oil and sustaining costs in H2. Given our projections for the remainder of the year, we are on track to deliver into our full-year production guidance of 275,000 to 300,000 ounces. The team's progress at Valentine in Newfoundland has been very pleasing as we march towards first gold in Q2 2025, which I will talk to more shortly. I'm excited by the significant exploration opportunities across our portfolio of assets, not the least being on our Valentine property, where we recently commenced a 100,000-metre drill program. More on that in a minute. Turning to slide four. As mentioned, first gold of Valentine remains on schedule for Q2 2025. The addition of Valentine to our portfolio of assets will establish Calibre as a quality mid-tier gold producer in the Americas, providing a compelling re-rate opportunity for all shareholders. I am pleased to report that construction of the fully-funded Valentine Gold Mine was 77% complete at the end of July, and the team continues to make good progress, consistent with the schedule and spend provided in our May project update. A few recent highlights. Line of placement is well advanced at the tailings management facility, and we expect to retain water by the end of September. SAG, ball mill and primary crusher installation is well underway. CIL tank area construction is nearing completion. Steel mechanical piping and electrical and instrumentation is advancing consistent with schedule. The operations leadership team is employed and engaged in pre-commissioning activities with RCC. Importantly, federal environmental approval and provincial mining and surface leases for the Berry Pit and associated infrastructure have all been obtained during the quarter. We have commenced a scoping study to review phase two process plan expansion options focused on investigating combination circuit alternatives. It's early in the analysis, but I'm encouraged that there are options which may present even higher returns than the feasibility study envisaged with the original phase two plan. With 211 million Canadian in initial project capital remaining to be spent and 350 million Canadian in cash and restricted cash, The Valentine build is fully funded. Moving to slide five. This slide provides an aerial view of the Valentine site, looking southwest over the tailings management facility towards the process plant and mining operations. The photo provides a good perspective of not only the scale of the project, but importantly, construction progress. It's great to see the project evolve as the team steadfastly progresses towards first gold in Q2 2025. Turning to slide six, the Valentine Gold Mine and surrounding property offers a robust 5 million ounce resource base and numerous discovery opportunities from an extremely prospective array of exploration targets with similar geology to the prolific Valdor and Timmins camps in the Abitibi Gold Belt. It is this prospectivity, coupled with the encouraging results we've seen, which supports the recently announced expansion to our Valentine Exploration Program. During Q2, we commenced an additional 100,000 metre drill program across the flagship property to confirm the vast potential of the Valentine District, comprised of 64 kilometres of high potential discovery opportunities along the two parallel shear zones. This program is in addition to the previously announced 50,000-meter wall control RC drilling program and the 10,000-meter Winky RAB drilling program, which is focused on testing for bedrock geology. Additionally, drill results from the exploration programs across Nicaragua reinforce the potential for discovery and resource expansion, both within the 176-square-kilometer eastern Barosi land package located in the northeast, and the VTEM Gold Corridor located within the Limon Mine Complex. At Volcan, rapid progress following receipt of key environmental approvals for the development of the open pit resulted in first ore being delivered to the Limpetag Mill within a month of permit receipt, which will contribute to a stronger H2. Drilling at Volcan confirms the deposit can host higher-grade near-surface gold mineralization in excess of the initial open-pit resource average of 2 grams per tonne. Moving to slide 7. In closing, I am confident in our ability, as we have demonstrated, to deliver on our commitments. With detailed engineering at 98% and construction at 77%, Calibre is well positioned to responsibly deliver the Valentine Goldmine and commence production in Q2 2025. The company remains committed to deliver into our 2024 production guidance as we drive increased production and lower costs during the second half of the year. With demonstrated resource growth and discovery potential across all assets, Calibre will continue to add significant value through investment and exploration. We will continue to look forward, grow the company organically, maximize the full potential of our existing assets, and choose the most sustainable and accretive path forward to drive shareholder value. With that, we're happy to take questions.

speaker
Moderator
Conference Moderator

I'll pass it back to you, operator.

speaker
Operator
Conference Operator

We will now begin the question and answer session. To ask a question, you may press star, then 1 on your touchtone phone. If you are using a speakerphone, please pick up your handset before pressing the keys. If at any time your question has been addressed and you would like to withdraw your question, please press star then 2. At this time, we will pause momentarily to assemble our roster. Our first question comes from Dom DeMarco with National Bank. Please go ahead.

speaker
Dom DeMarco
Analyst, National Bank

Thank you, operator. And good morning, Darren and team. My first question has to do with de-risking of mining in year one. You know, it's great to see that the build is coming along nicely, but now looking beyond the build, can you remind us of the reconciliation drilling in the pits that are planned to be mined in the first year?

speaker
Moderator
Conference Moderator

Yeah, good morning, Dom, and thanks very much, Bob.

speaker
Darren Hall
President and Chief Executive Officer

Yeah, no, if we look, if we remember back in February, we provided an update on the infill drilling there at Leprechaun, and we saw positive reconciliation results both in tons and ounces, and additionally led us to identify some extensions leading from the southwest of Leprechaun into the Frankstone, which Tom and the exploration team have been following up with infill drilling as well, and we've provided some results, and we look forward to providing some additional results in the very near future. But that being positive, we've been continuing in the background with infill drilling and marathon, and we would anticipate in the next month to two providing an update there as well. But initial results are not disappointing, I'm supposed to say.

speaker
Dom DeMarco
Analyst, National Bank

Okay, thanks. And then shifting to Nicaragua, we saw the press release that you're now mining from the recently permitted Vulcan pit. And there was no adjustment to guidance, but is this sort of on track with your timing, or do you feel that maybe you're into this Vulcan pit a little earlier than expected?

speaker
Darren Hall
President and Chief Executive Officer

No, Don, it's consistent with, as we foreshadowed earlier in the year, that we were H2 weighted. We did have some impacts earlier in the year, which moved some ounces from Q2 into H2. But Volcan was always part of the plan in the second half, and particularly as we lead into Q4. So, no, the encouraging thing here was, again, demonstrating the ability to go from permit to plant very quickly and, you know, or delivery into the plant within a month of permit receipt.

speaker
Dom DeMarco
Analyst, National Bank

Okay. Great. Well, that's all for me. Good luck with the rest of Q3. Thank you. Appreciate it. Thank you very much.

speaker
Operator
Conference Operator

The next question comes from Farouk Hamed with Raymond James. Please go ahead.

speaker
Farouk Hamed
Analyst, Raymond James

Good morning, everyone. Darren, my question is just kind of looking forward at Valentine a little bit. As you get towards the end of the construction and into your startup, which is expected for the second quarter of 2025, the last stages of construction at Valentine seem that they'll be happening through the winter season, particularly Q4 of 2024 and Q1 of 2025. I'm just wondering, given there's probably going to be more challenging weather conditions during that winter season, do you have, can you give us some kind of view on how you want construction to move forward ahead of the winter season? Is there a certain, you know, kind of milestone that you're targeting or certain things you want to get done before the, you know, traditional winter season that might slow things down? Or how are you anticipating operating through that season? Will it just be kind of normal and no real slowdown expected?

speaker
Darren Hall
President and Chief Executive Officer

Yeah, hi, Farouk. I appreciate the question. And good questions as well. I mean, you know, again, the most talked about thing in Newfoundland is the weather. But if we look at where we're positioned as we head into the fall and then into the winter season, the buildings are complete. The major components are on site. Now we have all the crushers, conveyors, sag mills, ball mills being erected. the majority of that work will actually be done prior to the winter. Now, we would anticipate being substantially mechanically complete early in Q4, in advance of the winter. And then additionally, the majority of the work that will be done during the winter will be done undercover, inside the mill. So, no, I think we're actually well positioned given the timing of activities heading into, you know, the January, February timeframe. So, no, with the tailings facility, as I mentioned, we'll be materially complete here in Q3 and we'll be in position to take water. Those civil works will be behind us as well. So, no, I think we're really well positioned.

speaker
Farouk Hamed
Analyst, Raymond James

Okay, that's good. Thanks for that color. Maybe if I can ask a follow-up question that's more strategically focused, and I appreciate that a lot of your concentration and effort right now is focused at the project at Valentine. But if we look a little bit forward and assume that Valentine will start up as expected, going forward, do you see, obviously then you diversify your production base, after that, but going forward, do you see Nicaragua as an area that you would want to continue to consolidate and continue to look for opportunity to acquire new assets, or are you kind of happy with your Nicaragua exposure at this point and would potentially look elsewhere as you potentially look to expand?

speaker
Darren Hall
President and Chief Executive Officer

Thanks, Farouk. An interesting question. And, of course, it gets lots of airplay both at management and with the board. But, you know, if you think about single determined focus right now, it's to continue to deliver in Nicaragua, continue to deliver in Nevada, and above all else is to deliver into expectations with Valentine. And as we just talked about, you know, we're well positioned given the 98% level of engineering we've got complete. The 77% construction complete, being mechanically complete here in Q4, we're positioning ourselves well to deliver into. And anything to distract from those three core activities, in addition to reinvesting in the drill bit for that organic growth, is very destructive. We're open to consider other opportunities, but again, at this time, our focus is explicitly on those aspects of the business. And as we can and look to the future, we'll consider other things. But right now, the team is absolutely myopicly focused on those three aspects of the business.

speaker
Farouk Hamed
Analyst, Raymond James

Okay, thanks for that, Darren, and good luck with the rest of the way on Valentine and looking forward to seeing the project in September.

speaker
Darren Hall
President and Chief Executive Officer

Yes, looking forward to hosting the visit in the first week of September, and it will be great to see you there, and I'm sure you'll walk away feeling pretty positive about what you see, so thanks for it.

speaker
Operator
Conference Operator

Again, if you have a question, please press star then 1. We will now pause momentarily to assemble our roster. Seeing no further questions, this will conclude our question and answer session. I would like to turn the conference back over to Darren Hall, President and CEO, for any closing remarks.

speaker
Moderator
Conference Moderator

Thanks, Operator.

speaker
Darren Hall
President and Chief Executive Officer

I'd like to thank all of our shareholders for their continued support in your participation and questions this morning. As always, Ryan, I, and the entire leadership team are available if you have any further questions. And with that, I'd like to wish everyone a wonderful and safe day. Back to you, Operator.

speaker
Operator
Conference Operator

The conference is now concluded. Thank you for attending today's presentation. You may now disconnect your lines and have a wonderful day.

Disclaimer

This conference call transcript was computer generated and almost certianly contains errors. This transcript is provided for information purposes only.EarningsCall, LLC makes no representation about the accuracy of the aforementioned transcript, and you are cautioned not to place undue reliance on the information provided by the transcript.

-

-