11/6/2024

speaker
Operator

Thank you for standing by. My name is Dee, and I will be your conference operator today. At this time, I would like to welcome everyone to our zone Q3 2024 results webcast and conference call. All lines have been placed on mute to prevent any background noise. After the speakers remarks, there will be a question and answer session. If you would like to ask a question during this time, simply press star followed by the number one on your telephone keypad. If you would like to withdraw your question, press star one again. Thank you. I would now like to turn the call over to Patrick Toney, president and CEO. Please go ahead.

speaker
Patrick Toney

Thank you, and welcome to the Q3 OZONE webcast and conference call. With me today will be Peter Tam, EVP, and chief financial officer who will run through most of the financial and operation metrics. Standard disclaimer, so please read this as you go through this presentation or afterwards. So quick summary of where we're at today. Obviously, we built our oxide plant. It was designed for 5.2, currently running at a run rate of 5.9 million tons per annum, expected to run up to around 6 million tons per annum, so running extremely well. We're in the next stage of our expansion, which will bring us up to over 170,000 ounces a year, which is a 2.5 million ton hard rock plant. The project financing is secured. Our construction has commenced, and I'll update you on that, with first goal expected in late 2025. And very excitingly, we really believe we're on a tier one potential here, which is a very large orogenic system, 14 kilometers, a strike extent. Drilling has started on a multi-year program. The first results were extremely robust, and we'll walk through that a little later on in the presentation of what next steps are in that regard as we continue to expand this operation. So Q3 highlights, very good quarter in terms of health and safety, zero LTIs, 1.31 million hours worked during the quarter, and 3.68 million hours worked year to date. Again, a testament to the system and the team down there in Bombore. A production was ,851,000 ounces. A record throughput through the mill of 1.5 million tons, which is at a run rate of 6 million tons per annum, even though we had a four day mill shutdown, including a full ball mill reline in late September. The oil and sustaining costs were affected somewhat by heavy rainfall events, really, this time, which restricted access to the higher grades in the south, which meant that we had to process some lower grade stockpiles during the quarter, and also impacted by the higher oil needs due to the higher gold price. Very robust in terms of the balance sheet, $67 million in cash at the end of the quarter, $68 million of senior debt. In that quarter, we also advanced all of our capital projects, including the Hard Rock expansion, and we'll walk you through what we spent during the quarter later on. We paid down an additional $5 million in senior debt, and we did add significant cash to the balance sheet during the quarter. Our Hard Rock expansion, as I stated, is well underway. Project financing announced on July the 10th. Our first goal is expected in Q4 of 2025, and that will increase our throughput by approximately 50%. And our expiration program, first two holes, were up to 240 meters below the Life of Mine Reserve pit. There were big swings, and we'll walk you through that, but we're very excited about our expiration potential as we continue to expand the reserves and resources on the project. Our three-year production forecast, our four-year guidance remains at 110 to 125,000 ounces, slightly revised, all in sustaining cost of 1,400 to 1,475, and then strong production growth into 2025, 2026 of 170,000 ounces a year run rate, and then continue beyond that into stage two. Hopefully, we can bring that forward in the timeline to 225 to 250,000 ounces, and our focus will be on the leverage of the balance sheet, continuing to build a strong treasury, and a renewed focus on exploration. I'll now hand you over to Peter Tam, who will go through the operational financial highlights. All right,

speaker
Peter Tam

thanks, Patrick. On financial and operating highlights, the goal production in Q3 rose slightly quarter over quarter to 26,581 ounces as mining progressed south into Seagate East and Seagate South. Mining is projected to ramp up in Q4 with more ore from the Seagate pits, which should help drive better fourth quarter goal production, as evidenced by the 12,096 gold ounces produced in October. All in sustaining cost per ounce remain elevated in Q3 at $1,655 per ounce, driven by higher strip ratios due to mine sequencing, and from the drawdown of lower grade stockpiles in August as heavy rainfall events and pre-stripping at Seagate South temporarily affected the volume of ore mined from the pits. Furthermore, government royalties, which are calculated on a sliding scale, rose in tandem with record gold prices. The company's board officially approved the Bonnebury Mine phase two hard rock expansion in early July, leading to 6.2 million in expansion expenditures in the third quarter. Additional expenditures are expected in the fourth quarter as the company rapidly moves forward with engineering and procurement towards achieving first goal by Q4 of next year. With the help of strong goal prices, the company was able to generate free cash flow of 14.1 million in Q3. The company exited the quarter with a healthy cash balance of 66.9 million, and is expected to continue to generate free cash flow for the remainder of the year. The phase two expansion as mentioned earlier remains fully funded. Next slide, on production and unit costs, notable highlights. Mining, as noted earlier, commenced at both Seaga East and Seaga South in Q3, and began to only contribute meaningful ore volumes in September. The mining contractor struggled to keep up with the mine plan in Q3 due to low equipment availability and wet ground conditions from heavy rainfall events, resulting in a mining of only 4.1 million tons for the quarter. Mining rates are expected to jump in Q4 as new heavy duty excavators and haul trucks are placed into service by the mining contractor at the beginning of November. Mining cost per ore ton process rose in Q3 to $9.58 per ore ton from the higher strip ratio and unit mining cost, both of which are expected to fall in Q4 as the strip ratio normalizes and less drill and blast and higher mining volumes help lower mining costs on a per ton mine basis. For processing, mill throughput is expected to reach another record in Q4, as no major maintenance is planned and grid availability is forecasted to remain stable. Head grades will see an improvement as higher grade ore from the Seaga pits make up a greater percentage of the mill feed in Q4. Processing cost per ton processed on expected decline and power costs of grid utilization improved significantly in Q3 to 92%. However, processing costs and throughput were impacted in the quarter by the mill reline and other maintenance activities. Unit processing costs are expected to be lower in Q4 as well from less estimated plant downtime in the evening. With that, I'll hand it back to you Patrick.

speaker
Patrick Toney

Thanks Peter. So just into 2024 production and cost guidance, our gold production guidance remains unchanged. We expect to be around the middle, just above the middle of that guidance for the year. All in sustaining costs have been revised to 1400 to 1475, a slight revision there. That's mainly attributed to the higher power costs we experienced in the first half of the year due to low grid availability, which was experienced throughout the region and affected several mining operations in the region. We have seen significantly better availability and in fact, most recently we've been around 95 to 100% availability on the grid. It was also affected by higher government royalties due to the better realized gold price, currently calculated around $40 an ounce. Really mostly the guidance is affected by outside of the operations itself. Sustaining capital remains unchanged at 14 to $15 million for the year. Growth capital excluding the phase two expansion remains unchanged at 16 to 17. The growth capital which no guidance was provided because we weren't really into it before the start of the year. The early works, approximately 3.6 which are now complete and the growth capital of between 15 to 18 million which I'll walk through later on in the presentation that will be for the year, we're guiding for the year based on current activities on the project. Into the hard rock expansion and our exploration update. On our 2.5 million tonne per annum hard rock expansion, I'm extremely pleased with progress to date, estimated capex of 85 million which is fully financed. The early works is complete. 100% of the process equipment has now been procured so we know all of their costs therein. The concrete contract was awarded and mobilization has commenced three months ahead of schedule. Our tank plate work has been awarded. We expect to award the structural mechanical piping contract later this quarter. We've received a first delivery of the hard rock mining fleet which is being used currently on the oxide and as Peter said is giving us better availability which will continue on through Q4 into 2025. And the major works on the project will commence in Q4 of 2024 with first gold expected in Q4 2025. Just a quick pictorial and we will do a monthly video updates here as we go forward as we did on the oxide. As you can see the oxide plant on the left hand side. The CIL tank platform is now complete. The lay down area for the contractors is in place to the top end of that photograph with the contractors for the concrete in place, the batch plants there so we expect to start pouring concrete this quarter. And the rest of the earthworks are complete for commencement of works in Q4 and into 2025. So very pleased with progress to date on the hard rock expansion. As you know this is a 14 kilometer strike extent. We really have not drilled a lot to any depth on this project. We've got a 2.4 million ounce reserve delineated along that strike. Average pit depth of 40 meters and essentially .1% or less than .1% of being between 250 to 300 meters of the holes drilled on this project. So really totally underexplored even at medium depth. So our exploration is really focusing on expanding that. The first two holes which we'll show you along sections BB and AA here which is the first pitch to the north. It's really not our highest priority target but we're starting in the north and working our way down and they were extremely successful. We took big swings here on an orogenic system. Normally you would take 40 to 50 meter type of swings. We took 200 meter swings down at depth and very successful. We really wanted to prove the robustness of the system. So looking southeast along section BB of that previous slide you can see we're down now 240 meters below the reserve pits. Thicker, very good grade ore. We're moving to the north and south of that right now. We should have results from there later this month. As I said, this is our first target. We believe it's not even our best target so we're very excited about this. On the next side along section AA, the long section, you can see where we are there below those reserves and resource pits. The dark blue is the reserve. The light blue is the resource. So you can see where this really would expand this down to 320 meters. And we have now drilled to the north and to the south of that which would really take a 600 to 700 meter strike extent along that first section. And we will release those hopefully in the next couple of weeks here to really show the robustness of this project and where it can go. Obviously if this continues to provide the results that we expect, we do not expect to be mining at 2.5 million tons for the next 40 to 50 years. We would like to make this a very large robust project in the five to seven million ton per annum range which will be our goal here in the coming months and years. And that concludes our Q3 presentation and I'll now hand it back to the operator.

speaker
Operator

Thank you. At this time, I would like to remind everyone in order to ask a question, press star, then the number one on your telephone keypad. We will pause for just a moment to compile the Q&A roster. Our first question comes from a line of Bryce Adams from CIBC. Please go ahead.

speaker
Bryce Adams

Hi

speaker
Bryce

there, thanks all for the presentation. Since you... Sorry. Since you reported the October production which looks pretty strong, can you say what the grade profile was in October and should we take that October number and then triple it for Q4 production expectations?

speaker
Patrick Toney

The grade was higher because we're in the south around 0.81 I think. We do expect to be up in that range, maybe not 0.81 throughout the quarter because we will be mining from other areas continuing in the north. But yes, we do expect quite robust production. The other thing that you will expect Bryce is we will not have the same stripper issue because we have stripped off that area in the south as well. We actively stripped that during Q1 when we could do it during the rainy season. We weren't totally affected by that. And the other thing is we will not be having drill and blast which also affected the costs in Q1. But yes, I expect a fairly very robust quarter in Q4.

speaker
Bryce

Thanks, Patty. Sounds like a lot of operational momentum into year end. That's all I had, all the best for the phase two expansion.

speaker
Patrick Toney

Yeah, very much so. That was always the case price. We expected it to be stronger in Q4.

speaker
Operator

Our next question comes from the line of Jeremy Hoy from Kanakora Genuity. Please go ahead.

speaker
Jeremy Hoy

Hi Pat and Peter. Thanks for taking my questions. Appreciate it. First question is on the expansion. In the last update, you guys mentioned some pretty significant savings from purchasing the previously owned mill. Are you guys able to quantify that at all and how that impacts the overall Catholics of the project?

speaker
Patrick Toney

Well, on the equipment, we're very much in line on budget, maybe a bit below. We really have to see the structural mechanical piping which will be the main contract. That will really tell us where we're trending. We don't expect, we're not dipping into any contingency even with the contract award. We expect to award the plate work pretty soon here. So we're pretty happy with that. So we generally do a detailed update at a certain point through the project which will likely be in January, February and we'll update everybody at that time.

speaker
Peter Tam

Jeremy, I will add the figure that we provided in terms of the phase two expansion did take into consideration that we were buying this pre-owned used but really never placed in service mill. So that's been factored into their figure and we're tracking towards that number. Yeah, and the other thing is what it does

speaker
Patrick Toney

is that mill will be delivered to site this year. So it'll be sitting on site ready to go which is a big part of the schedule in terms of getting things moving forward. We're not gonna be waiting for the mill to be delivered.

speaker
Jeremy Hoy

God, okay, no, that's really helpful, thank you. Another question is on the stage two of the Hard Rock expansion. What's your latest thinking on when you'll inform the market on a potential decision on the additional expansion for the Hard Rock?

speaker
Patrick Toney

We're looking at that carefully right now actually in terms of what we may want to do in 2025 to pull some of that stuff forward. Obviously, well, today maybe not but 30 robust gold prices out there. We're putting cash on the balance sheet. We're obviously drilling to show that it's bigger and better. So there's no point in waiting two, three years to do an expansion which is sitting in front of us. So if things continue the way they are, we will likely look to bring that forward here and maybe update the market sometime in 2025 in that regard.

speaker
Jeremy Hoy

Okay, that's great to know. And I guess the last one I had is on the Jensor claim. What is the timing of the potential conclusion of that and can you remind us what the claim was for, the amount?

speaker
Peter Tam

Yeah, so Jeremy, we're right in the middle of that obviously in terms of the arbitration proceedings. I think it'll come to a conclusion sometime within the first half of next year. We obviously are pursuing significant damages against Jensor for the fact that we were not delivered the fixed price low cost rate tariff that we would have been enjoying under the power purchase agreement that was signed originally with Jensor. So there's that aspect of the claim as well as obviously additional cost to obviously run our power plan on diesel until we got onto the grid. And there is also a slight differential between the grid cost and what we would have otherwise enjoyed under the power purchase agreement. So when you wrap all that in, it's a multimillion dollar damage claim that we are going after Jensor for. I won't get into the details obviously in terms of just the fact that we are in the midst of this arbitration, but suffice to say, we're looking for significant damages here.

speaker
Jeremy Hoy

Okay, fair enough, that's a great caller. Appreciate it, Pat and Peter, thanks very much.

speaker
Patrick Toney

Okay, thanks Jeremy.

speaker
Operator

Our next question comes from the line of Alex Therentil from Venture Financial, please go ahead.

speaker
Alex Therentil

Hey, good morning everyone. Great to see some good operational progress being made that we should see start being delivered in Q4. Two remaining questions for me. First, just on the Coors Bank loan, it was originally signed I believe in July, you're guiding towards closing that remaining 58 million available to you this month. I just wanted to just double check, make sure there's, you know, are there any sticking points there that we should be worried about, or just kind of a procedural item that's taking its time to get through?

speaker
Peter Tam

Yeah, Alex, you hit the nail on the head there, really it's just sort of taking its time, you know, things that there are intercreditor consents we've also got to work through. So it's a matter of just sorting through all that. Obviously with the raise that we did back in August, with the strong cash generation that we've been able to obviously create in Q3, you know, we've been able to fully fund the expansion expenditures without affecting in any way that the schedule or on the expansion. So it's just a matter of really working through the final steps now, and we do expect to get that concluded here before the end of the month here.

speaker
Alex Therentil

Okay, okay, that's good to hear. And then just last one, you know, some talks about, you know, resources and the phase two, stage two expansion. But when do you think we could see a resource update on the sulfide? Obviously you're doing some drilling there, gold prices are a lot higher, there's simple revisions that could be made just by incorporating higher gold prices, but what do you think, we could see timing on that front?

speaker
Patrick Toney

Yeah, great question, Alex. Well, first of all, when we looked at this, we did quite a bit of work both internally with what we'd seen on our own drilling, looking at a lot of data, bearing in mind a lot of our stuff is in oxide, so you can't see structure. We had a structural review done by an independent structural geologist last year. We brought that all into the frame, and these holes we drilled. I mean, normally you would not drill a 240 meter hole. You're gonna drill a 40 or 50 step out and then look beyond that. So we'll put out some more results here. What we want to do, now that we're pretty confident about where we're seeing this model and what we're seeing happening here, is we'd like to add two to four more rigs on this project in 2025. And really drill it off very, very fast, and we'd like to do an update on the resources and reserve by the end of next year. You're right, just to state, our reserves were done at 1500, our resources were done at 1700. Obviously, we will update all of that, bearing in mind the gold price environment. But when you're going from 200 meters below reserve pits and still hitting bigger and thicker intervals, you obviously really want to outline what we believe this is. And we firmly believe this is a seven to 10 million ounce deposit, and that will really set the sort of pipeline for how we want to expand this going forward.

speaker
Alex Therentil

Okay, sounds good, thank you. But the

speaker
Patrick Toney

critical factor is, we're gonna do more drilling next year, a lot more drilling, and we're gonna do it fast.

speaker
Bryce Adams

Good, good to hear.

speaker
Operator

Again, if you would like to ask questions, press star one on your telephone keypad and wait for a name to be announced. Our next question comes from the line of Sean Fieler from Equinox Partners, please go ahead.

speaker
Sean Fieler

Hey, Patty. Hey, Sean. Let's see, your tax is receivable, that's mainly VAT, up at $34 million at the end of the quarter. And when and where do you expect that to peak out before it starts declining?

speaker
Patrick Toney

We are in discussions right now with government officials, so there is movement in that regard, Sean. Latest meeting was yesterday, which based on what I saw was quite positive. We do hope to see a start of reduction of that by the end of this year, going into next year. So that's essentially what we're hearing. When I get the first check, that's when I know I'm getting it. But this is what we have heard, and the meetings have been fairly productive here going forward in terms of VAT receivables.

speaker
Sean Fieler

So does that, hopefully you get a reduction in it, but is it gonna not keep growing? Is that?

speaker
Patrick Toney

It grows, it grows a little higher with the VAT on the expansion, so the rate is higher, Peter, maybe you could

speaker
Peter Tam

comment? Yeah, so obviously we are continuing with our phase one, oxide operation. Once we do ramp up spending in country on the expansion, obviously there will be VAT on those expenditures as well. So for 2025 and really for Q4 this year, we will be paying more VAT than we normally would. So the refunds we are hoping to receive are from earlier months in 2023 and the last quarter of 2022. So it's hard to predict obviously the size and the timing of the refund. So in terms of whether our VAT receivable will sort of stabilize or whether it's gonna continue to grow, I would say at this point it's hard to predict. We'll probably have more visibility in the next quarter, hopefully as we get our first set of refunds back from the government.

speaker
Bryce Adams

Thanks.

speaker
Operator

I will now turn the call back over to Patrick Donnie for closing remarks.

speaker
Patrick Toney

Okay, thank you. And thank you everyone for attending. As we said, we look forward to a strong Q4 in terms of production and costs and into 2025, expanding both our expiration and our phase two expansion. So we will be updating everybody on that on a consistent basis throughout this quarter and through 2025. Thank you.

speaker
Operator

Ladies and gentlemen, that concludes today's call. Thank you all for joining. You may now disconnect.

Disclaimer

This conference call transcript was computer generated and almost certianly contains errors. This transcript is provided for information purposes only.EarningsCall, LLC makes no representation about the accuracy of the aforementioned transcript, and you are cautioned not to place undue reliance on the information provided by the transcript.

-

-